Market Performance Report December 2015

Size: px
Start display at page:

Download "Market Performance Report December 2015"

Transcription

1 Market Performance Report December 215 February 1, 216 ISO Market Quality and Renewable Integration CAISO 25 Outcropping Way Folsom, California 9563 (916)

2 Executive Summary 1 The market performance in December 215 is summarized as follows. In the CAISO areas, The peak load continued to be at low levels. In the IFM market, VEA prices were depressed for a couple of days due to transmission congestion. In the FMM and RTD markets, SCE, SDG&E and VEA prices were depressed on December 25 due to the congestion on Path 15. The congestion rent for interties rose to $7.25 million from $1.46 million in November. Majority of the congestion rents in December accrued on Palo Verde (6 percent) and MALIN5 (34 percent) interties. The congestion revenue rights market revenue adequacy was percent as compared with 7.92 percent in November due to an intertie derate. The monthly average ancillary service cost to load sank to $.21/MWh in December from $.24/MWh in November. There were no scarcity events in December. The cleared virtual supply was well above the cleared virtual demand in the middle of December and late December. The profits from convergence bidding increased to $2.81 million in December from $.41 million in November. The bid cost recovery in December skidded to $4.99 million from $6.29 million in November. The real-time energy offset cost inched up to $1.98 million in December from $1.75 million in November. The real-time congestion offset cost rose to $4.1 million in December from $.57 million in November. The volume of exceptional dispatch increased to 44,558 MWh from 31,728 MWh in November. The monthly average of total exceptional dispatch volume as a percentage of load increased to.24 percent in December from.19 percent in November. In the EIM areas, On December 1, 215, the Nevada-based utility NV Energy successfully began participating in the western Energy Imbalance Market. In FMM and RTD, PACE and NEVP prices were depressed on December 25 due to the binding EIM transfer constraint from PACE to PACW. The total EIM BCR, RTIEO and RTCO costs were $.78 million, $4.85 million and -$.9 million respectively. 1 This report contains the highlights of the reporting period. For a more detailed explanation of the technical characteristics of the metrics included in this report please download the Market Performance Metric Catalog, which is available on the CAISO web site at Market Performance Report Page 2 of 43

3 TABLE OF CONTENTS Executive Summary... 2 Market Characteristics... 4 Loads... 4 Direct Market Performance Metrics... 5 Energy... 5 Day-Ahead Prices... 5 Real-Time Prices... 5 Congestion... 9 Congestion Rents on Interties... 9 Congestion Rents on Branch Groups and Market Scheduling Limits... 9 Congestion Revenue Rights Ancillary Services IFM (Day-Ahead) Average Price Ancillary Service Cost to Load Scarcity Events Convergence Bidding Renewable Generation Curtailment Indirect Market Performance Metrics Bid Cost Recovery Real-time Imbalance Offset Costs... 3 Market Software Metrics Market Disruption Manual Market Adjustment Exceptional Dispatch Energy Imbalance Market Market Performance Report Page 3 of 43

4 MW Market Characteristics Loads The peak load for CAISO continued to be at low levels. Figure 1: System Peak Load 35, 3, 25, 2, 15, 1, 5, Market Performance Report Page 4 of 43

5 $/MWh Direct Market Performance Metrics Energy Day-Ahead Prices Figure 2 shows daily prices of four DLAPs. The binding constraints along with the associated DLAP locations and the occurrence dates are listed in Table 1. Figure 2: Day-Ahead Simple Average LAP Prices (All Hours) PGE SCE SDGE VEA Table 1: Day-Ahead Transmission Constraints DLAP Date Transmission Constraint VEA December 7-1 DOUBLTTP-FRIARS -138kV line VEA December BARRE -VILLA PK-23kV line SCE, SDG&E December 3 OMS PDCI_NG Real-Time Prices FMM daily prices of the four DLAPs are shown in Figure 3. The binding constraints along with the associated DLAP locations and the occurrence dates are listed in Table 2. Market Performance Report Page 5 of 43

6 $/MWh Figure 3: FMM Simple Average LAP Prices (All Hours) PGE SCE SDGE VEA Table 2: FMM Transmission Constraints DLAP Date Transmission Constraint VEA December 7-8, BARRE -VILLA PK-23kV line SCE, SDG&E, VEA December 25 PATH15_S-N Figure 4 below shows the daily frequency of positive price spikes and negative prices by price range for the default LAPs in FMM. The cumulative frequency of prices above $25/MWh continued to be percent in December. The cumulative frequency of negative prices decreased to 1.71 percent in December from 2.13 percent in November. The frequency of negative prices was high on December 25 when the congestion on Path15 resulted in negative prices in a couple of hours. Market Performance Report Page 6 of 43

7 $/MWh 1-Nov Frequency Figure 4: Daily Frequency of FMM LAP Positive Price Spikes and Negative Prices.% -5.% -1.% -15.% -2.% -25.% <=-$25 $(-1, -25] $(-4,-1] $(-2,-4] $(,-2] $[25,5) $[5,75) $[75,1) $[1,3] RTD daily prices of the four DLAPs are shown in Figure 5. The binding constraint along with the associated DLAP locations and the occurrence dates are listed in Table Figure 5: RTD Simple Average LAP Prices (All Hours) PGE SCE SDGE VEA Table 3: RTD Transmission Constraints DLAP Date Transmission Constraint VEA December 7-8, BARRE -VILLA PK-23kV line SCE, SDG&E December 24 OMS PDCI_NG SCE, SDG&E, VEA December 25 PATH15_S-N Market Performance Report Page 7 of 43

8 Frequency Figure 6 below shows the daily frequency of positive price spikes and negative prices by price range for the default LAPs in RTD. The cumulative frequency of prices above $25/MWh decreased to.24 percent in December from.48 percent in November. The cumulative frequency of negative prices dropped to 2.9 percent in December from 4.57 percent in November. December 25 saw high frequency of negative prices when the congestion on Path15 resulted in negative prices in a couples of hours. Figure 6: Daily Frequency of RTD LAP Positive Price Spikes and Negative Price 5.%.% -5.% -1.% -15.% -2.% -25.% <=-$25 $(-1, -25] $(-4,-1] $(-2,-4] $(,-2] $[25,5) $[5,75) $[75,1) $[1,3] Market Performance Report Page 8 of 43

9 Thousands Congestion Congestion Rents on Interties Figure 7 below illustrates the daily integrated forward market congestion rents by interties. The cumulative total congestion rent for interties in December rose to $7.25 million from $1.46 million in November. Majority of the congestion rents in December accrued on Palo Verde (6 percent) and MALIN5 (34 percent) interties. Total congestion rent on Palo Verde increased to $4.34 million in December from $.78 million in November. December 1 saw high congestion rents on interties, which was mainly driven by the congestion on Palo Verde intertie. From December 1 to December 4, Palo Verde intertie was derated due to the outage of Colorado River-Palo Verde 5 kv Line. The congestion rent on MALIN5 increased to $2.46 million in December from $.47 million in November. MALIN5 was derated this month due to various outages including the outage of Vaca Dixon #2 5 kv series capacitor bank, Grand Coulee-Hanford 5 kv line, and Buckley-Grizzly #1 5 kv line. $4, $3,5 $3, $2,5 $2, $1,5 $1, $5 $ Figure 7: IFM Congestion Rents by Interties (Import) IPPUTAH_ITC MALIN5 PALOVRDE_ITC MEAD_ITC COTPISO_ITC WSTWGMEAD_ITC MKTPCADLN_ITC CASCADE_ITC Congestion Rents on Branch Groups and Market Scheduling Limits Figure 8 illustrates the IFM congestion rents on selected branch groups and market scheduling limits. Total congestion rents for branch groups and market scheduling limits dropped to $ in December from $.5 million in November. Market Performance Report Page 9 of 43

10 Congestion Cost ($/MWh) 1-Nov Thousands Figure 8: IFM Congestion Rents by Branch Groups and Market Scheduling Limits $3 $25 $2 $15 $1 $5 $ BLYTHE_BG SUTTEROBANION_BG Average Congestion Cost per Load Served This metric quantifies the average congestion cost for serving one megawatt of load in the ISO system. Figure 9 shows the daily and monthly averages for the day-ahead and real-time markets respectively. Figure 9: Average Congestion Cost per Megawatt of Served Load Day Ahead Real Time Day-Ahead Average Real-Time Average The average congestion cost per MWh of load served in the integrated forward market increased to $.94/MWh in December from $.21/MWh in November. The average congestion cost per load served in the real-time market went to -$.21/MWh in December from -$.3/MWh in November. Market Performance Report Page 1 of 43

11 Revenue Adequacy () Congestion Revenue Rights Figure 1 illustrates the daily revenue adequacy for congestion revenue rights (CRRs) broken out by transmission element. The average CRR revenue deficit in December increased to $396,66 from the average revenue deficit of $48,698 in November. Figure 1: Daily Revenue Adequacy of Congestion Revenue Rights $1. $. -$1. -$2. -$3. -$4. -$5. -$ _ESCNDIDO_69._22724_SANMRC 22831_SYCAMORE_138_22124_CHCARIT 2416_BARRE _23_24154_VILLA P OTHER PALOVRDE_ITC 22356_IMPRLVLY_23_2236_IMPRLVL NdGrp: 3683_KIFER _6._B1 OMS PDCI_NG 22192_DOUBLTTP_138_223_FRIARS 35122_NWARK EF_115_3535_AMES BS Overall, December experienced CRR revenue deficit. Revenue shortfalls were observed in most days of this month. Palo Verde intertie was binding in seven days, resulting in revenue shortfall of $6.18 million. A line (2416_BARRE _23_24154_VILLA P) was binding in 24 days, resulting in revenue shortfall of $1.27 million. A line (35122_NWARK EF_115_3535_AMES BS) was binding in 12 days, resulting in revenue shortfall of $1.67 million. Market Performance Report Page 11 of 43

12 The shares of the revenue surplus and deficit accruing on various congested transmission elements for the reporting period are shown in Figure 11 and the monthly summary for CRR revenue adequacy is provided in Table 4. Figure 11: CRR Revenue Adequacy by Transmission Element OMS PDCI_NG 8% 2416_BARRE _23_24154_VILL A PK_23_BR_1 _1 1% 22192_DOUBLTTP _138_223_FRI ARS _138_BR_1 _1 3% NdGrp: 3683_KIFER _6._B1 3% PALOVRDE_ITC 49% 35122_NWARK EF_115_3535_A MES BS _115_BR_2 _1 13% OTHER 14% Revenue Shortfall, $12.77 Million 2248_MIRAMAR _69._22756_SCRIP PS _69._BR_1 _1 18% 3278_CLARMNT _115_32782_STATIN D_115_BR_1 _1 8% NdGrp: 3326_BAYSHOR1_1 15_B1 5% MEAD_ITC 2% 35642_METCALF _115_35645_EVRGR N J_115_BR_2 _2 25% OTHER 21% 35618_SN JSE A_115_3562_EL PATIO_115_BR_1 _1 21% Revenue Surplus, $.41 Million Market Performance Report Page 12 of 43

13 Overall, the total amount collected from the IFM was not sufficient to cover the net payments to congestion revenue right holders and the cost of the exemption for existing rights. The revenue adequacy level was percent in December. Out of the total congestion rents, 6.45 percent was used to cover the cost of existing right exemptions. The net total congestion revenues in December were in deficit by $12.28 million, compared to the deficit of $1.46 million in November. The auction revenues credited to the balancing account for December were $6.59 million. As a result, the balancing account for December had a deficit of approximately $5.64 million, which will be allocated to measured demand. Table 4: CRR Revenue Adequacy Statistics IFM Congestion Rents $18,325,23.82 Existing Right Exemptions -$1,181,252.5 Available Congestion Revenues $17,143, CRR Payments $29,421, CRR Revenue Adequacy -$12,278,56.6 Revenue Adequacy Ratio 58.27% Annual Auction Revenues $4,94,988.9 Monthly Auction Revenues $1,647, CRR Settlement Rule $48,32.36 Allocation to Measured Demand -$5,641,52.48 Market Performance Report Page 13 of 43

14 $/MW Ancillary Services IFM (Day-Ahead) Average Price Table 5 shows the monthly IFM average ancillary service procurements and the monthly average prices. In December the monthly average procurement decreased for regulation up. Table 5: IFM (Day-Ahead) Monthly Average Ancillary Service Procurement Average Procurred Average Price Reg Up Reg Dn Spinning Non-Spinning Reg Up Reg Dn Spinning Non-Spinning Dec $5.68 $3.26 $2.44 $.9 Nov $6.4 $3.6 $3.6 $.12 Percent Change -1.11%.28% 3.25% 3.12% -5.9% 6.68% -2.28% % The monthly average prices increased for regulation down in December. Figure 12 shows the daily IFM average ancillary service prices. The prices were relatively stable this month. Figure 12: IFM (Day-Ahead) Ancillary Service Average Price Non-Spinning Regulation Down Regulation Up Spinning Market Performance Report Page 14 of 43

15 $/MWh Ancillary Service Cost to Load The monthly average cost to load sank to $.21/MWh in December from $.24/MWh in November. Figure 13: System (Day-Ahead and Real-Time) Average Cost to Load $.4 $.35 $.3 $.25 $.2 $.15 $.1 $.5 $. Spinning Non-Spinning Regulation Down Regulation Up Monthly Average Scarcity Events Reserve scarcity pricing is a mechanism that will allow prices for reserves and energy to rise automatically when there is inadequate supply in the market to meet the minimum procurement requirements of reserves and regulation on the ISO grid. The ancillary services scarcity pricing mechanism is triggered when the California ISO is not able to procure the target quantity of one or more ancillary services in the IFM and real-time market runs. There were no scarcity events in December. Market Performance Report Page 15 of 43

16 $/MWh 1-Nov MW Convergence Bidding Figure 14 below shows the daily average volume of cleared virtual bids in IFM for virtual supply and virtual demand. The cleared virtual supply was well above the cleared virtual demand in the middle of December and late December Figure 14: Cleared Virtual Bids Virtual Demand Virtual Supply Convergence bidding tends to cause the day-ahead market and real-time market prices to move closer together, or converge. Figure 15 shows the energy prices (namely the energy component of the LMP) in IFM, HASP, FMM, and RTD Figure 15: IFM, HASP, FMM, and RTD Prices IFM HASP FMM RTD Market Performance Report Page 16 of 43

17 Profit (Thousands) Figure 16 shows the profits that convergence bidders receive from convergence bidding. The total profits from convergence bidding increased to $2.81 million in December from $.41 million in November. The profit on December 25 was high when the real-time prices were much lower than day-ahead prices and the cleared virtual supply was well above the cleared virtual demand in a couple of hours. $2,5 $2, Figure 16: Convergence Bidding Profits $1,5 $1, $5 $ -$5 Renewable Generation Curtailment Figure 17 below shows the monthly wind and solar VERs (variable energy resource) curtailment due to system wide condition or local congestion in FMM. Figure 18 shows the monthly wind and solar VERs (variable energy resource) curtailment by resource type in FMM. Economic curtailment is defined as the resource s dispatch upper limit minus its FMM schedule when the resource has an economic bid. Dispatch upper limit is the maximum level the resource can be dispatched to when various factors are take into account such as forecast, maximum economic bid, generation outage, and ramping capacity. Selfschedule curtailment is defined as the resource s self-schedule minus its FMM schedule when FMM schedule is lower than self-schedule. When a VER resource is exceptionally dispatched, then exceptional dispatch curtailment is defined as the dispatch upper limit minus the exceptional dispatch value. As Figure 17 and Figure 18 below indicate, the renewable curtailment declined since May 215. Most of the curtailment were economic curtailment or solar curtailment. Market Performance Report Page 17 of 43

18 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 MWh May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 MWh 35, 3, 25, 2, 15, 1, 5, Figure 17: Renewable Curtailment by Reason Economic Local Economic System Exceptional Dispatch Local Exceptional Dispatch System Self Schedule Local Self Schedule System 35, 3, 25, 2, 15, 1, 5, Figure 18: Renewable Curtailment by Resource Type Economic wind Exceptional Dispatch Wind Self Schedule Wind Economic Solar Exceptional Dispatch Solar Self Schedule Solar Market Performance Report Page 18 of 43

19 Thousands Indirect Market Performance Metrics Bid Cost Recovery Figure 19 shows the daily uplift costs due to exceptional dispatch payments. The monthly uplift costs in December went up to $227,17 from $117,555 in November. Figure 19: Exceptional Dispatch Uplift Costs $2 $15 $1 $5 $ -$5 -$1 -$15 -$2 Figure 2 shows the allocation of bid cost recovery payment in the IFM, RUC and RTM markets. The total bid cost recovery for December fell to $4.99 million from $6.29 million in November. Out of the total monthly bid cost recovery payment for the three markets in December, the IFM market contributed 26 percent, RTM contributed 63 percent, and RUC contributed 11 percent of the total bid cost recovery payment. Market Performance Report Page 19 of 43

20 Nov Figure 2: Bid Cost Recovery Allocation $.5 $.45 $.4 $.35 $.3 $.25 $.2 $.15 $.1 $.5 $. ($.5) IFM RUC RTM Figure 21 and Figure 22 show the daily and monthly BCR cost by local capacity requirement area (LCR) respectively. Figure 21: Bid Cost Recovery Allocation by LCR $.5 $.45 $.4 $.35 $.3 $.25 $.2 $.15 $.1 $.5 $. Bay Area Big Creek-Ventura Fresno Humboldt LA Basin NCNB Other San Diego-IV Sierra Stockton Kern Market Performance Report Page 2 of 43

21 Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra Stockton Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra Figure 22: Monthly Bid Cost Recovery Allocation by LCR $2. $1.8 $1.6 $1.4 $1.2 $1. $.8 $.6 $.4 $.2 $. ($.2) Nov-15 Dec-15 IFM RUC RTM Figure 23 and Figure 24 show the daily and monthly BCR cost by utility distribution company (UDC) respectively. Figure 23: Bid Cost Recovery Allocation by UDC $.5 $.45 $.4 $.35 $.3 $.25 $.2 $.15 $.1 $.5 $. PGAE SCE SDGE Other NCPA Market Performance Report Page 21 of 43

22 NCPA Other PGAE SCE SDGE NCPA Other PGAE SCE SDGE Figure 24: Monthly Bid Cost Recovery Allocation by UDC $4.5 $4. $3.5 $3. $2.5 $2. $1.5 $1. $.5 $. Nov-15 Dec-15 IFM RUC RTM Figure 25 shows the cost related to BCR by type in RUC. RUC cost in December was mainly driven by minimum load cost. $25, Figure 25: Cost in RUC $2, $15, $1, $5, $ RUC_MLC RUC_SUC Market Performance Report Page 22 of 43

23 Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra Stockton Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra 1-Nov Figure 26 and Figure 27 show the daily and monthly cost related to BCR by type and LCR in RUC respectively. $.25 $.2 $.15 Figure 26: Cost in RUC by LCR $.1 $.5 $. Bay Area Big Creek-Ventura Fresno Humboldt LA Basin NCNB Other San Diego-IV Sierra Stockton Kern Figure 27: Monthly Cost in RUC by LCR $.6 $.5 $.4 $.3 $.2 $.1 $. Nov-15 Dec-15 ruc_mlc ruc_suc Market Performance Report Page 23 of 43

24 NCPA Other PGAE SCE SDGE NCPA Other PGAE SCE SDGE 1-Nov Figure 28 and Figure 29 show the daily and monthly cost related to BCR by type and UDC in RUC respectively. $.25 Figure 28: Cost in RUC by UDC $.2 $.15 $.1 $.5 $. $.7 $.6 $.5 PGAE SCE SDGE Other NCPA Figure 29: Monthly Cost in RUC by UDC $.4 $.3 $.2 $.1 $. Nov-15 Dec-15 ruc_mlc ruc_suc Market Performance Report Page 24 of 43

25 Nov Figure 3 shows the cost related to BCR by type in RT. Minimum load cost and energy cost contributed mostly to the RT cost in December. $.6 $.5 $.4 $.3 $.2 $.1 $. -$.1 -$.2 -$.3 Figure 3: Cost in RT RT_MLC RT_ENERGY RT_AS_COST RT_SUC RT_PUMP_COST RUC_TRANSITION_COST Figure 31 and Figure 32 show the daily and monthly cost related to BCR by type and LCR in RT respectively. $.6 $.5 $.4 $.3 $.2 $.1 $. -$.1 -$.2 -$.3 Figure 31: Cost in RT by LCR Bay Area Big Creek-Ventura Fresno Humboldt LA Basin NCNB Other San Diego-IV Sierra Stockton Kern Market Performance Report Page 25 of 43

26 Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra Stockton Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra Figure 32: Monthly Cost in RT by LCR $4. $3. $2. $1. $. ($1.) ($2.) Nov-15 Dec-15 rt_energy rt_mlc rt_suc rt_as_cost rt_transition_cost rt_pump_cost Figure 33 and Figure 34 show the daily and monthly cost related to BCR by type and UDC in RT respectively. Figure 33: Cost in RT by UDC $.6 $.5 $.4 $.3 $.2 $.1 $. -$.1 -$.2 -$.3 PGAE SCE SDGE Other NCPA Market Performance Report Page 26 of 43

27 Dec NCPA Other PGAE SCE SDGE NCPA Other PGAE SCE SDGE Figure 34: Monthly Cost in RT by UDC $6. $5. $4. $3. $2. $1. $. ($1.) ($2.) Nov-15 Dec-15 rt_energy rt_mlc rt_suc rt_as_cost rt_transition_cost rt_pump_cost Figure 35 shows the cost related to BCR by type in IFM. Minimum Load cost and energy cost contributed mostly to the cost in IFM in December. $1.2 $1. $.8 $.6 $.4 $.2 $. -$.2 Figure 35: Cost in IFM IFM_TRANSITION_COST IFM_MLC IFM_ENERGY IFM_SUC IFM_PUMP_COST IFM_AS_BID_COST Market Performance Report Page 27 of 43

28 Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra Stockton Bay Area Big Creek-Ventura Fresno Humboldt Kern LA Basin NCNB Other San Diego-IV Sierra 1-Nov Figure 36 and Figure 37 show the daily and monthly cost related to BCR by type and location in IFM respectively. Figure 36: Cost in IFM by LCR $1.2 $1. $.8 $.6 $.4 $.2 $. -$.2 Bay Area Big Creek-Ventura Fresno Humboldt LA Basin NCNB Other San Diego-IV Sierra Stockton Kern Figure 37: Monthly Cost in IFM by LCR $3.5 $3. $2.5 $2. $1.5 $1. $.5 $. ($.5) Nov-15 Dec-15 ifm_energy ifm_mlc ifm_suc ifm_as_bid_cost ifm_transition_cost ifm_pump_cost Market Performance Report Page 28 of 43

29 NCPA Other PGAE SCE SDGE NCPA Other PGAE SCE SDGE 1-Nov Figure 38 and Figure 39 show the daily and monthly cost related to BCR by type and UDC in IFM respectively. $1.2 $1. $.8 Figure 38: Cost in IFM by UDC $.6 $.4 $.2 $. -$.2 PGAE SCE SDGE Other NCPA Figure 39: Monthly Cost in IFM by UDC $5 $4 $4 $3 $3 $2 $2 $1 $1 $ -$1 Nov-15 Dec-15 ifm_energy ifm_mlc ifm_suc ifm_as_bid_cost ifm_transition_cost ifm_pump_cost Market Performance Report Page 29 of 43

30 $ Real-time Imbalance Offset Costs Figure 4 shows the daily real-time energy and congestion imbalance offset costs. Real-time energy offset cost inched up to $1.98 million in December from $1.75 million in November. Real-time congestion offset cost rose to $4.1 million in December from $.57 million in November. 1.5 Figure 4: Real-Time Energy and Congestion Imbalance Offset RT_ENGY_OFFSET RT_CONG_OFFSET Market Performance Report Page 3 of 43

31 Market Software Metrics Market performance can be confounded by software issues, which vary in severity levels with the failure of a market run being the most severe. Market Disruption A market disruption is an action or event that causes a failure of an ISO market, related to system operation issues or system emergencies. 2 Pursuant to section of the ISO tariff, the ISO can take one or more of a number of specified actions to prevent a market disruption, or to minimize the extent of a market disruption. There were a total of 5 market disruptions in December. Table 6 lists the number of market disruptions and the number of times that the ISO removed bids (including self-schedules) in any of the following markets in this month. The ISO markets include IFM, RUC, FMM and RTD processes. Type of CAISO Market Table 6: Summary of Market Disruption Market Disruption or Reportable Events Removal of Bids (including Self-Schedules) Day-Ahead IFM RUC Real-Time FMM Interval 1 1 FMM Interval 2 5 FMM Interval 3 2 FMM Interval 4 5 Real-Time Dispatch 28 Figure 41 shows the frequency of IFM, HASP (FMM interval 2), FMM (intervals 1, 3 and 4), and RTD failures. On December 19, one HASP, five FMM and seven RTD disruptions occurred due to the application problem. 2 These system operation issues or system emergencies are referred to in Sections 7.6 and 7.7, respectively, of the ISO tariff. Market Performance Report Page 31 of 43

32 Figure 41: Frequency of Market Disruption HASP FMM RTD Market Performance Report Page 32 of 43

33 Thousands MWh Per Day Manual Market Adjustment Exceptional Dispatch Figure 42 shows the daily volume of exceptional dispatches, broken out by market type: day-ahead, real-time incremental dispatch and real-time decremental dispatch. Generally, all day-ahead exceptional dispatches are unit commitments at the resource physical minimum. The real-time exceptional dispatches are among one of the following types: i) a unit commitment at physical minimum, ii) an incremental dispatch above the day-ahead schedule, and iii) a decremental dispatch below the day-ahead schedule. The total volume of exceptional dispatch in December increased to 44,558 MWh from 31,728 MWh in November. Figure 42: Total Exceptional Dispatch Volume (MWh) by Market Type Day-Ahead Real-Time INC Real-Time DEC Figure 43 shows the volume of the exceptional dispatch broken out by reason. 3 The majority of the exceptional dispatch volumes in December were driven by planned transmission outage and constraint (33 percent), operating procedure number and constraint (31 percent), software limitation (15 percent), and voltage support (8 percent). 3 For details regarding the reasons for exceptional dispatch please read the white paper on exceptional dispatch published on the ISO website: Market Performance Report Page 33 of 43

34 Nov Thousands MWh Per Day Figure 43: Total Exceptional Dispatch Volume (MWh) by Reason Load Forecast Uncertainty Voltage Support Planned Transmission Outage and Constraint Software Limitation Other Conditions beyond the control of the CAISO Contingency Dispatch Operating Procedure Number and Constraint Incomplete or Inaccurate Transmission Figure 44 shows the total exceptional dispatch volume as a percent of load, along with the monthly average. The monthly average percentage rose to.24 percent in December from.19 percent in November. 1.4% 1.2% 1.%.8%.6%.4%.2%.% Figure 44: Total Exceptional Dispatch as Percent of Load Percent Monthly Average Market Performance Report Page 34 of 43

35 $/MWh Energy Imbalance Market On November 1, 214, the California Independent System Operator Corporation (CAISO) and Portland based PacifiCorp fully activated the Energy Imbalance Market (EIM). This real-time market is the first of its kind in the West. EIM covers six western states: California, Oregon, Washington, Utah, Idaho and Wyoming. On December 1, 215, NV Energy, the Nevada-based utility successfully began participating in the western Energy Imbalance Market (EIM). With the addition of NV Energy, the EIM expands into Nevada, where the utility serves 2.4 million customers. The CAISO real-time market is now in seven states, saving millions of dollars for consumers. The newly expanded marketplace enables the CAISO and participants to incorporate thousands of megawatts of variable generating resources, such as wind and solar, into the power grid while reducing greenhouse emissions, and improving grid resiliency and reliability. Figure 45 shows daily simple average ELAP prices for PacifiCorp east (PACE), PacifiCorp West (PACW) and NV Energy (NEVP) for all hours in FMM. On December 25, PACE and NEVP prices were depressed due to binding EIM transfer constraint between PACE and PACW Figure 45: EIM Simple Average LAP Prices (All Hours) in FMM PACE PACW NEVP Figure 46 shows daily simple average ELAP prices for PACE, PACW and NEVP for all hours in RTD. PACE and NEVP prices were depressed on December 25 due to binding EIM transfer constraint between PACE and PACW. Market Performance Report Page 35 of 43

36 Frequency 1-Nov $/MWh Figure 46: EIM Simple Average LAP Prices (All Hours) in RTD PACE PACW NEVP Figure 47 shows the daily price frequency for prices above $25/MWh and negative prices in FMM for PACE, PACW and NEVP. The cumulative frequency of prices above $25/MWh decreased to percent from.3 percent in November. The cumulative frequency of negative prices increased to 1.24 percent in December from.69 percent in November. Figure 47: Daily Frequency of EIM LAP Positive Price Spikes and Negative Prices in FMM 2.%.% -2.% -4.% -6.% -8.% -1.% -12.% -14.% <=-$25 $(-1, -25] $(-4,-1] $(-2,-4] $(,-2] $[25,5) $[5,75) $[75,1) $[1,3] Figure 48 shows the daily price frequency for prices above $25/MWh and negative prices in RTD for PACE, PACW and NEVP. The cumulative frequency of prices above $25/MWh edged down to.5 percent in December from.6 percent in November. The cumulative frequency of negative prices decreased to 3.2 percent in December from 8.39 percent in November. Market Performance Report Page 36 of 43

37 MWh 1-Nov Frequency Figure 48: Daily Frequency of EIM LAP Positive Price Spikes and Negative Prices in RTD 5.%.% -5.% -1.% -15.% -2.% -25.% -3.% -35.% -4.% <=-$25 $(-1, -25] $(-4,-1] $(-2,-4] $(,-2] $[25,5) $[5,75) $[75,1) $[1,3] Figure 49 shows the daily volume of EIM transfer between CAISO and PacifiCorp in FMM. Figure 5 shows the daily volume of EIM transfer between PACE and PACW in FMM. The EIM transfer from PacifiCorp to CAISO fell in early December and then trended upward in the rest days of December. The EIM transfer from PACE to PACW dropped in the first half of December and then increased generally in the second half of this month. 6, 5, 4, 3, 2, 1, -1, -2, -3, Figure 49: EIM Transfer between CAISO and PAC in FMM CAISO to PACW PACW to CAISO Market Performance Report Page 37 of 43

38 MWh 1-Nov MWh Figure 5: EIM Transfer between PACE and PACW in FMM 3, 2,5 2, 1,5 1, 5 PACE to PACW Figure 51 shows the daily volume EIM transfer between CAISO and NEVP in FMM. Figure 52 shows the daily volume EIM transfer between PACE and NEVP in FMM. Most EIM transfer between PACE and NEVP was from PACE to NEVP. 6, 4, 2, Figure 51: EIM Transfer between CAISO and NEVP in FMM -2, -4, -6, -8, CAISO to NEVP NEVP to CAISO Market Performance Report Page 38 of 43

39 MWh MWh 8, 6, 4, Figure 52: EIM Transfer between PACE and NEVP in FMM 2, -2, -4, NEVP to PACE PACE to NEVP Figure 53 shows the daily volume of EIM transfer between CAISO and PacifiCorp in RTD. Figure 54 shows the daily volume of EIM transfer between PACE and PACW in RTD. The EIM transfer from PacifiCorp to CAISO dropped in early December and then increased generally in the rest days of December. The EIM transfer from PACE to PACW decreased in the first half of December and increased in the second half of this month. 6, 5, 4, 3, 2, 1, -1, -2, -3, -4, Figure 53: EIM Transfer between CAISO and PAC in RTD CAISO to PACW PACW to CAISO Market Performance Report Page 39 of 43

40 MWh 1-Nov MWh 3,5 3, 2,5 2, 1,5 1, 5 Figure 54: EIM Transfer between PACE and PACW in RTD PACE to PACW Figure 55 shows the daily volume EIM transfer between CAISO and NEVP in RTD. Figure 56 shows the daily volume EIM transfer between PACE and NEVP in RTD. Most EIM transfer between PACE and NEVP was from PACE to NEVP. 8, 6, 4, 2, -2, -4, Figure 55: EIM Transfer between CAISO and NEVP in RTD -6, CAISO to NEVP NEVP to CAISO Market Performance Report Page 4 of 43

41 MWh Figure 56: EIM Transfer between PACE and NEVP in RTD 8, 7, 6, 5, 4, 3, 2, 1, -1, -2, -3, NEVP to PACE PACE to NEVP Figure 57 shows daily real-time imbalance energy offset cost (RTIEO) for PACE, PACW, and NEVP respectively. Total RTIEO for PACE and PACW was -$1.26 million in December, decreasing from -$.4 million in November. The RTIEO for NEVP in December was $6.11 million. Therefore total RTIEO for EIM area was $4.85 million. $2.5 $2. $1.5 Figure 57: EIM Real-Time Imbalance Energy Offset by Area $1. $.5 $. -$.5 -$1. PACE PACW NEVP Figure 58 shows daily real-time congestion offset cost (RTCO) for PACE, PACW, and NEVP respectively. Total RTCO for PACE and PACW inched up to -$.71 million in December from -$.78 million in November. The RTCO for NEVP in December was -$.19 million. Total RTCO for EIM area was -$.9 million. Market Performance Report Page 41 of 43

42 Nov Figure 58: EIM Real-Time Congestion Imbalance Offset by Area $.3 $.2 $.1 $. -$.1 -$.2 -$.3 -$.4 PACE PACW NEVP Figure 59 shows daily bid cost recovery for PACE, PACW, and NEVP respectively. Total BCR for PACE and PACW rose to $.16 million in December from $.11 million in November. The BCR for NEVP in December was $.62 million. Total BCR for EIM area was $.78 million. $.25 Figure 59: EIM Bid Cost Recovery by Area $.2 $.15 $.1 $.5 $. PACE PACW NEVP Market Performance Report Page 42 of 43

43 The ISO s Energy Imbalance Market Business Practice Manual 4 describes the methodology for determining whether an EIM Participating Resource is dispatched to support transfers to serve California load. The methodology ensures that the dispatch considers the combined energy and associated marginal greenhouse gas (GHG) compliance cost based on submitted bids 5. In the first two months of EIM operations (November and December 214), EIM startup issues related to processing GHG bid adder resulted in the dispatch of coal generation to support transfers into California. Once GHG bid adders were properly accounted for, beginning in January 215, almost all of the EIM dispatches to support transfers into the ISO were from resources other than coal, as documented in Table 7 below. Table 7: EIM Transfer into CAISO by Fuel Type Month Coal (%) Gas (%) Non-Emitting (%) Total 14-Nov 3.66% 11.11% 85.23% 1% 14-Dec 24.18% 1.78% 65.4% 1% 15-Jan.7% 6.22% 93.71% 1% 15-Feb.32% 88.69% 1.99% 1% 15-Mar.46% 99.54%.% 1% 15-Apr.13% 65.48% 34.39% 1% 15-May.% 84.37% 15.62% 1% 15-Jun.% 72.95% 27.5% 1% 15-Jul.% 65.16% 34.84% 1% 15-Aug.2% 86.48% 13.51% 1% 15-Sep.% 92.27% 7.73% 1% 15-Oct.1% 99.9%.% 1%.% 25.25% 74.75% 1%.% 15.79% 84.21% 1% 4 See the Energy Imbalance Market Business Practice Manual for a description of the methodology for making this determination, which begins on page Imbalance Market. 5 A submitted bid may reflect that a resource is not available to support EIM transfers to California. Market Performance Report Page 43 of 43

Market Performance Report January 2016

Market Performance Report January 2016 Market Performance Report January 216 February 29, 216 ISO Market Quality and Renewable Integration CAISO 25 Outcropping Way Folsom, California 9563 (916) 351-44 Executive Summary 1 The market performance

More information

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way California Independent System Operator October 30, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

_ Dear Secretary Bose: The attached. Folsom, CA

_ Dear Secretary Bose: The attached. Folsom, CA California Independent System Operator June 29, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009 Midwest ISO Overview - ATC Customer Meeting February 26, 2009 Agenda Overview January 2009 Dashboard Module E RAR Timeline Questions 2 Overview January was characterized by seasonal cold temperatures,

More information

Slow Response Local Capacity Resource Assessment CAISO-CPUC Joint Workshop

Slow Response Local Capacity Resource Assessment CAISO-CPUC Joint Workshop Slow Response Local Capacity Resource Assessment CAISO-CPUC Joint Workshop October 4, 2017 Revision as of 10/11/17: Revisions were made on page 62 and page 64 is marked for deletion ISO Public REVISED

More information

Release Notes. OASIS Fall 2015 Application Release Version 1.0

Release Notes. OASIS Fall 2015 Application Release Version 1.0 Release Notes OASIS Fall 2015 Application Release 6.8.0 Version 1.0 September 17, 2015 REVISION HISTORY VERSION NO. DATE DESCRIPTION 1.0 09/17/2015 Initial version Page 2 of 12 Release Identification Application/System

More information

Powerex EIM Implementation Informational Call. Mark Holman, Powerex Don Tretheway, California ISO October 3, 2017

Powerex EIM Implementation Informational Call. Mark Holman, Powerex Don Tretheway, California ISO October 3, 2017 Powerex EIM Implementation Informational Call Mark Holman, Powerex Don Tretheway, California ISO October 3, 2017 Agenda Time Topic Presenter 9:00 9:05 Introduction Kristina Osborne, ISO 9:05 10:05 Powerex

More information

Contingency Modeling Enhancements Prototype Analysis with Production Cases

Contingency Modeling Enhancements Prototype Analysis with Production Cases August 17, 2017 Table of contents 1. Executive summary... 4 2. Purpose... 4 3. Analysis of stressed system scenarios... 5 Methodology... 5 Non-binding scenarios... 6 Binding scenario... 7 Other observations...

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 17. Transmission Ownership Rights (TORs)... 2 17.1 TRTC Instructions... 2 17.1.1 Responsibility to Create TRTC Instructions... 2 17.1.2 TOR Scheduling Coordinator Responsibilities...

More information

Energy Imbalance Market Technical Workshop. BAA Real-Time Congestion Balancing Account August 12, 2013

Energy Imbalance Market Technical Workshop. BAA Real-Time Congestion Balancing Account August 12, 2013 Energy Imbalance Technical Workshop BAA Real-Time Congestion Balancing Account August 12, 2013 Overview BAA Real-Time Congestion Balancing Account Real Time Convergence Bid Settlement Slide 2 BAA Real-Time

More information

Table of Contents. Preface. SECTION 1 Introduction 1. SECTION 3 Operating Reserve 65. SECTION 2 Energy Market 17

Table of Contents. Preface. SECTION 1 Introduction 1. SECTION 3 Operating Reserve 65. SECTION 2 Energy Market 17 Table of Contents Table of Contents Preface SECTION 1 Introduction 1 Q3 2012 In Review 1 PJM Market Background 2 Conclusions 3 Role of MMU 6 Reporting 7 Monitoring 7 Market Design 8 Recommendations 8 Highlights

More information

Load Conformance Limiter Enhancement

Load Conformance Limiter Enhancement TECHNICAL BULLETIN December 28, 2016 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400 TECHNICAL BULLETIN Revision History Date Version Description Author December 28, 2016 1.0 Draft Proposal

More information

Residual Auction Revenue Rights Enhancement

Residual Auction Revenue Rights Enhancement Residual Auction Revenue Rights Enhancement Brian Chmielewski Sr. Analyst, Market Simulation Department Markets and Reliability Committee December 22, 2016 Solution Package Overview - Package A Proposed

More information

Residual Auction Revenue Rights

Residual Auction Revenue Rights Residual Auction Revenue Rights Brian Chmielewski Sr. Analyst, Market Simulation Department Market Implementation Committee November 2, 2016 Overview Auction Revenue Rights (ARRs) prorated in Stage 1B

More information

Residual Auction Revenue Rights

Residual Auction Revenue Rights Residual Auction Revenue Rights Brian Chmielewski Sr. Analyst, Market Simulation Department Markets and Reliability Committee November 17, 2016 Overview Auction Revenue Rights (ARRs) prorated in Stage

More information

This report is printed on recycled paper

This report is printed on recycled paper This 2015 Integrated Resource Plan Update Report is based upon the best available information at the time of preparation. The IRP action plan will be implemented as described herein, but is subject to

More information

Market Participant User Guide ISO Reliability Requirements Application (IRR UI)

Market Participant User Guide ISO Reliability Requirements Application (IRR UI) Market Participant User Guide ISO Reliability Requirements Application (IRR UI) Version 1 Last Revised: November 21, 2011 ISO Public 1 of 84 Table of Contents 1. Introduction... 5 1.1 Resource Adequacy

More information

BPM Proposed Revision Requests (PRR): Summary Report Attachment 2

BPM Proposed Revision Requests (PRR): Summary Report Attachment 2 Proposed Revision Requests (): Summary Report Attachment 2 TITLE Reliability Requirements TITLE 215 Details related to the Forbidden Operating Region (FOR) implementation 214 Tracking change for Scarcity

More information

Business Practice Manual Change Management Meeting

Business Practice Manual Change Management Meeting Business Practice Manual Change Management Meeting Name Chris Kirsten Date May 24, 2011 Web Address: https://www.webmeeting.att.com Meeting Number: 5114682337 Access code: 9842446 Teleconference Dial-in

More information

Interface Specification for OASIS

Interface Specification for OASIS Version: 3.06 Date: 03/28/2011 Author: Arul Jayaraman Technical Lead Interface Specification for OASIS Version: 3.06 04/15/2011 Revision History Date Version Description Author May 30, 2006 July 14, 2006

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

FNM Expansion Training Webinar

FNM Expansion Training Webinar FNM Expansion Training Webinar Cynthia Hinman Lead Client Trainer August 11, 2014 The information contained in these materials is provided for general information only and does not constitute legal or

More information

Data Release & Accessibility

Data Release & Accessibility Draft Final Proposal Data Release & Accessibility Phase 1: Transmission Constraints January 6, 2010 Jan-08-2010: To correct for minor edits that were inadvertently omitted, this revised copy was posted.

More information

Business Practice Manual for Managing Full Network Model. Version 1213

Business Practice Manual for Managing Full Network Model. Version 1213 Business Practice Manual for Managing Full Network Model Version 1213 Last Revised: January 3, 2018January 24, 2018 Approval History Approval Date: October 1, 2009 Effective Date: October 1, 2009 BPM Owner:

More information

Business Practice Manual for Managing Full Network Model. Version 910

Business Practice Manual for Managing Full Network Model. Version 910 Business Practice Manual for Managing Full Network Model Version 910 Last Revised: September 7November 16, 2016 Approval History Approval Date: October 1, 2009 Effective Date: October 1, 2009 BPM Owner:

More information

Workshop on PJM ARR and FTR Market 2012/2013

Workshop on PJM ARR and FTR Market 2012/2013 Workshop on PJM ARR and FTR Market 2012/2013 www.pjm.com PJM 2012 1 Training Objectives At the completion of this training, you should be able to Understand the concepts and principles of Auction Revenue

More information

Nigerian Telecommunications Sector

Nigerian Telecommunications Sector Nigerian Telecommunications Sector SUMMARY REPORT: Q4 and full year 2015 NATIONAL BUREAU OF STATISTICS 26th April 2016 Telecommunications Data The telecommunications data used in this report were obtained

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

Annual Policy Initiatives Roadmap Process Straw Proposal

Annual Policy Initiatives Roadmap Process Straw Proposal Annual Policy Initiatives Roadmap Process Straw Proposal July 18, 2017 Copyright 2017 Table of Contents 1 Introduction... 2 2 Proposal... 3 2.1 Policy Initiatives Catalog... 3 Stakeholder Comments... 4

More information

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012 CAISO Metering & Telemetry Requirements Jeremy Laundergan - Director, EnerNex November 8, 2012 Background and Overview Both federal and state regulatory authorities are advocating the participation of

More information

Nigerian Telecommunications (Services) Sector Report Q2 2016

Nigerian Telecommunications (Services) Sector Report Q2 2016 Nigerian Telecommunications (Services) Sector Report Q2 2016 01 SEPTEMBER 2016 Telecommunications Data The telecommunications data used in this report were obtained from the National Bureau of Statistics

More information

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Background Power Grid has evolved from a vertically integrated

More information

Southern California Edison. Leading the Way in Electricity TM

Southern California Edison. Leading the Way in Electricity TM Southern California Edison Leading the Way in Electricity TM Smart Metering Essentials at SCE End-Use Energy Reductions through Monitoring, Feedback, and Behavior Modification Precourt Institute for Energy

More information

Exhibit to Agenda Item #1a

Exhibit to Agenda Item #1a Exhibit to Agenda Item #1a Sandra Kopp Wednesday, Board Finance September & Audit 28, Committee 2011 Meeting and Special SMUD Board of Directors Meeting Budget 2018 Wednesday,, scheduled to begin at 5:00

More information

EIM Entity Readiness Criteria May 6, 2015

EIM Entity Readiness Criteria May 6, 2015 EIM Entity Readiness Criteria May 6, 2015 FERC Directive Regarding Readiness Criteria We therefore direct CAISO to submit a compliance filing within 60 days of issuance of this order, to revise the EIM

More information

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission The following White Paper proposes a draft methodology for determining the incremental amount of transfer capability that would be the basis for the quantity of Merchant Transmission CRRs to be allocated

More information

Business Practice Manual Change Management Meeting

Business Practice Manual Change Management Meeting Business Practice Manual Change Management Meeting Name Chris Kirsten Date August 23, 2011 Web Address: https://www.webmeeting.att.com Meeting Number: 5114682337 Access code: 9842446 Teleconference Dial-in

More information

Overview of DSASP; Telemetry/Communication Alternatives

Overview of DSASP; Telemetry/Communication Alternatives Overview of DSASP; Telemetry/Communication Alternatives The New York Independent System Operator Price Responsive Load Working Group May 12, 2010 Agenda Overview of DSASP Market Rules Current Communications/Telemetry

More information

Integrated Resource Planning April 20, 2010

Integrated Resource Planning April 20, 2010 Integrated Resource Planning April 20, 2010 Judy Stokey, Executive Government and External Affairs Jack McGinley, Development Director, Renewables Gary Smith, Project Director-Smart Technologies Presentation

More information

Frequently Asked Questions Real-Time Revenue Sufficiency Guarantee

Frequently Asked Questions Real-Time Revenue Sufficiency Guarantee Frequently Asked Questions Revenue Sufficiency Guarantee What is Revenue Sufficiency Guarantee (RSG)? Midwest ISO has the responsibility to ensure that adequate capacity is available and committed to meet

More information

Economic and Housing Market Trends and Outlook

Economic and Housing Market Trends and Outlook Economic and Housing Market Trends and Outlook Lawrence Yun, Ph.D. Chief Economist NATIONAL ASSOCIATION OF REALTORS Presentation to Memphis Area Association of REALTORS Memphis, TN April 2, 213 Forecast

More information

Business Requirements Specification

Business Requirements Specification Business Requirements Specification EIM Enhancements Winter 2017 Page 1 of 46 Revision History Date Version Description 7/31/2017 1.0 Create Document 8/15/2017 1.1 Include ESDER 1C for 9 BRQs that identified

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

Billing and Collection Agent Report For period ending January 31, To FCC Contract Oversight Sub-Committee. February 11, 2019

Billing and Collection Agent Report For period ending January 31, To FCC Contract Oversight Sub-Committee. February 11, 2019 Billing and Collection Agent Report For period ending January 31, 2019 To FCC Contract Oversight Sub-Committee February 11, 2019 Welch LLP - Chartered Professional Accountants 123 Slater Street, 3 rd floor,

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

GO15 Reliable & Sustainable Power Grids

GO15 Reliable & Sustainable Power Grids Travis Rouillard Markets & Distributed Resources GE Grid Solutions GO15 Reliable & Sustainable Power Grids April 13, 2016 Corporate Enterprise February 2014 1 2040 GLOBAL POPULATION: 9 billion INCREASED

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

Nigerian Telecommunications (Services) Sector Report Q3 2016

Nigerian Telecommunications (Services) Sector Report Q3 2016 Nigerian Telecommunications (Services) Sector Report Q3 2016 24 NOVEMBER 2016 Telecommunications Data The telecommunications data used in this report were obtained from the National Bureau of Statistics

More information

Markets Gateway Roadmap

Markets Gateway Roadmap Markets Gateway Roadmap As of April 17, 2018 www.pjm.com Background Markets Gateway allows users to submit information and obtain data needed to conduct business in the Day-Ahead, Regulation and Synchronized

More information

For Every Action There is An Equal and Opposite Reaction Newton Was an Economist - The Outlook for Real Estate and the Economy

For Every Action There is An Equal and Opposite Reaction Newton Was an Economist - The Outlook for Real Estate and the Economy For Every Action There is An Equal and Opposite Reaction Newton Was an Economist - The Outlook for Real Estate and the Economy Ted C. Jones, PhD Chief Economist Twitter #DrTCJ Mega Themes More Jobs Than

More information

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting Contingency Reserve Sharing; Ancillary Services Market Presented to the JCM Joint Stakeholder Meeting 1 Agenda Products and Nature of Current Services Contingency Reserve Sharing Group (CRSG) Agreement

More information

Response to Stakeholder Comments on Draft and Revised Draft Tariff Language CCE3 and RSI Clarifications

Response to Stakeholder Comments on Draft and Revised Draft Tariff Language CCE3 and RSI Clarifications Response to Stakeholder Comments on Draft and Revised Draft Tariff Language CCE3 and RSI Clarifications 30.4.1.1.6.1 Six Cities Placement of the phrase on an annual basis creates ambiguity. The Six Cities

More information

Economic Outlook. William Strauss Senior Economist and Economic Advisor Federal Reserve Bank of Chicago

Economic Outlook. William Strauss Senior Economist and Economic Advisor Federal Reserve Bank of Chicago Economic Outlook Illinois Public Pension Fund Association Hoffman Estates, IL February 16, 217 William Strauss Senior Economist and Economic Advisor Federal Reserve Bank of Chicago GDP expanded by 1.9%

More information

Strategic Reserve in Belgium Design and functioning

Strategic Reserve in Belgium Design and functioning Strategic Reserve in Belgium Design and functioning Andreas Tirez Director Technical functioning of the markets IAEE March 9, 2015 Paris 1 Strategic Reserve (SR) Generation capacity that is being closed,

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

More information

Contents:

Contents: Contents: Conventional/REO/Short Sale Single Family Sold Sold Properties by Cities - Properties Sold Supply Inventory Median Price Comparison by Year www.swflrealtors.com Page #. Single Family & Condo

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop a Successor to Existing Net Energy Metering Tariffs Pursuant to Public Utilities Code Section 2827.1,

More information

Regional Group Nordic GRID DISTURBANCE AND FAULT STATISTICS

Regional Group Nordic GRID DISTURBANCE AND FAULT STATISTICS Regional Group Nordic GRID DISTURBANCE AND FAULT STATISTICS Table contents Table contents Page 1 INTRODUCTION... 4 1.1 Contact persons... 5 1.2 Guidelines the statistics... 5 1.3 Voltage levels in the

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

MOD Transmission Reliability Margin Implementation Document

MOD Transmission Reliability Margin Implementation Document Transmission Margin Implementation Document Transmission Margin Implementation Document For NERC Page 1 of 7 Transmission Margin Implementation Document 1.0 Purpose The California Independent System Operator

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Urban Land Institute. November Make Your Move. Brian Beaulieu ITR Economics.

Urban Land Institute. November Make Your Move. Brian Beaulieu ITR Economics. Urban Land Institute November 212 Make Your Move Brian Beaulieu ITR Economics Results for 211 2 Duration Forecast Actual GDP 18 $13.525 $13.332 (-1.4%) US Ind Prod. 11 93.1 (12MMA) 93.8 (.8%) EU Ind. Prod.

More information

RELIABILITY AS A SERVICE FOR BUSINESS. by MidEnterprises, LLC

RELIABILITY AS A SERVICE FOR BUSINESS. by MidEnterprises, LLC RELIABILITY AS A SERVICE FOR BUSINESS by MidEnterprises, LLC THE OPPORTUNITY Less than 30% of commercial facilities have a reliable back-up power supply Only10-15% of those having existing installations

More information

MISO PJM Joint and Common Market Cross Border Transmission Planning

MISO PJM Joint and Common Market Cross Border Transmission Planning MISO PJM Joint and Common Market Cross Border Transmission Planning February 28, 2017 1 Agenda 2 Targeted Market Efficiency Projects 2-Year Coordinated System Plan Study FERC Order No. 1000 Interregional

More information

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Opening 2013/2014 Transmission Planning Process Stakeholder Meeting Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Yesterday s Agenda November 20 th Topic Opening Introduction

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

Data Miner 2 Release Notes Release 18.09

Data Miner 2 Release Notes Release 18.09 Data Miner 2 Release Notes Release 18.09 Release Date: September 24, 2018 New Features: 1. New feeds These feeds will be available from September 25, 2018 onwards Enhancements: Real Time Temperature Sets

More information

REPORT ON TELECOMMUNICATIONS SERVICE QUALITY WINDSTREAM FLORIDA, INC.

REPORT ON TELECOMMUNICATIONS SERVICE QUALITY WINDSTREAM FLORIDA, INC. REPORT ON TELECOMMUNICATIONS SERVICE QUALITY For WINDSTREAM FLORIDA, INC. Alachua, Brooker, High Springs, Melrose, and Waldo s February 4 March 14, 2008 Division of Service, Safety & Consumer Assistance

More information

Assessing Opportunities to Exploit Stranded Power

Assessing Opportunities to Exploit Stranded Power Assessing Opportunities to Exploit Stranded Power Andrew A. Chien *University of Chicago and Argonne National Laboratory w/ Fan Yang, Rich Wolski (UCSB), Victor Zavala, Kibaek Kim (Argonne) UCSB Institute

More information

AMI Applications at SDG&E Metering America March 24, 2009 Ted M. Reguly Smart Meter Program Director SDG&E

AMI Applications at SDG&E Metering America March 24, 2009 Ted M. Reguly Smart Meter Program Director SDG&E AMI Applications at SDG&E Metering America March 24, 2009 Ted M. Reguly Smart Meter Program Director SDG&E 2008 San Diego Gas & Electric Company. All copyright and trademark rights reserved About Sempra

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Energy Storage and Distributed Energy Resources Phase 2. Customer Partnership Group March 27, p.m. 2 p.m. (Pacific Standard Time)

Energy Storage and Distributed Energy Resources Phase 2. Customer Partnership Group March 27, p.m. 2 p.m. (Pacific Standard Time) Energy Storage and Distributed Energy Resources Phase 2 Customer Partnership Group March 27, 2018 1 p.m. 2 p.m. (Pacific Standard Time) Agenda Item Project Schedule Update New Baseline Requests - Submittal

More information

Reliability Coordinator Procedure

Reliability Coordinator Procedure No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...

More information

Customer Market Results Interface (CMRI) Interface Specification Fall 2016 Release

Customer Market Results Interface (CMRI) Interface Specification Fall 2016 Release Customer Market Results Interface (CMRI) Interface Specification Fall 2016 Release : 3.5.0 February 3, 2016 Revision History Date Description 10/23/2013 2.0 Initial document release related to the Spring

More information

DS3 Ambitious approach to future network requirements. Mo Cloonan Commission for Energy Regulation, Ireland

DS3 Ambitious approach to future network requirements. Mo Cloonan Commission for Energy Regulation, Ireland DS3 Ambitious approach to future network requirements Mo Cloonan Commission for Energy Regulation, Ireland 1 Overview Irish/N.Irish power system and policy objectives Operational challenges for Ireland-

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

The Vision Council Winds of Change

The Vision Council Winds of Change The Vision Council Winds of Change Brian Beaulieu CEO Preliminary 217 Forecast Results If you heard ITR a year ago 2 Duration Accuracy US GDP (data through Sep) 24 98.5% US Ind. Prod. (Dec) 24 96.8% Eur

More information

Sales Drop, Inventories Fell, Prices Climb

Sales Drop, Inventories Fell, Prices Climb 1 Economics.. -. - Sales (Millions of Units) -1. Sep-1 Dec-1 Mar-1 Jun-1 Sep-1 Dec-1 Mar-1 Jun-1 Sep-1.. Millions of Units Consensus *: Actual: * from Bloomberg. Record High:.2 mln (/) Percent Change from

More information

TSO-DSO RELATIONS IN THE FUTURE EUROPEAN POWER SYSTEM

TSO-DSO RELATIONS IN THE FUTURE EUROPEAN POWER SYSTEM TSO-DSO RELATIONS IN THE FUTURE EUROPEAN POWER SYSTEM Carlo SABELLI GO 15 San Francisco April 13 2016 42 TSOs in ENTSO-E the European Network for Transmission System Operators for Electricity 42 TSOs from

More information

Kenya at the tipping Point?

Kenya at the tipping Point? Kenya at the tipping Point? with a special focus on the ICT revolution and Mobile Money World Bank Economic Team Presentation by Jane Kiringai Nairobi December 2, 2010 Main messages 1 2 Kenya may now be

More information

Total Market Demand Wed Jul 26 Thu Jul 27 Fri Jul 28 Sat Jul 29 Sun Jul 30 Mon Jul 31 Tue Aug 01

Total Market Demand Wed Jul 26 Thu Jul 27 Fri Jul 28 Sat Jul 29 Sun Jul 30 Mon Jul 31 Tue Aug 01 MW July 26, 2017 - August 1, 2017 This report provides a summary of key market data from the IESO-administered markets. It is intended to provide a quick reference for all market stakeholders. It is composed

More information

CTIA s Wireless Metrics Reports

CTIA s Wireless Metrics Reports CTIA s Wireless Metrics Reports Bobby Franklin Executive Vice President CTIA-The Wireless Association April 30, 2009 Background on Semi-Annual Survey CTIA s survey began in January 1985 focusing on operational

More information

European Developments

European Developments European Developments Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Transmission Workgroup

More information

1.2 Characteristics of Function Graphs

1.2 Characteristics of Function Graphs 1.2 Characteristics of Function Graphs Essential Question: What are some of the attributes of a function, and how are they related to the function s graph? Resource Locker Explore Identifying Attributes

More information

E.ON UK plc Group Consolidated Segmental Report. for the year ended 31 December 2011

E.ON UK plc Group Consolidated Segmental Report. for the year ended 31 December 2011 E.ON UK plc Group Consolidated Segmental Report for the year ended 31 December 2011 In accordance with the Electricity Generation Licence Condition 16 - Financial Information Reporting and the Electricity

More information

ERCOT MARKET. PNUCC Larry Weis June 2, 2017

ERCOT MARKET. PNUCC Larry Weis June 2, 2017 ERCOT MARKET PNUCC Larry Weis June 2, 2017 1 AGENDA Overview Evolution ERCOT Wholesale Market/COUs Business Change Questions and Wrap-up 2 ELECTRIC RELIABILITY COUNCIL OF TEXAS (ERCOT) Manages the flow

More information

Seattle (NWMLS Areas: 140, 380, 385, 390, 700, 701, 705, 710) Summary

Seattle (NWMLS Areas: 140, 380, 385, 390, 700, 701, 705, 710) Summary November, 2016 MTD MARKET UPDATE Data Current Through: November, 2016 (NWMLS Areas: 140, 380, 385, 390,, 701, 705, 710) Summary 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 0 Active, Pending, & Months

More information

2016 Market Update. Gary Keller and Jay Papasan Keller Williams Realty, Inc.

2016 Market Update. Gary Keller and Jay Papasan Keller Williams Realty, Inc. 2016 Market Update Gary Keller and Jay Papasan Housing Market Cycles 1. Home Sales The Numbers That Drive U.S. 2. Home Price 3. Months Supply of Inventory 4. Mortgage Rates Real Estate 1. Home Sales Nationally

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

DAS LRS Monthly Service Report

DAS LRS Monthly Service Report DAS LRS Monthly Service Report Customer Service Manager : Diploma Aggregation Service : Daniel Ward Project/document reference : DAS LRS 2010-12 Issue : 1.0 Issue date : 17 th January 2011 Reporting Period

More information

App Economy Market analysis for Economic Development

App Economy Market analysis for Economic Development App Economy Market analysis for Economic Development Mustapha Hamza, ISET Com Director mustapha.hamza@isetcom.tn ITU Arab Forum on Future Networks: "Broadband Networks in the Era of App Economy", Tunis

More information

San Joaquin County Emergency Medical Services Agency

San Joaquin County Emergency Medical Services Agency San Joaquin County Emergency Medical Services Agency http://www.sjgov.org/ems Memorandum TO: All Interested Parties FROM: Rick Jones, EMS Analyst DATE: January, 19 Mailing Address PO Box French Camp, CA

More information

TRANSMISSION MAINTENANCE COORDINATION COMMITTEE (TMCC) MINUTES October 16, 2014 Meeting from the ISO Headquarters Folsom, California

TRANSMISSION MAINTENANCE COORDINATION COMMITTEE (TMCC) MINUTES October 16, 2014 Meeting from the ISO Headquarters Folsom, California TRANSMISSION MAINTENANCE COORDINATION COMMITTEE (TMCC) MINUTES October 16, 2014 Meeting from the ISO Headquarters Folsom, California Steve Rutty, Acting Chairperson of the Transmission Maintenance Coordination

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC Order 1000, 2018-19 Biennial Planning Cycle Quarter 2 Meeting June 14, 2018 PAGE 2 Agenda Pacific Time Topic Presenter 9:00 9:05 Greetings and

More information

Uninstructed Deviation Penalty Charge Types 4470, and 4480

Uninstructed Deviation Penalty Charge Types 4470, and 4480 Description Uninstructed Deviation Penalty Charge Types 4470, and 4480 This section of the Dispute Submittal Guide describes the information pertinent to charges for Uninstructed Deviation Penalties, specifically

More information

Table of Contents. TOP TOP BA Data Request and Specification Guidelines. Operating Procedure

Table of Contents. TOP TOP BA Data Request and Specification Guidelines. Operating Procedure No. 3140 Table of Contents Purpose... 2 Responsibilities... 2 2. Scope/Applicability... 4 2.1 Background... 4 2.2 Scope / Applicability... 4 3. Detail... 5 3.1... 5 Introduction... 5 3.2 Data Specification

More information

Real Estate Forecast 2017

Real Estate Forecast 2017 Real Estate Forecast 2017 Twitter @DrTCJ Non-Renewals - Dead on Arrival Mortgage Insurance Deductibility Residential Mortgage Debt Forgiveness Residential Energy Savings Renewables Wind and Solar ObamaCare

More information

Business Practice Manual Change Management Meeting

Business Practice Manual Change Management Meeting Business Practice Manual Change Management Meeting Name Chris Kirsten Date February 26, 2013 Web Address: https://www.webmeeting.att.com Meeting Number: 5114682337 Access code: 9842446 Teleconference Dial-in

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

Customer Market Results Interface (CMRI) Interface Specification Fall 2018Independent 2019 Release

Customer Market Results Interface (CMRI) Interface Specification Fall 2018Independent 2019 Release Customer Market Results Interface (CMRI) Interface Specification Fall 2018Independent 2019 Release : 3.8.12 September 6Feburary 6, 20182019 Revision History Date Description 10/23/2013 2.0 Initial document

More information