Small Generator Interconnection System Impact Study Report. Completed for Q0373
|
|
- Magdalene Adams
- 5 years ago
- Views:
Transcription
1 Small Generator Interconnection Completed for Q0373 Proposed Interconnection To the Existing Q kV substation on the 13.8kV side of the bus July 7, 2011
2 TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING FACILITY SCOPE OF THE STUDY DESCRIPTION OF PROPOSED INTERCONNECTION STUDY ASSUMPTIONS REQUIREMENTS GENERATING FACILITY MODIFICATIONS TRANSMISSION MODIFICATIONS EXISTING BREAKER MODIFICATIONS SHORT-CIRCUIT PROTECTION REQUIREMENTS DATA REQUIREMENTS (RTU) COMMUNICATION REQUIREMENTS For LINE Protection For Data Delivery to the Control Centers SUBSTATION REQUIREMENTS METERING REQUIREMENTS COST ESTIMATE SCHEDULE PARTICIPATION BY AFFECTED SYSTEMS APPENDICES... 8 Q373 Page 1 July 7, 2011
3 1.0 DESCRIPTION OF THE GENERATING FACILITY Interconnection Customer proposed interconnecting 5 MW of new generation to PacifiCorp s ( Transmission Provider ) switch 11L16 (Q0006 Meridian 500kV transmission line) and to the Transmission Providers switch 11L34 (Q0006 Captain Jack 500kV transmission line) through the existing Interconnection Customer Q kV substation on the 13.8kV side of the Q0006 bus. The Project is located in Klamath County, Oregon and will consist of 10 SMA Sunny Central 500HE inverters for a total output of 5 MW. The requested commercial operation date is approximately March 1, The Interconnection Customer will not operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Transmission Provider has assigned the project Q SCOPE OF THE STUDY The may consist of a short circuit analysis, a stability analysis, a power flow analysis, voltage drop and flicker studies, protection and set point coordination studies, and grounding reviews, as necessary. These studies were deemed not necessary by the Transmission Provider for the Q0373 interconnection. The System Impact Study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested interconnection service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. The System Impact Study shall provide a list of facilities that are required as a result of the Interconnection Request and non-binding good faith estimates of cost responsibility and time to construct. A stability study will not be performed because the project is less than 10 MWs. 3.0 DESCRIPTION OF PROPOSED INTERCONNECTION The Project s proposed interconnection is located on the Transmission Provider s switch 11L16 (Q0006 Meridian 500kV transmission line) and on the Transmission Providers switch 11L34 (Q0006 Captain Jack 500kV transmission line). Metering and associated communication equipment will need to be installed at the Q0373 generation facility as well as at the 901 and 902 units. Figure 1 is a one-line diagram that illustrates the interconnection of the proposed generation facility to the Transmission Provider s system. Q373 Page 1 July 7, 2011
4 Figure 1: Simplified System One Line Diagram Q373 Page 2 July 7, 2011
5 3.1 STUDY ASSUMPTIONS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change. For study purposes there are two separate queues: o Transmission Service Queue: to the extent practical, all network upgrades that are required to accommodate active transmission service requests and are expected to be in-service on or after the Interconnection Customer s requested in-service date for the Project will be modeled in this study. o Generation Interconnection Queue: when relevant, interconnection facilities associated with higher queue interconnection requests will be modeled in this study. However, network upgrades required to provide delivery will only be modeled for projects which have requested network resource integration service only or qualified facility status. No generation will be simulated from any higher queued project unless a commitment has been made to obtain transmission service. The Interconnection Customer s request for interconnection service in and of itself does not convey transmission service. This study assumes the Project will be integrated into Transmission Provider s system at the agreed upon and/or proposed point of interconnection. Unless otherwise specified, the Interconnection Customer will construct and own the any facilities required between the point of interconnection and the Project. Generator tripping may be required for certain outages. All facilities will meet or exceed the minimum WECC, NERC, and Transmission Provider performance and design standards. Q373 Page 3 July 7, 2011
6 4.0 REQUIREMENTS 4.1 GENERATING FACILITY MODIFICATIONS The Interconnection Customer shall design its generating facility to operate reactive compensation, typically located at the collector station, under voltage control mode with the voltage sensed electrically at the point of interconnection, and to have sufficient reactive capacity to enable the facility to deliver 100 percent of the plant output to the point of interconnection at unity power factor measured at 1.0 per unit voltage. The voltage control shall be designed to include a voltage control band, nominally set to 1.01 and 1.04 per unit (actual voltage band may be adjusted depending on typical voltage at the interconnection or other area local conditions), such that if the actual voltage is above the upper band setting, capacitor increments will be automatically removed and if the actual voltage is below the lower band setting, capacitor increments will be automatically be added. The control scheme should be designed so as to avoid hunting when switching between modes (i.e., effectively power factor control inside the band, voltage control outside the band). Inside the voltage bandwidth, the facility shall operate as much as possible to a unity power factor. Settings must be coordinated with the Transmission Provider who may, from time to time, request changes in response to operating conditions or actual operating experience. The reactive compensation must be designed such that the capacitor switching does not cause step voltage changes greater than +/-3% on the Transmission Provider s system. 4.2 TRANSMISSION MODIFICATIONS There are no transmission modifications required for the Q0373 Project. 4.3 EXISTING BREAKER MODIFICATIONS SHORT-CIRCUIT The increase in the fault duty on the system as the result of the addition of the generation facility with photovoltaic arrays fed through ten (10) 500kVA inverters and five 1000kVA 13.8kV 270V transformers with 4% impedance will not push the fault duty above the interrupting rating of any of the existing fault interrupting equipment. 4.4 PROTECTION REQUIREMENTS The existing transmission line protection will continue to response to faults on the Transmission Provider s system. The Interconnection Customer shall install facilities to detect faults and isolate the new facilities from the existing generation facilities at this site. Q373 Page 4 July 7, 2011
7 4.5 DATA REQUIREMENTS (RTU) The Transmission Provider has as a RTU at the Q0006 substation. As part of this project the following quantities will need to be added to that RTU: Analogs: Real power from the PV 13.8kV collector line Reactive power flow from the PV 13.8kV collector line Accumulator Pulses: Interchange metering kwh from the PV 13.8kV collector line Status: 13.8-kV breaker for the PV collector line 4.6 COMMUNICATION REQUIREMENTS For LINE Protection No additional line protection communication is required For Data Delivery to the Control Centers The Transmission Provider will install a Loop 3440A channel bank equipped with digital channel cards at the Q0006 substation. DNP 3.0 protocol outputs from the three new interconnect backup meters will be routed to the channel cards, through fiber-optic modems if necessary. The channels will be bridged to a new digital SCADA comm line in Transmission Provider s Medford Digital Cross-Connect System. The primary meter outputs will be wired to the Transmission Provider s existing GE D20 RTU in the Q0006 substation. The Transmission Provider will install a data concentrator in the Q0373 generation facility. The Transmission Provider will install Multimode fiber-optic cable between the Q0373 generation facility and the existing Q0006 substation. Fiber optic modems will enable the data concentrator to communicate with the Transmission Provider s channel bank in the Q0006 substation. A circuit will be routed to Transmission Provider s EMS system carrying the data concentrator circuit. The Interconnect Customer will provide a dial-up circuit for meter remote interrogation in the generation facility. 4.7 SUBSTATION REQUIREMENTS No addition Transmission Provider substation work was identified for this portion of the project. Q373 Page 5 July 7, 2011
8 4.8 METERING REQUIREMENTS Stand alone revenue metering will be installed at the Q0006 substation on the 13.8kV side of the transformer to measure the net output of the Interconnection Customers Q0373 project. Two revenue grade meters (primary and back-up) will be installed on a panel in the Interconnection Customers control house. The primary and backup meter will be used for SCADA which will include: bi-directional MWH and MVARH quantities, MW, MVAr, and per phase volts and amps. Both meters will provide these quantities to the existing RTU at the Transmission Provider s control house in the 500kV yard via a DNP3.0 signal or ma analog signals and KYZ outputs. The current transformers must be 0.15% metering grade accuracy and be dedicated solely for metering. The voltage transformers will be connected in a WYE configuration. A single land line must be installed for MV90 communications, which can be used for all the meters. Digital or analog output signals from the meter can be provided to the Interconnection Customer, but must be requested before final designs are complete. The existing net metering for the 901 and 902 units is on the high-side of the GSU. With the addition of the Q0373 project on the low side of the GSU, two new metering points will be required to capture the net generation. In addition to the metering required for the Q0373 Project, one meter for the 901 unit and one meter for the 902 unit will also be required. A primary and back-up meter will be installed on a panel for each unit. Each meter will be used for SCADA which will include: bi-directional MWH and MVARH quantities, MW, MVAr, and per phase volts and amps. Both meters will provide these quantities to the new data concentrator and then to the existing RTU at the control house in the 500kV yard via a DNP3.0 signal or ma analog signals and KYZ outputs. MV90 communications will be required for each meter, which will require a dial up land line. Q373 Page 6 July 7, 2011
9 5.0 COST ESTIMATE Costs for all excavation, duct installation and easements shall be borne by the Interconnection Customer and are NOT included in this estimate. This estimate is as accurate as possible given the level of study that has been undertaken to-date and approximates the costs incurred by the Transmission Provider to interconnect this generator to Transmission Provider s electrical transmission system. The Interconnection Customer will be responsible for all actual costs, regardless of the estimated costs communicated to or approved by the Interconnection Customer. A more detailed estimate is calculated during the Facilities Study. Direct Assignment Costs Q0006 substation - Engineering, procurement and installation of communication equipment. $ 64,000 Q0373 Generation Facility - Engineering, procurement and installation of communication equipment. $78,000 Q0006 and Q0373 Generation Facilities - Engineering, procurement and installation of metering equipment. $340,000 Subtotal Direct Assigned $482,000 Network Upgrades Costs Klamath substation Engineering and installation of communication upgrades. $ 15,000 Medford Service Center Engineering and installation of communication upgrades. $ 10,000 Portland Control Center Engineering and installation of communication upgrades. $ 5,000 Subtotal Network Upgrades $ 30,000 Estimated Total Project Costs $ 512, SCHEDULE At this time, it is estimated that the upgrades required to place this project in service could be completed within 12 months of a signed interconnection agreement. Further details regarding the schedule will be available through the Facilities Study when a more detailed estimate has been prepared. Q373 Page 7 July 7, 2011
10 The schedule is driven by the date that the Small Generator Interconnect Agreement is signed. Changes in this date affect the entire schedule. Please note this timeframe does not support the Interconnection Customer s requested in-service date of March 1, PARTICIPATION BY AFFECTED SYSTEMS Transmission Provider has identified the following entities as having affected systems based upon the interconnection of the proposed generation facility. A copy of this report will be shared with the identified Affected Systems: Bonneville Power Administration 8.0 APPENDICES Appendix 1: Higher Priority Requests Q373 Page 8 July 7, 2011
11 APPENDIX 1: HIGHER PRIORITY REQUESTS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are identified below. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change. Transmission/Generation Interconnection Queue Requests considered: QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Commercial Operation (GI) MW 1 9/1/2000 West N/A Wallula Substation, 230 kv 6/1/ /31/2001 West N/A Distribution Connect, Near Murder Creek Substation, 12 kv 6/1/ /16/2001 West N/A Roseburg Lumbar Substation, 69 kv /20/2001 West N/A Meridian-Captain Jack Line 500 kv 9/1/ /25/01 West GEN Meridian-Captain Jack 500kV 11/15/ /21/01 West GEN Walla Walla- N.Lewiston 230kV 11/1/ /21/01 West GEN Walla Walla- N.Lewiston 230kV 11/1/ /08/01 West GEN Wallula 230kV 12/21/ /08/01 West N/A Walla Walla Central - Pendleton Line, 69-kV 12/22/ Q373 Page 9 July 7, 2011
12 39 03/09/04 West GEN Tieton 115kV 9/6/ /28/04 West GEN Tieton 115kV 9/6/ /05/05 West GEN 54 04/21/05 West GEN Line 66, Iajkabd- Winchester Segment, 115kV 9/13/ kV Line in Weed, CA 7/1/ /30/05 West GEN /09/05 West NT 68 12/28/05 West NR w/er Santiam- Hazelwood Lyons, OR 11/1/ Hermiston (from BPA) Ponderosa 25 JC Boyle Hydro Plant Sub, 230kV 6/22/ /17/06 West 75 04/21/06 West NR 97 10/16/06 West N/A 99 10/20/06 West N/A Three Mile Road, Boardman Oregon 7/15/ Clearwater Switching Station, 115Kv 3/7/ Near O'Brian Substation, 12.47kV 2/18/ Distribution Feeder 4M100, 20.8kV 2/26/ /07/06 West N/A Substation, 69kV 2/23/ /07/06 West N/A Substation, 69kV 2/23/ S/3.3-W /07/06 West N/A Substation, 69kV 1/7/ /07/06 West N/A Substation, 69kV 2/23/ /07/06 West N/A Substation, 69kV 1/7/ Q373 Page 10 July 7, 2011
13 108 11/28/06 West N/A Rocky Point Feeder near Running Y sub.48kv 8/18/ A 12/12/06 West ER Union Gap- Midway, 230kV 8/15/ B 12/12/06 West ER /17/07 West NT Union Gap- Midway, 230kV 11/1/ PACW (Resource) PACW 01/01/ /16/07 West NR Talbot Switchyard near Dayton, WA 8/1/ /12/07 West N/A Deschutes, OR 5/14/ a 07/02/07 West N/A Substation, 69kV 1/11/ b 07/02/07 West N/A Substation, 69kV 1/11/ /02/07 West N/A Substation, 69kV 1/11/ /02/07 West N/A Substation, 69kV 1/11/ /03/07 West NR w/er /16/07 West ER Wallula - Hatrock, 230kV 10/1/ PAC's 115 kv system on Line 40 from White City to Vilas Road 2/3/ /06/07 West N/A Marion, OR TBD /08/07 West N/A Marion, OR TBD /05/07 West N/A PAC's 20.8 kv Sunset Feeder 4M182 out of Hillview Substation 7/9/ Q373 Page 11 July 7, 2011
14 176 12/26/07 West N/A Linn County, OR 6/17/ /09/08 West NR w/er 500 kv Burns Reactor (Oregon) 12/1/ /09/08 West NR w/er 500 kv Burns Reactor (Oregon) 12/1/ /09/08 West NR w/er 190 1/11/2008 West N/A 193a 1/28/2008 West NR w/er 193b 1/28/2008 West NR w/er 197 2/18/2008 West N/A 500 kv Burns Reactor (Oregon) 12/1/ Chiloquin - Mile Hi 115 KV, Line 61 7/1/2012 PAC's 500 kv Burns Reactor 12/31/ PAC's 500 kv Burns Reactor 12/1/ PAC's 69 kv Arlington Substation 12/1/ /30/08 West NR w/er New Substation on PAC's 230 kv WALA-ENPR line 12/31/ /30/08 West NR w/er New Substation on PAC's 230 kv WALA-ENPR line 12/31/ /23/08 West NR w/er 234 7/1/08 West NR w/er line 5, 69-kV transmission line in Klamath County, OR 10/19/ Walla Wall- Enterprise Line 230 kv 12/31/ Q373 Page 12 July 7, 2011
15 237A 7/31/08 West NR w/er Swift 1 switching station adjacent to Swift 1 12/31/ B 7/31/08 West NR w/er Swift 1 switching station adjacent to Swift 1 12/31/ C 7/31/08 West NR w/er Swift 1 switching station adjacent to Swift 1 12/31/ /12/08 West NR with ER existing 115-kV line between Davis Creek and Mile High substations 10/1/ /14/08 West N/A 69- kv Tumalo Line (Bend-Redmond) south of Deschutes Substation 9/1/ /17/08 N/A West /20/08 N/A West 260 3/3/09 West N/A 261 3/3/09 West N/A Distribution grid along existing Memorial Dr. Fountain Ave kV circuit 5L49 out of Lakeport Substation 3/31/ /6/ Substation, 69 kv 12/30/09 10 Substation, 69 kv 12/30/09 10 Q373 Page 13 July 7, 2011
16 262 3/3/09 West N/A 263 3/3/09 West N/A Substation, 69 kv 12/30/09 10 Substation, 69 kv 12/30/ /29/09 West PTP Walla Walla McNary 01/01/ /11/09 West NR with ER 230- kv Wallula Substation 12/31/ /30/09 West N/A Powerdale Woody Gutherie 69-kV Line 01/25/ /11/09 West PTP Walla Walla McNary 01/01/ /17/09 West N/A 284 8/19/09 West NR with ER Creighton Feeder, 4W8 out of Enterprise Substation 11/01/ kv Lemolo Switchyard 07/21/ /21/09 West N/A 289 9/21/09 West NR with ER 292 9/25/09 West NR/ER /5/09 West N/A 12 kv Yuba Feeder 12/14/ miles past Summer Lake Substation 09/01/ Roseburg Lumber Substation, 69 kv 07/01/ kv Circuit 5P395 05/30/ /13/09 West N/A 12.0 kv Crystal Springs, 5L45 out of Hornet Substation 04/30/ /13/09 West N/A 20.8 kv Aumsville feeder, out of Stayton Substation 08/31/ Q373 Page 14 July 7, 2011
17 /24/2009 West NT BPAT.PACW (BPAP) PACW (Yakama) 8/1/ /27/2010 West NR/ER 319 2/4/2010 West N/A 230 kv breaker ring bus station approx. 5 mi. south of Wallula 230 kv substation 10/1/ Chiloquin - Mile Hi 115 kv, Line 61 7/1/ /26/2010 West N/A /10/2010 West PTP New POR Low side of 12.5kV/277/480V transformer at the end of existing tap line 8/27/ Round Mountain 1/1/ /11/2010 West NT PACW PACW (Load) 12/31/ /2/2010 West NT PACW PACW 1/1/ /15/2010 West NT GSHN PACE TBD /13/2010 West N/A 350 9/8/2010 West N/A 351 9/8/2010 West NR 12.5-kV Circuit, 5P123, out of Killingsworth Substation 12/31/ kv line 32 7/1/ line 18, 69-kV transmission line in Klamath County, OR 3/1/ S/39-W 352 9/15/2010 West N/A Knappa Svensen Substation, kv TBD /23/2010 West PTP Summer Lake Hemingway 6/1/ /23/2010 West PTP Midpoint 500kV Hemingway 6/1/ Q373 Page 15 July 7, 2011
18 353 10/7/2010 West N/A kV Distribution line out of Warrenton Substation 12/18/ /12/2010 West NR/ER West Salem -- Dallas 115 kv transmission line in Polk Co., Oregon 12/1/ S/32.5-W /1/2010 West N/A /3/2010 West N/A /3/2010 West N/A 12.5 kv distribution line out of Cave Junction Substation TBD KV Mint circuit, 4M125, out of Jefferson Substation 7/31/ kv Mint circuit, 4M125, out of Jefferson Substation 7/31/ /4/2010 West N/A kV South circuit, 5K74, out of Hood River Substation TBD /9/2010 West PTP Malin230 Malin500 9/2/ /11/2010 West N/A /15/2010 West N/A /15/2010 West NT BPAT.PACW 34.5-kV Sim/Tag circuit, 4K40, out of Dalreed Substation 11/30/ kV Village Green Substation 7/1/ PACW (Load) 1/1/ Q373 Page 16 July 7, 2011
19 366 12/22/2010 West N/A 20.8-kV Circuit 4U30 out of Southgate Substation 10/1/ /21/2010 West NT PACW /11/2011 West PTP M500 BPAT.PACW (Load) 4/1/ Summer Lake 12/1/ /18/2011 West N/A 20.8-kV Circuit 4U38 out of Cloake Substation 10/1/ /19/2011 West PTP BPAT.PACW CRAG 10/1/ /14/2011 West N/A /25/2011 West NT PACW 34.5-kV Sim/Tag circuit, 4K40, out of Dalreed Substation 11/30/ PACW (Load) 3/31/ /25/2011 West N/A kV Culver circuit, 5D5, out of Madras Solar TBD /28/2011 West ER Existing Q0006 Substation 3/15/ Q373 Page 17 July 7, 2011
Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationSmall Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662
Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationLocal Area Studies Update - PACW Kevin Putnam
Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationGeneration Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationFeasibility Study on Load Flow and Short Circuit Project
Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationPacifiCorp Transmission Technical Workshop
PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt
More informationGeneration Interconnection Impact Study Report. For. Interconnection Customer Q0022
Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer
More informationRFP Attachment 13. January 2010
PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationMarch 4, Mona Substation Line position & assoc relaying, communications & metering
700 N.E. Multnomah, Suite 550 Portland, OR 97232 March 4, 2004 Merrill Brimhall PacifiCorp Merchant 201 South Main, Suite 2200 Salt Lake City, Utah 84111 Dear Mr. Brimhall: PacifiCorp Transmission Systems
More informationQ44 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December
More informationTransmission Planning Attachment K Public Input Meeting
Transmission Planning Attachment K Public Input Meeting FERC Order 1000, 2018-19 Biennial Planning Cycle Quarter 2 Meeting June 14, 2018 PAGE 2 Agenda Pacific Time Topic Presenter 9:00 9:05 Greetings and
More informationITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems
ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017
More informationGeneration Interconnection Feasibility Study Report
Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationWECC Criterion MOD-(11 and 13)-WECC-CRT-1.1
WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationColstrip Transmission System. Transmission Service and Interconnection Processes and Procedures
APPENDIX A COLSTRIP TRANSMISSION SYSTEM TRANSMISSION SERVICE AND INTERCONNECTION PROCESSES AND PROCEDURES Colstrip Transmission System Transmission Service and Interconnection Processes and Procedures
More information4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)
A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure
More information4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)
A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved
More informationSMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM
SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the
More informationRequirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company
Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents
More informationSMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2
SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:
More informationISO New England Data Modeling Requirements
A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationATTACHMENT I: Generator Interconnection Procedures (GIP)
ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections
More informationElectric Utility Facility Connection Requirements
City of Coffeyville Municipal Light and Power Electric Utility Facility Connection Requirements Approved: Date: Version Date Change Tracking Reviewer/Editor 1.0 June, 2010 Original document. Steve McGie
More informationNEW ERA METER. Installation & Operation Guide NE METER
NEW ERA METER Installation & Operation Guide NE METER Autoranging Power Supply Installation Diagnostics Per Phase Voltage & Current kwh, Demand and TOU 0.2% Accuracy -40 C to +85 C Watertight Enclosure
More informationSession Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers
Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power 1. Abstract Dinesh Mithanthaya Design Manager, Horizon Power Higher capacity substation power transformers ( 5MVA),are
More informationGrid Interconnection of Renewable Generation
Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection
More informationLegal Name of the Customer (or, if an individual, individual's name):
Instructions An Interconnection Customer who requests a Utah Public Service Commission jurisdictional interconnection must submit this Interconnection Request by hand delivery, mail, or delivery service
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationSmart Distribution Technology
Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications
More informationFor the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)
Electrical Company: PacifiCorp For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Designated Contact Person: Robin Moore Address
More informationPower System Network Simulator (PSNsim)
The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment
More informationMONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES
MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES 1. Introduction Real time monitoring and control is necessary to ensure public and employee safety and to protect the integrity
More informationLevel 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW
Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &
More informationOC IEEE IAS/PES Meeting February 21, 2013
San Diego International Airport: Building For The Future, Through Underground Distribution Automation and SCADA OC IEEE IAS/PES Meeting February 21, 2013 1 Presenter: Randy Denton, PE Under Ground Utility
More informationAPPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT
APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT THIS AGREEMENT is made and entered into this day of, 20 by and between [Customer Name (Project Name, QXXXX)], a [Type of company] organized
More informationAPPENDIX B-2. TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES. and SMALL GENERATION FACILITIES
APPENDIX B-2 TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES and SMALL GENERATION FACILITIES Revision: 4.0 12/30/2011 Page 1 of 39 TABLE OF CONTENTS DEFINITIONS A. Scope 1. Ownership 2.
More informationATC Zone 2 Projects Update U.P. Energy Summit
ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project
More informationMetering System and Communication Requirements
Metering System and Communication Requirements Andrew Levitt Sr. Market Strategist MIC Special Session on DER June 20, 2017 Definitions Metering system: includes all components from the meter location
More informationAttachment H: Small Generator (10 MW and Below) Technical Requirements and Standards
Attachment H: Small Generator (10 MW and below) Technical Requirements and Standards Scope Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards The PJM Small Generator Interconnection
More informationSMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)
Attachment 2 Transmission Provider: SMALL GENERATOR INTERCONNECTION REQUEST Designated Contact Person: Address: Telephone Number: (Application Form) An Interconnection Request is considered complete when
More informationINTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM. July 2011 UPDATED STANDARDS
INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM July 2011 UPDATED STANDARDS Rev 9.0 July 2011 2 TABLE OF CONTENTS 1.0 SCOPE AND GENERAL REQUIREMENTS...5
More informationOperations ISO Version: 1.6. Effective Date: 8/02/2018. Fieldwork Guide. Fieldwork Guide
REVISION HISTORY VERSION NO. (Must match header) DATE REVISED BY DESCRIPTION 1.0 6/6/2016 EDAS Created Document 1.1 6/29/2016 EDAS Updates to include all Meter Work and instruction 1.2 8/29/2016 EDAS Included
More informationFacilities Study for XXXXXXXXXXXX 50 MW PV
Final Report on the Facilities Study for XXXXXXXXXXXX 50 MW PV Project No. 67270 July 2012 Facilities Study for XXXXXXXXXXXX 50 MW PV Prepared for Copany El Paso, Texas July 2012 Project No. 67270 Prepared
More informationATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service
Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationKarl Iliev, San Diego Gas & Electric Company
INTEGRATING DER THROUGH DISTRIBUTION SYNCROPHASORS Karl Iliev, San Diego Gas & Electric Company 2002 San Diego Gas and Electric Co. and Southern California Gas Company. All copyright and trademark rights
More informationAutomate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control
Welcome to NovaTech Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control Paul Grabowski About the Author Paul Grabowski
More informationAdvanced Protection and Control Technologies for T&D Grid Modernization
Advanced Protection and Control Technologies for T&D Grid Modernization i-pcgrid Workshop San Francisco, CA March 31, 2016 Jeff Shiles, Principal Manager Protection & Automation Engineering Southern California
More informationGlencoe Light and Power
Glencoe Light and Power REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS 1 Table of Contents Page I. INTRODUCTION...5 A. Authority... 5 B. Objectives...5 C. Interconnection
More informationJanuary 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.
California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California
More informationTECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM
TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM Version 1.2 May 28, 2009 Transmission Planning Department Revisions Rev. No. Date Description By Approval 1.0 8/10/06
More informationSTCP 04-3 Issue 005 Real Time Data Provision
STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More informationWhat You Should Know About Communication Systems: Business Strategies and Options
Doug Voda, PPMV Global Segment Leader for Smart Grid February 2015 NRECA TechAdvantage What You Should Know About Communication Systems: Business Strategies and Options The visionary Smart Grid Five Pillars
More informationCalifornia lndependent System Operator Corporation Compliance Filing Docket No. ER
The Woshington Harbour 3000 K Street, N.W., Suite 300 Washington, D.C. 20007-51 16 Phone 202.424.7500 Fox 202.424.7647 January 3l.2005 The Honorable Magalie R. Salas Secretary Federal Energy Regulatory
More informationJEA. Facility Connection Requirements
JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities
More informationStudies Overview and Data Requirements. Robert Pan
Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application
More informationDistributed Generation Requirements Update
Distributed Generation Requirements Update Toronto Hydro has updated its real time monitoring and control requirements for Distributed Generation facilities. The latest version of the Distributed Generation
More informationHigh-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY
S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are
More informationCAISO RIG Acceptance Test Procedure
CAISO RIG Acceptance Test Procedure TABLE OF CONTENTS 1.0 PURPOSE... 3 2.0 INTRODUCTION... 3 3.0 TEST PROCEDURE... 8 Market Services/ EDAS CAISO Public Revision History 1.0 PURPOSE The procedure is intended
More informationSPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5
Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System
More information1 Description of Methodology for Volt / Var Optimization
Methodology for Volt / Var Optimization on a Substation Basis May 13th, 2011 Version 1.7 1 Methodology for Volt / Var Optimization (VVO) on a Substation Basis This use case discusses how the utility will
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationRevision 6.0. Transmission Interconnection Guide
Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview
More informationEvolution of Control for the Power Grid
Evolution of Control for the Power Grid Anjan Bose Washington State University Pullman, WA, USA PaiFest In Honor of Prof. M. A. Pai Urbana-Champaign, IL October 15, 2015 The Past (before 1960s) Hard
More informationLONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL
LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL DISTRIBUTION SYSTEM Revised and Issued March 2003 I.
More informationReal-time Power System Operation. Energy Management Systems. Introduction
1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern
More informationAPPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:
APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd
More informationSMALL GENERATOR INTERCONNECTION REQUEST (Application Form)
SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: _Cleco Power LLC Designated Contact Person: Cindy Guillot Address: P.O Box 70, (2180 St. Landry Hwy) St. Landry, LA 71367
More informationPG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.
Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4
More information(801) Spanish Fork Power. 860 East 4500 South Suite 312 Salt Lake City, UT 84107
(801) 288-4033 info@comlinkls.com Spanish Fork Power 860 East 4500 South Suite 312 Salt Lake City, UT 84107 S P A N I S H F O R K C I T Y Municipal Power Substation Siting & Capital Project Study October
More informationTechnology Innovation Delivering Value to BPA Organized, Disciplined, Focused
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused Keeping the Lights on for the Long Term The Basics Bonneville Power
More informationWESTERN AREA POWER ADMINISTRATION Meter Policy
WESTERN AREA POWER ADMINISTRATION Table of Contents 1. Purpose... 4 2. Scope... 4 3. General Requirements... 5 4. WAPA-Owned Facilities... 6 5. Customer-Owned Facilities... 7 6. New Boundary Meter Installations...
More informationAUTOMATION OF POWER DISTRIBUTION USING SCADA
1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from
More informationMONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS
MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS Table of Contents I. Introduction... 5 A. Authority... 5 B. Objectives... 5 C. Interconnection
More informationGeneration, Transmission, and End User Facilities
Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3
More informationAPPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS. for GENERATION & INTERCONNECTION FACILITIES
APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS for GENERATION & INTERCONNECTION FACILITIES Revision: 4.0 12/28/2011 Page 1 of 40 DEFINITIONS TABLE OF CONTENTS A. Scope 1. Generation Connection and Operating
More informationB O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Loss of EMS:
More informationFacility Connection Requirements
SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationThe current state of the electrical grid And the technologies that will enable its transformation
ABB POWER GRIDS The current state of the electrical grid And the technologies that will enable its transformation IEEE POWER & ENERGY SOCIETY - SUBSTATIONS COMMITTEE May 7-11 th Agenda State of the Industry
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationMemorandum. This memorandum requires Committee action.
California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure
More informationPRC Coordination of Protection Systems for Performance During Faults
PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To
More information