March 4, Mona Substation Line position & assoc relaying, communications & metering
|
|
- Mervyn McKenzie
- 5 years ago
- Views:
Transcription
1 700 N.E. Multnomah, Suite 550 Portland, OR March 4, 2004 Merrill Brimhall PacifiCorp Merchant 201 South Main, Suite 2200 Salt Lake City, Utah Dear Mr. Brimhall: PacifiCorp Transmission Systems has completed the Generation Interconnection Facilities Study ("Facilities Study") pursuant to the October 21, 2003 Generation Interconnection Facilities Study Agreement ("Study Agreement") for Phase I of the Current Creek Generation Project. The Facilities Study determined the enclosed Scope of Work and the estimated cost for facilities to be completed by PacifiCorp Power Delivery for the interconnection of Phase I with Mona Substation. PacifiCorp's estimated cost required to complete the required interconnection facilities for Phase I is $4,123,468, broken down as follows: Mona Substation Line position & assoc relaying, communications & metering Engineering $ 487,679 Materials 947,338 Installation 1,799,287 Overheads 371,944 Total $3,606,248 Current Creek Substation Relay panel, communications, RTU & assoc testing Engineering $ 132,970 Materials 158,538 Installation 108,299 Overheads 45,977 Total $ 455,784
2 Lake Mountain Microwave Site Communications modifications Engineering $ 10,962 Materials 2,743 Installation 2,117 Overheads 1,820 Total $ 17,642 Salt Lake Control Center Communications modifications Engineering $ 22,894 Materials 7,064 Installation 13,736 Overheads 5,025 Total $ 48,719 Sigard Substation Communications modifications Engineering $ 3,447 Materials 638 Installation 467 Overheads 523 Total $ 5,075 Total Estimated Cost Engineering $ 657,952 Materials 1,116,321 Installation 1,923,906 Overheads 425,289 Total $4,123,468 If you have any questions, please call Larry Soderquist at (503) or Dan Johannsen at (503) Sincerely, Enclosure cc: Colin Persichetti 600 LCT David B. Cory Director, Transmission Services
3 Attachment B Scope of Work I. Currant Creek Generation Interconnection Project Scope (Phase I) A. Mona Substation (design, procurement, installation, and testing) Transmission Provider will be responsible for: Transmission Provider will provide the design and procure all the materials and equipment required to complete the necessary modifications at Mona Substation associated with the interconnection of the Currant Creek 525 MW (Phase I) generation facility to the 345kV system. In addition, Transmission Provider will complete all the work necessary to install and test the required substation equipment and materials including civil, communications, protection & controls, metering, and SCADA in the Mona Substation associated with the interconnection of the Currant Creek 525 MW (Phase I) generation facility. Transmission Provider will complete the connection of the 345kV transmission line to the 345 kv bus inside Mona Substation. Transmission Provider will provide specifications for the 345kV transmission line connecting Interconnection Customer s switchyard with Mona Substation and the fiber optic cable used for protection & control and communications. B. Currant Creek Substation (design, procurement, installation, and testing) Interconnection Customer shall be responsible for: Interconnection Customer shall be responsible for providing the design, procurement, installation, and testing of all materials and equipment required for the interconnection of the Currant Creek 525 MW generation facility to the 345kV system at Mona Substation except those items identified below to be the responsibility of Transmission Provider. Interconnection Customer shall be responsible for the installation of the Transmission Provider provided metering and protection & control panel required at Currant Creek Substation for the sole purpose of interconnecting the generation facility to the 345kV system at Mona Substation. Interconnection Customer shall provide switchyard operational design drawings to Transmission Provider for review. The switchyard shall be designed and built to meet Transmission Provider s standards, specifications, and practices for such facilities connecting to Transmission Provider s 345kV transmission system. Transmission Provider will be responsible for: Transmission Provider will design and procure the meter and protection & control panel for the 345kV line protection. Transmission Provider will provide the design documentation for the line P&C panel and the relay settings for the 345 kv transmission line interconnecting the Currant Creek Substation to Mona Substation FS Scope of Work FINAL to OASIS.doc Page 1 of 11
4 Transmission Provider will design, procure, and install the RTU and some of the communications equipment (identified below) that is required at the Currant Creek Substation for the sole purpose of interconnecting the Currant Creek Generation facility with Mona Substation. Transmission Provider will be responsible for reviewing Interconnection Customer s switchyard operational design drawings. In addition, Transmission Provider will test the required communications, metering, protection & control panel, and RTU equipment required at Currant Creek Substation for the sole purpose of interconnecting with Mona Substation prior to the equipment being placed in-service. C. Installation 1. Mona Substation Work to be completed by both Transmission Provider and Interconnection Customer as noted below a) Substation Mona Substation (all work to be completed by Transmission Provider except where otherwise noted) Interconnection Customer will terminate the new 345 kv transmission line on a new 60 high full tension dead-end tower provided by Transmission Provider in-line with a new 345kV Bay just inside the south fence in the lower level of Mona Substation. Transmission Provider will extend the existing 345kV north main bus and south main bus into the lower level yard. Both main buses will be 6 EHPS aluminum. The new cross bus will be 5 IPS Aluminum and kcm bundled aluminum conductor. This work will require the following equipment: 1. Two 362kV 2000 amp Circuit Breakers (GE-Hitachi HVB) with pre-insertion resistors 2. Four 345kV 2000 amp breaker disconnect switches (double side break) 3. One 345kV 2000 amp Line disconnect switch (double side break) with grounding blades 4. One 345kV Line full tension dead-end structure 5. One set of 345kV instrument transformers for revenue metering (3 CCVT s and 3 CT s with extended accuracy range) 6. Foundations for all the above structures 7. Grounding mat extension into the lower yard 8. New cable trench to the control building for all wiring for indication and revenue metering, control, power, lighting, and receptacles. All wiring used from the equipment in the yard into the control house shall be multi-conductor shielded cable (#10 or larger) as specified in PacifiCorp s standard ZS Substation yard lighting and receptacles with a local AC panel FS Scope of Work FINAL to OASIS.doc Page 2 of 11
5 10. Coordination of the microwave tower relocation 11. Connection to the customer s point of contact at the full tension dead-end structure kV station class lightning arrestors, complete with support structures and foundations. Additional work will also be required in the control building. This will include installation and interconnection of: 1. Two 12-inch breaker control panels 2. One 24-inch static relay panel 3. One RTU rack 4. Inter-panel wiring. The control cable used for inter-panel wiring inside the control house shall be non-shielded cable as specified in PacifiCorp s standard ZS A new 40 position DC LC, a new 42 position AC LC, and a new 44 point Annunciator Panel. (Depending on the timing of the construction these panels may not be necessary). b) Civil Mona Substation (all work to be completed by Transmission Provider) Since future development of Mona Substation to the east of the Currant Creek interconnection bays will not be possible, the first bay position will be placed along the east fence in the lower yard of Mona Substation and the yard will be expanded to the east approximately 100 feet for the second line position coming from Currant Creek Generation for (Phase II) of the project. The 345kV yard will be expanded 90 feet to the north. Approximately 400 feet of existing fence will be relocated and 180 feet of new fence will be installed. Approximately SF of ground needs to cleared, grubbed, and graded. Approximately 2900 SF of the expanded yard to the north will be graded to a 1:1 slope to match existing conditions and require large boulders for erosion control. The expanded area (less the slope) will have 4 of yard and road finish rock placed over an aggregate base course. The existing yard surfacing will be repaired after below grade construction to include base rock backfill and four inches of insulating rock. Install 400 of new cable trench with 30 wide road crossing and 4 protective bollards The following structures and foundations are required: high 3-phase bus support structures with 2 pier foundations per structure 7 345kV switch support structures with 2 pier foundations per structure FS Scope of Work FINAL to OASIS.doc Page 3 of 11
6 3 CCVT support structures with pier foundations 3 CT support structures with pier foundations 3 Lightning arrestor support structures with pier foundations 1-50 full tension dead-end structure with 10 static mast (2 columns with spread foundations) phase pull-off structure with drilled pier foundations 2 Circuit breaker foundations The oil spill plan (SPCC Plan) will be updated and revised to reflect the addition of the oil filled VTs. c) Protection & Control Mona Substation (all work to be completed by Transmission Provider) A new 345 kv bay position will be added at Mona Substation as part of the interconnection of the Current Creek Generation to 345kV system at Mona Substation. For that addition the following protection and control work will be done at Mona Substation: 1) Addition of two panels for the control, protection, and indication metering of the two new 345kV circuit breakers. 2) Addition of one panel for the protection and indication metering of the new 345kV line. The protection for this line will use two systems. Two current differential systems using SEL 311L relays communicating over two separately routed fiber-optic cables. 3) Fiber jumper cables between the SEL-311L relays and the fiber optic cable patch boxes. 4) Development of the relay settings for the line and breaker protection. 5) There is an existing digital fault recorder (DFR) in the substation, but there are no spare channels to monitor the new breakers and line position. A new 32-channel DFR will be procured and installed for the additional breakers and line position. This new DFR will connect to an existing Teltone SLSS that will provide 2-wire phone access to the DFR and its modem. d) Communications Mona Substation (work to be completed by both Transmission Provider and Interconnection Customer as noted below) One SONET fiber optic terminal will be installed at Mona Substation. Two diverse routes of fiber cables will be installed between Mona Substation and Currant Creek Substation by Interconnection Customer. These fiber cables will provide for two separate protection routes for the 345 kv line (SEL 311L relaying) and two paths for the SONET FS Scope of Work FINAL to OASIS.doc Page 4 of 11
7 equipment. Both protection routes will be via direct fiber. The SONET will provide for all other communications channels between Mona Substation and Currant Creek Substation. 1. Interconnection Customer will install and terminate two fiber cables, using diverse paths, coming from Currant Creek Substation to Mona Substation and provide splice boxes (hand-holes) as required. Interconnection Customer will procure and install the fiber cables and associated materials and equipment to install and terminate the fiber cables on patch panels at each end in the control buildings. Transmission Provider will provide a pathway for routing the fiber cables from the kV line dead-end structure to the control building and from a point approximately 10 outside the east fence line of Mona Substation to the control building. Transmission Provider will install all the additional associated hardware, innerduct, racks, fiber distribution centers, etc. required inside the control building beyond the patch panels where Interconnection Customer will terminate the fiber cables. The fiber cables will provide for two separate protection routes for the 345 kv line (SEL 311L relaying) and two paths for the SONET equipment. Transmission Provider will be responsible for: 1. Purchase and install one new SONET terminal (Lucent DMXplore). 2. Purchase and install one new Coastcom 2-T1 channel bank shelf. 3. Install 7 ea. Coastcom circuits (two telemetry, one substation SCADA, one plant SCADA, and three OPXs for Schweitzer, meters, and voice). Five of the circuits will be back-to-back channels to SCC. One telemetry channel will be for watt telemetry to the Sigurd alternate control center via Lake Mtn. and the second telemetry channel will be to SCC. 4. Install two Schweitzer 2830 fiber modems for the SEL 311L Mirrored Bits protection over the Coastcom and a single mode duplex jumper between the SEL 311Ls over the ADSS fiber. 5. Provide telemetry equipment and audio bridge equipment to SCC dispatch and Sigurd for alternate control (RFL 98 TMX Transmitter) at the substation. 6. Install miscellaneous equipment to include: racks, fuse panels, and DSX jack-fields. 7. The new Currant Creek Plant facility may obstruct the existing microwave path between Mona Substation and Nebo. If this occurs, it will be necessary to relocate the existing 30-foot microwave tower to provide a clear path. A new tower will be installed or the existing tower will be relocated to provide the required microwave path clearance between Mona Substation and Nebo. A determination of whether or not the existing path will be obstructed will be made after the exact location of the plant has been resolved FS Scope of Work FINAL to OASIS.doc Page 5 of 11
8 e) SCADA Mona Substation (all work to be completed by Transmission Provider) 1. All RTU modifications will be designed, wired and installed by Transmission Provider personnel. 2. The existing RTU will use spare points to accommodate the Revenue Inter-tie Metering analog outputs (MW and MVAR). 3. EMS data base changes will be made to support the new points. All scale factor information will be provided by Transmission Provider Engineering. f) Transmission Mona Substation (work to be completed by both Interconnection Customer and Transmission Provider as noted below) Interconnection Customer shall terminate the incoming transmission line on the full tension dead-end structure just inside of the south fence line of Mona Substation. Interconnection Customer shall procure and install the insulators used for terminating the 345kV line on the full tension dead-end structure and provide the 4-hole pads on the incoming line for Transmission Provider to connect jumpers to the incoming line. The full tension tower will be designed and installed by Transmission Provider. Transmission Provider will install the taps from the 345kV line to the 345kV bus inside the substation. g) Metering Mona Substation (Delivery Point Metering all work to be completed by Transmission Provider) All revenue metering and corresponding instrument transformers will be designed, procured, and installed by Transmission Provider personnel. Revenue Inter-tie Metering 1. Siemens meters will be used for primary delivery point metering. The primary meter will provide SCADA input s and back-up meter will provide telemetry input s 2. SCADA analog outputs for MW and MVAR. In addition, two accumulators are required one for MWH delivered and one for MWH received (dispatch) 3. Modem communications for dial-up metering 4. Note both Telemetry and SCADA metering will be required. 345 kv instrument transformers (wye connected) 1. Revenue current transformers shall be dedicated entirely for metering. The transformers shall be wound type.15 percent high accuracy with a ratio of (1000/5) FS Scope of Work FINAL to OASIS.doc Page 6 of 11
9 2. Voltage Transformers (1800:1) Wound type transformers are the present standard but some CCVT types are acceptable by meter engineering 2. Currant Creek Substation a) Protection & Control Currant Creek Substation (work to be completed by both Transmission Provider and Interconnection Customer as noted below) Transmission Provider will supply the line protection & control panel for Currant Creek Substation for the protection of the 345kV transmission line that will terminate in Mona Substation. The panel will contain two relay systems. Two current differential relay systems using SEL 311L relays communicating over two separately routed fiber optic cables. Also, on the panel will be a GPS satellite clock to provide accurate time tagging of the relay event records, a modem and a data switch to access the fault records from the relays using a voice grade channel over the fiber communications cables. Transmission Provider will supply the panel, documentation for the panel, the relay settings, and test the relays prior to them being placed inservice. Interconnection Customer shall develop the design drawings and install the cabling between the potential transformers, current transformers, circuit breaker s control circuits, and the protection & control panel provided by Transmission Provider. In addition, Interconnection Customer shall provide ungrounded 125VDC circuits for powering the equipment on the protection & control panel. The tie breaker(s) at Currant Creek Substation shall be equipped with the following: Maximum fault clearing time of 3 cycles Two current transformer (CT) sets, one for each of the line relays CT rated at the load rating of the breaker Relay accuracy CT C800 CT are cabled into the control house with one 4 conductor #10 Cu wire in shielded cable per CT Breaker failure relay protection on each of the tie breakers. Interconnection Customer shall provide a three-phase set of 345kV potential transformers (PT) or capacitive coupling potential devices on the 345 kv line to Mona Substation. The PTs shall be connected line to ground on the line to Mona Substation or on a location on the bus that is energized any time any one of the generators are connected to the system. Three phase 67 volt line to neutral shall be cabled into the control house using #10 Cu conductors in a shielded cable. The control cable used from the equipment in the yard into the Transmission Provider provided protection & control panel inside the FS Scope of Work FINAL to OASIS.doc Page 7 of 11
10 control house shall be multi-conductor shielded cable as specified in Transmission Provider s standard ZS The control cable used for inter-panel wiring inside the control house shall be non-shielded cable as specified in Transmission Provider s standard ZS The CT circuits shall be connected using 4-conductor #10 shielded cable as specified in Transmission Provider s standard ZS b) Communications Currant Creek Substation (work to be completed by both Transmission Provider and Interconnection Customer as noted below) Interconnection Customer will be responsible for: One SONET fiber optic terminal will be installed at Currant Creek Substation. Two diverse routes of fiber cables will be installed between Currant Creek Substation and Mona Substation. These fiber cables will provide for two separate protection routes for the 345 kv line (SEL 311L relaying) and two paths for the SONET equipment. Both protection routes will be via direct fiber. The SONET will provide for all other communications channels between Mona Substation and Currant Creek Substation. 1. Interconnection Customer will install and terminate two fiber cables, using diverse paths, going to Mona Substation and provide splice boxes (hand-holes) as required. Interconnection Customer will procure and install the fiber cables and associated materials and equipment to install and terminate the fiber cables on patch panels at each end in the control buildings. Transmission Provider will procure and install the additional associated equipment and materials as identified below. The fiber cables will provide for two separate protection routes for the 345 kv line (SEL 311L relaying) and two paths for the SONET equipment. 2. Interconnection Customer will procure and install a new 48 VDC wet cell battery in the Currant Creek substation control building along with a new battery charger to supply the required power for the communications equipment. Transmission Provider will be responsible for: 1. Purchase and install one new SONET terminal (Lucent DMXplore) at the substation. 2. Purchase and install one new Coastcom 2-T1 channel bank shelf at the substation. 3. Install 5 ea. Coastcom circuits (one substation SCADA, one plant SCADA, and three OPXs for Schweitzer, meters, and voice) at the substation. 4. Install two Schweitzer 2830 fiber modems for the SEL 311L Mirrored Bits protection over the Coastcom and a single mode FS Scope of Work FINAL to OASIS.doc Page 8 of 11
11 duplex jumper between the SEL 311Ls over the ADSS fiber at the substation. 5. Install miscellaneous equipment to include: racks, fuse panels, DSX jack-fields, and two Teltone SLSS s for dial access to end devices (Schweitzer Relays and meters). c) SCADA Currant Creek Substation (work to be completed by both Interconnection Customer and Transmission Provider as noted below) Transmission Provider will provide an RTU that is mounted on a 19- inch rack, configured and wired to interface terminal blocks. The RTU will communicate with the System Dispatch SCADA master. RTU Points Required (Note: this is not a detailed points list, but only a general overview): Status of all generator breakers and each of the three 345 kv transformer high side breakers. Net MWh and gross MWh reads for each generator unit at Currant Creek Net Generation (MW, MVAR - gross generator less auxiliary load) on the high side of each step-up transformer. Note, total net generation (MW, MVAR) is also required, but it can be picked up from the bi-directional revenue meter at Mona Substation. The total net generation will be required for delivery to the control center as real time data. 345 kv bus voltage at Currant Creek - measured at the Currant Creek side of the switch on the interconnecting line. Interconnection Customer shall be responsible for: 1. Assisting in the check out of all analog or digital points originating from their equipment. 2. Providing any scaling information as required for points originating from their equipment. 3. Providing status points for all 345 kv breakers and all low side generator breakers if used. Providing net MW and MVARs for each generator. All wiring for these points to be brought to the Transmission Provider RTU in Currant Creek substation. The analog points to the RTU shall be 0-1 ma. 4. Providing and installing cable for the voltage outputs from the Transmission Provider procured 345kV interconnecting line protection panel to the Transmission Provider procured and installed RTU FS Scope of Work FINAL to OASIS.doc Page 9 of 11
12 5. Providing and installing cable for the analog output from the RTU in Currant Creek substation to the plant. This circuit will be used by the System Dispatcher for communicating the desired reactive flow target to the Plant Operator to be used in making adjustments in generator output. 6. Providing space in the Currant Creek control building adjacent to the 345kV interconnecting line protection panel for the installation of the Transmission Provider RTU. 7. Providing a 125VDC power source to the installation location of Transmission Provider s RTU for powering the RTU. Transmission Provider will be responsible for: Procuring an RTU that is mounted on a 19 inch rack, configured, and wired to interface terminal blocks. The RTU will communicate via the fiber optic cable channel bank to the System Dispatch SCADA master. The RTU will require Interconnection Customer to provide a 125VDC source for powering the RTU. Transmission Provider will provide a telephone to communicate to the Salt Lake City office to facilitate the testing of the RTU. The RTU will be mounted in the Plant s switchyard control house. EMS data base changes will be made to support the new RTU. d) Transmission Currant Creek Substation (all work to be completed by Interconnection Customer) Interconnection Customer shall complete all terminations of the transmission line inside Currant Creek Substation. 3. Additional Communication Sites Requiring Modifications (all work to be completed by Transmission Provider) a) SCC: 1. The existing Coastcom shelves in SCC will support the channels required for Currant Creek Plant and Substation. 2. Install 6 ea. Coastcom circuits (one telemetry, one Substation SCADA, one Plant SCADA, and three OPX for Schweitzer, meters, and voice). 3. Install telemetry receiver equipment for interchange watts. b) Sigurd Substation: 1. Install telemetry receiver equipment for alternate control center (watts). An existing Coastcom channel card is available for use FS Scope of Work FINAL to OASIS.doc Page 10 of 11
13 c) Lake Mountain Microwave site: 1. Install required back-to-back digital channels. If sufficient capacity exists directly between Mona and SCC, these back-to-back channels will not be required kv Transmission Line from Currant Creek Substation to Mona Substation (all work to be completed by Interconnection Customer except as noted otherwise below) a) 345 kv Transmission Line Design and construct a 345 kv transmission line from Currant Creek Substation to Mona Substation. The transmission line shall be designed, surveyed, and constructed by Interconnection Customer according to Transmission Provider Engineering s standards. Engineering design shall meet Transmission Provider Engineering s Construction Standards (sections TA 001 through TA 201) for Transmission Lines connecting to PacifiCorp s 345kV system. Clearances used for construction shall meet Transmission Provider Engineering s standards TC001 through TC391. The basic structure will be a 345kV D-3 structure with steel poles. Conductor size shall be double vertical-bundled (2-conductors per phase with 18 separation) 954kCM ACSR (Cardinal). Shield wire shall be 3/8 EHS. The OPGW shall be Transmission Provider Engineering s standard diameter cable. Weather loadings on the transmission line structures shall be the worst case of NESC Heavy with overload factors, NESC Light with overload factors and 120 mph wind with 1.0 overload factor. The 120 mph wind will cause a minimum psf wind on structure body, conductors and shield or OPGW wire. All other design parameters shall be coordinated with Transmission Provider s Transmission Engineering Group. Rights-of-Way procurement shall be the responsibility of Interconnection Customer subject to Transmission Provider s Property Department R/W standards. All line materials will be standard Transmission Provider materials supplied by the Interconnection Customer FS Scope of Work FINAL to OASIS.doc Page 11 of 11
Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022
Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationSmall Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662
Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationMedium Voltage Metal-Enclosed Power Capacitor Banks
66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Power Capacitor Banks General Northeast Power System s (NEPSI's) medium
More informationSPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station
SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet Reference: ZD23 Version: 1.1 Issue date: 15 May 2014 Contents 1 Scope... 3 2 Deer Park Terminal
More informationi-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection
i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection 1 Process PG&E Order No. 754 Analysis Receive Bus List from Planning that Meet the Criteria in Table A Protection Computes Actual Clearing
More informationSapphire Wind Farm 330/33kV Substation
Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationMedium Voltage Metal-Enclosed Harmonic Filter Systems
66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Harmonic Filter Systems General NEPSI s armorvar, medium voltage metal-enclosed
More informationNEW ERA METER. Installation & Operation Guide NE METER
NEW ERA METER Installation & Operation Guide NE METER Autoranging Power Supply Installation Diagnostics Per Phase Voltage & Current kwh, Demand and TOU 0.2% Accuracy -40 C to +85 C Watertight Enclosure
More informationTarget Interface / Construction Compliance Inspection Checklist
A. Targets Quantities meet DD9, applicable TC -, and CEHNC Design Guide 0-- Oriented to face firing line or firing positions/points B. Roads-Service, Lanes Number of lanes meets DD 9, applicable TC -,
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationTarget Interface / Construction Compliance Inspection Checklist
A. Targets Quantities meet DD9, applicable TC -, and CEHNC Design Guide 0-- Oriented to face firing line or firing positions/points B. Roads-Service, Lanes Number of lanes meets DD 9, applicable TC -,
More informationMONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES
MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES 1. Introduction Real time monitoring and control is necessary to ensure public and employee safety and to protect the integrity
More informationMehta Tech, Inc. TRANSCAN IED For Multi-Function, Multi-Speed Recording
Mehta Tech, Inc. TRANSCAN IED For Multi-Function, Multi-Speed Recording Two independent, simultaneously operating recorders in one package Triggering on input quantities and calculated values, such as
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationTarget Interface / Construction Compliance Inspection Checklist
TES A. Roads-Service, Lanes Common Items Trails and service roads provide adequate access to buildings for maintenance B. Testing Results-provided to the local government construction representative Data
More informationLONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL
LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL DISTRIBUTION SYSTEM Revised and Issued March 2003 I.
More informationTarget Interface / Construction Compliance Inspection Checklist
A. Targets Quantities meet DD9, applicable TC 5-, and CEHNC Design Guide 0-- Oriented to face firing line or firing positions/points B. Roads-Service, Lanes Number of lanes meets DD 9, applicable TC 5-,
More informationSWITCHYARD SYSTEM BC1-SS-11-SD TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1
SWITCHYARD SYSTEM TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1 November 2011 PREFACE This Training System Description has been designed to assist you in meeting the requirements of Module BC1-SS-11
More informationPresented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011
Photovoltaic Solutions Make the most of your solar PV project Presented by: Oscar Araujo Photovoltaic Solutions Manager 4 th Canadian German Solar PV Conference March 2 nd 2011 Agenda Solutions for Renewable
More informationSCADA Training - T&D Automation
SCADA Training - T&D Automation Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq This course covers all the
More informationTable of Contents 1 ABOUT THIS GUIDE CONTACT INFORMATION ANTENNA INSTALLATION... 4
Table of Contents 1 ABOUT THIS GUIDE... 3 1.1 CONTACT INFORMATION... 3 2 ANTENNA INSTALLATION... 4 2.1 GENERAL INFORMATION... 4 2.2 SPECIFIC MOUNTING EXAMPLES... 5 2.3 CONNECTOR MOISTURE PROTECTION...
More informationIt is acceptable to place all required information in the main element (such as G4010) and delete the sub-elements provided in this template.
6. ENGINEERING SYSTEMS REQUIREMENTS G40 SITE ELECTRICAL UTILITIES SYSTEMS REQUIREMENTS SITE ELECTRICAL UTILITIES TEMPLATE 02/18 Instructions for using this template: There are template files for each UNIFORMAT
More informationCalifornia lndependent System Operator Corporation Compliance Filing Docket No. ER
The Woshington Harbour 3000 K Street, N.W., Suite 300 Washington, D.C. 20007-51 16 Phone 202.424.7500 Fox 202.424.7647 January 3l.2005 The Honorable Magalie R. Salas Secretary Federal Energy Regulatory
More informationSubstation SCADA Monitoring
Substation SCADA Monitoring Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Substations are a critical component
More informationELG4125: System Protection
ELG4125: System Protection System Protection Any power system is prone to 'faults', (also called short-circuits), which occur mostly as a result of insulation failure and sometimes due to external causes.
More informationReal-time Power System Operation. Energy Management Systems. Introduction
1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern
More informationSTATE OF NEW JERSEY BUREAUS OF ITS ENGINEERING AND SAFETY & DATA DEVELOPMENT DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625
September 2011 STATE OF NEW JERSEY BUREAUS OF ITS ENGINEERING AND SAFETY & DATA DEVELOPMENT DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625 MATERIAL SPECIFICATIONS FOR WEIGH-IN-MOTION SYSTEM The
More informationJanuary 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.
California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California
More informationSmall Power Station Surge Protection Analysis and Plan
[Type the document title] Small Power Station Surge Protection Analysis and Plan By ArresterWorks Jonathan Woodworth ArresterWorks Page 1 Contents 1.0 Executive Summary... 3 1.1 Project Overview... 3 1.2
More informationFor the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)
Electrical Company: PacifiCorp For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Designated Contact Person: Robin Moore Address
More informationProtection, Monitoring, and Control System for Distribution Substations ALARM HISTORY SYSTEM COMM. On-Line Documentation TRANSFORMER 12 MW
SEL Distribution Substation Protection and Automation System Protection, Monitoring, and Control System for Distribution Substations Data Sheet SYSTEM ONE-LINE RELAY TARGETS ALARM HISTORY SYSTEM COMM.
More informationBus Differential and Breaker Failure Relay. Advanced bus protection with built-in breaker failure detection
SEL-487B Bus Differential and Breaker Failure Relay Advanced bus protection with built-in breaker failure detection Protect busbars with up to 21 terminals using high-speed, low-impedance bus differential
More informationDeploying Digital Substations: Experience with a Digital Substation Pilot in North America. Harsh Vardhan, R Ramlachan GE Grid Solutions, USA
Deploying Digital Substations: Experience with a Digital Substation Pilot in North America Harsh Vardhan, R Ramlachan GE Grid Solutions, USA Wojciech Szela, Edward Gdowik PECO, USA SUMMARY Though IEC 61850
More informationTOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT
TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT 06045-0191 TRAFFIC SIGNAL INSTALLATIONS MIDDLE TURNPIKE EAST AT SUMMIT STREET MIDDLE TURNPIKE EAST AT
More information4-W HDSL/56Kbps Isolation Card With 130/190V Span Powering. Description & Installation P30140
4-W HDSL/56Kbps Isolation Card With 130/190V Span Powering Description & Installation P30140 Printed in USA 11/12 TO506 Rev. A Table of Contents 1.0 PRODUCT SCOPE 3 2.0 PRODUCT OVERVIEW 3 2.1 System Requirements
More informationRemote Real-Time Measurements of Voltage, Current and Energy
Remote Real-Time Measurements of Voltage, Current and Energy Chris Yakymyshyn Pam Hamilton Michael Brubaker yakymyshyn@fieldmetricsinc.com 727-319-0299 Slide 1 Outline Introduction FieldMetrics (FMI) Products
More informationThe Smart Utility Meets The Smart tgid Grid. The Smart. Bob Uluski. Technology Quanta Technology LLC
The Smart Utility Meets The Smart tgid Grid The Smart Substation Bob Uluski Quanta Technology Why is the Smart Substation Key power apparatus important? for maintaining the reliability and efficiency of
More informationICX-CMOS-E-2006 Electrical / I&C Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS
102904-ICX-CMOS-E-2006 Electrical / I&C Engineer Holds a B. Sc. in Electronics & Electrical Communications Engineering and has over 9 years hands-on experience working in I&C field. Has extensive experience
More informationSPECIAL PROVISION Scope of Work
2004 Specifications CSJ 0914-00-301 & 0914-00-314 SPECIAL PROVISION 004---018 Scope of Work For this project, Item 004, Scope of Work, of the Standard Specifications, is hereby amended with respect to
More informationIDM DATA ACQUISITION SYSTEM
DATA ACQUISITION SYSTEM The a compact and economical multifunction data acquisition system Rendering all Unrivalled product profile Advanced multifunctional distributed data acquisition system Fully multitasking
More informationBus Differential and Breaker Failure Relay. Advanced bus protection with built-in breaker failure detection
SEL-487B Bus Differential and Breaker Failure Relay Advanced bus protection with built-in breaker failure detection Protect busbars with up to 21 terminals using high-speed, low-impedance bus differential
More information1995 Metric CSJ 's & SPECIAL PROVISION ITEM 4. Scope of Work
1995 Metric CSJ 's 0015-13-235 & 3136-01-098 SPECIAL PROVISION TO ITEM 4 Scope of Work For this project, Item 4, "Scope of Work", of the Standard Specifications, is hereby amended with respect to the clauses
More informationElectrical Demand Specification (Reference SOP: )
Project: Equipment Description: Location: Equipment No.: Project No: Protocol No.: Content Index 1. GENERAL...3 Design Standards...3 1.1. Standards...3 2. DESIGN...3 2.1. Safety...3 2.2. Circuit protection...3
More informationDigital Substation Overview of Technology, Industry
Digital Substation Overview of Technology, Industry Trends and Standardization Efforts 4th International Scientific & Technical Conference Actual Trends in Development of Power System Protection and Automation
More informationBus Differential and Breaker Failure Relay. Advanced bus protection with built-in breaker failure detection
SEL-487B Bus Differential and Breaker Failure Relay Advanced bus protection with built-in breaker failure detection Protect busbars with up to 21 terminals using high-speed, low-impedance bus differential
More informationAutomate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control
Welcome to NovaTech Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control Paul Grabowski About the Author Paul Grabowski
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December
More informationAwareness of the Situation
17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog
More informationPower System Network Simulator (PSNsim)
The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment
More informationAUTOMATION OF POWER DISTRIBUTION USING SCADA
1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from
More informationCommission Testing Methods for Protection Systems
Commission Testing Methods for Protection Systems Tom Ernst GE Grid Solutions Ken Sletten Minnesota Power Abstract Commission testing should be designed to assure that the protection system is set and
More informationA Hybrid Communications Network Approach for Advanced Applications on the Modern Grid
A Hybrid Communications Network Approach for Advanced Applications on the Modern Grid Mark A. Carella, PE Manager Distribution Control and Integration nationalgrid Private Telecom Network Key Stats Private
More informationSECTION SWITCHBOARDS
SECTION 26 24 13 PART 1 - GENERAL 1.1 SUMMARY A. Work Included: 1. Switchboards 2. Commercial Metering Switchboards 3. Non-Utility Power Meters (Microprocessor-Based Metering Equipment) PART 2 - PRODUCTS
More informationPower Supply (48Vdc, 2.5A)
Telecommunications Group Section 855-180-201 Equipment Issue 1 Fourth Printing, September 2006 8551-80 Power Supply (48Vdc, 2.5A) Compliant with UL Standard 60950, Second Edition* CONTENTS PAGE Part 1.
More informationDECK All-In-One Enclosure. Quick Installation Guide for Field Installers
DECK All-In-One Enclosure Quick Installation Guide for Field Installers 1 Contents Legal Statement... 2 Preliminary Considerations... 2 Required Installation Tools and Materials... 2 Networking Information...
More informationNpefm!681F! !!!681F!Gjcfspqujd!Usbotdfjwfs! Gjcfspqujd!Ofuxpsl!Tpmvujpo!! Model 570E Features. The Fiberoptic Communications Specialists
!!!681F!Gjcfspqujd!Usbotdfjwfs! Gjcfspqujd!Ofuxpsl!Tpmvujpo!! The Fiberoptic Communications Specialists The Model 570E offers high-speed serial communication to meet the challenging needs of distribution
More informationTRANSMISSION FACILITIES INTERCONNECTION REQUIREMENTS
TRANSMISSION FACILITIES INTERCONNECTION REQUIREMENTS Corresponds to NERC Standard FAC-001-1 Developed By CPP Engineering Department May 1, 2015 Prepared by: Raymond O Neill, P.E. Version 3 INDEX CPP Transmission
More informationTFS 2100 Traveling Wave Fault Location System
Traveling Wave Fault Location System The most accurate overhead transmission and distribution line fault locator Accuracy: ±150m typical regardless the line length Unaffected by fault resistance Suitable
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationFiber Optic Selector Guide for Analog & Digital Data Links, Contact Closures & Multiplexers
Fiber Optic Selector Guide for Analog & Digital Data Links, Contact Closures & Multiplexers Analog Data Links Multi-Channel Contact Closures Multiplexers Digital Data Links - Contact Closures Power Supply
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationPackaged Solutions. Grid Solutions. Value Added Solutions for Protection, Control and Automation Applications. Flexible and Expandable
Grid Solutions Packaged Solutions Value Added Solutions for Protection, Control and Automation GE s Packaged Solutions provide fully integrated, modular solution sets comprising of engineering, design,
More informationElectric Utility Facility Connection Requirements
City of Coffeyville Municipal Light and Power Electric Utility Facility Connection Requirements Approved: Date: Version Date Change Tracking Reviewer/Editor 1.0 June, 2010 Original document. Steve McGie
More informationJuly 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities
More informationUsing the Bitronics 70 Series to Improve Local Monitoring and Control
Automate a Substation and Preserve the Electromechanical Relay Investment Part Two of Four Using the Bitronics 70 Series to Improve Local Monitoring and Control Paul Grabowski - Bitronics Senior Application
More informationTHROWMASTER 409 T-1 System Transfer Set
THROWMASTER 409 T-1 System Transfer Set The Throwmaster Model 409 is a revolutionary new way of transferring T-1 circuits from one transmission system to another, There can be any number of repeaters or
More informationPacifiCorp Transmission Technical Workshop
PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt
More informationEnerSure Installation Guide
EnerSure Installation Guide Danger!!! The electrical components of this system may contain voltage and /or amperage sufficient to injure or kill. Installation is only to be performed by a licensed, bonded
More informationSPOS (Station Point of Sale) 200. SFTP (Station Fare Transaction Processor) 35. CQD (Card Query Device) 35. HCR (Handheld Card Reader) Cradles 120
DESIGN GUIDELINES PRESTO INSTALLATION & CONNECTIVITY PAGE 1 of 4 ELECTRICAL CONNECTIVITY AND WIRING Communications Conduits Conduits designated for Presto equipment data wiring shall be clearly identified
More informationMODEL SIB-V245 / V453
WILKERSON INSTRUMENT CO., INC INSTALLATION & OPERATION MANUAL SCADA INTERFACE BOARD MODEL SIB-V245 / V453 FOR MOTOROLA ACE3600 MIXED I/O MODULE RoHS Compliant UL/cUL Recognized Motorola is a registered
More informationCONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]
Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected
More informationLCRA Transmission Services Corporation. Facility Connection Requirements
LCRA Transmission Services Corporation Facility Connection Requirements April 2017 Table of Contents 1.0 INTRODUCTION... 3 2.0 Facility Connection Requirements... 3 2.1 Summary of Basic Interconnection
More informationMeter Enclosure and Equipment Standards
Meter Enclosure and Equipment Standards (a) (b) General Requirements: CITY OF OCALA UTILITY SERVICES METER ENCLOSURE AND EQUIPMENT STANDARDS: (1) To avoid the costs associated with having to replace unacceptable
More informationOC IEEE IAS/PES Meeting February 21, 2013
San Diego International Airport: Building For The Future, Through Underground Distribution Automation and SCADA OC IEEE IAS/PES Meeting February 21, 2013 1 Presenter: Randy Denton, PE Under Ground Utility
More informationASCO 920 Remote Control (RC) Switches
Maximum reliability and excellent value ASCO 920 Remote Control (RC) Switches ASCO 920 Remote Control Switch in Type Enclosure The ASCO 920 is designed as a feeder disconnect switch for load capacities
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationGAS. POWER. WATER. TELCO. POWER
GAS. POWER. WATER. TELCO. POWER Who is Zinfra? Zinfra is a leading power, gas, water and telco infrastructure service provider. We offer a comprehensive range of engineering, construction and maintenance
More information1993 SPECIFICATIONS CSJ , ETC. & SPECIAL SPECIFICATION ITEM 6132 ARTERIAL TRAFFIC MANAGEMENT SYSTEM
1993 SPECIFICATIONS CSJ 1685-05-068, ETC. & 1685-02-042 1.0 DESCRIPTION SPECIAL SPECIFICATION ITEM 6132 ARTERIAL TRAFFIC MANAGEMENT SYSTEM THIS ITEM DESCRIBES THE OPERATION AND INSTALLATION OF AN ARTERIAL
More informationMESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR
Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR 22 kv Version: 2 Issued: 19 th December 2016 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering - Electrical
More informationEntry Level Assessment Blueprint Electrical Occupations
Entry Level Assessment Blueprint Electrical Occupations Test Code: 3029 / Version: 01 Specific Competencies and Skills Tested in this Assessment: Safety Apply shop safety rules and ergonomics Explain fire
More informationTitle System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)
Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards
More informationAPPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:
APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd
More informationSPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5
Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System
More informationPower Systems Communications Implementation of IEC61850 in a Substation Environment
Power Systems Communications Implementation of IEC61850 in a Substation Environment 26 October 2009 Reference VEE4700-01 Revision 0 Document Control Document ID: DOCUMENT1 Rev No Date Revision Details
More informationHow smart can the grid really be?
How smart can the grid really be? by Dale Pudney, HVT Power Systems and Luo Wei, NR Electric With the improvement of electronic communications and computing technology, it becomes possible to integrate
More information3710 ACM 3750 PDC 3800 RTU. ISOCOM Communications Card Retrofit Instructions
3710 ACM 3750 PDC 3800 RTU ISOCOM Communications Card Retrofit Instructions Danger During normal operation of this device, hazardous voltages are present which can cause severe injury or death. These
More informationElastimold Molded Vacuum Recloser - MVR
Subject: Elastimold Recloser Technical Specification Date: 4/24/12 File: MVR-RS-0412 Page: 1 of 6 1.0 SCOPE Elastimold Molded Vacuum Recloser - MVR 1.1 This specification covers electrical and mechanical
More information1. Project Description
Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal
More informationTransmission Infrastructure Investment & Development in Vietnam
Transmission Infrastructure Investment & Development in Vietnam Presented by: Mr. Cao Duc Dung Expert of Technical Department National Power Transmission Corporation (NPT) 28 September, 2011 1 CONTENTS
More informationSPECIFICATION FOR CUSTOMER 138 KV SUBSTATION DESIGN
2.8. The customer will coordinate the operation of their high voltage facilities with CenterPoint Energy's Real Time Operations Division per CenterPoint Energy's "Transmission & Substation Outage and Clearance
More informationMedium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks
66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks General NEPSI's activar, Medium
More informationHigh-speed transformer differential protection for up to five terminals
Transformer Protection Relay High-speed transformer differential protection for up to five terminals Advanced differential protection and three restricted earth fault (REF) elements minimize damage and
More information