MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension
|
|
- Randolph Walters
- 5 years ago
- Views:
Transcription
1 MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 03/08/2018 Final Action Ahmad Fazel, DECM Executive Director Dan Abernathy, Executive Project Director Federal Way Link Extension Soraya Lowry, HCT Development Manager PROPOSED ACTION Authorizes the chief executive officer to increase Task Order 2 under the City Services Agreement between the City of Des Moines and Sound Transit for the Federal Way Link Extension in the amount of $236,700, with a 10% contingency of $23,670, for a total not to exceed amount of $385,370 for Task Order 2 and $566,870 for the City Services Agreement. KEY FEATURES SUMMARY The proposed action increases funding for services to be provided by the City of Des Moines for the Federal Way Link Extension during the Request for Proposals (RFP) finalization and the selection phase for the design-build contractor. This amendment will include: o Participating in the design-build contractor selection process as requested by Sound Transit. o o Completing a mutually agreeable staffing plan to support the project schedule. An option to fill key functions/positions needed for design review and permitting after notice to proceed is given to the design-build contractor to support the project schedule. This amendment revises the schedule for Task Order 2 through notice to proceed to the design-build contractor, currently anticipated for August Sound Transit will manage each task order under the agreement separately. Costs authorized under this action are for city staff and city consultant time. Staff will return to the Board, currently anticipated for Q3 of 2019, for approval of additional task orders relating to permitting and construction services to be provided by the City. BACKGROUND The Federal Way Link Extension adds approximately 7.8 miles of light rail from the Angle Lake light rail station at South 200th Street in the City of SeaTac to the Federal Way City Center area in Federal Way. The extension generally parallels State Route 99 (SR 99) and Interstate 5 (I-5), with stations at Kent/Des Moines, S 272nd Star Lake park and ride and the Federal Way Transit Center. New parking structures will be constructed at each of the three stations. Notice to proceed for the design-build contract is anticipated in 2019 and the project is planned to open for service in The Federal Way Link Final Environmental Impact Statement was issued on November 18, 2016 pursuant to the State Environmental Policy Act (SEPA) and National Environmental Policy Act (NEPA), completing the SEPA process. The Sound Transit Board selected the project route, profile, and stations on January 26, The Federal Transit Administration issued a Record of Decision on March 6, 2017 and the Federal Highway Administration issued a Record of Decision on March 9, 2017, completing the NEPA process.
2 In May 2017, the Capital Committee authorized 1) an umbrella City Services Agreement with the City of Des Moines to support expedited design, design review, permitting and construction services for the Federal Way Link Extension and 2) Task Order 1 for the Design-Build Request for Proposals Preparation Phase. The original Task Order 2 was authorized under the Executive Director s authority in the amount of $125,000. PROJECT STATUS Project Identification Alternatives Identification Conceptual Engineering Preliminary Engineering Final Design Construction Projected Completion Date for Preliminary Engineering Phase: 3Q 2019 Project scope, schedule, and budget summary located on page 75 of the December 2017 Light Rail Program Progress Report. FISCAL INFORMATION This action is within the authorized project allocation to date and sufficient funds remain after approval of this action to fund the anticipated remaining work in the third party phase as contained in the current cost estimates. The authorized project allocation to date for the Federal Way Link Extension is $412,625,000. Within that amount, $1,488,000 has been set aside in the City of Des Moines budget line item in the third party phase. The proposed action would commit an additional $260,370 to this line item, leaving a remaining uncommitted balance of $921,130. Federal Way Link Extension (in thousands) Project Phase Authorized Project Allocation to Date Board Approvals This Action Board Approved Plus Action Uncommitted / (Shortfall) Agency Administration $14,915 $9,415 $ $9,415 $5,500 Preliminary Engineering 43,409 43,086 43, Final Design 2, ,044 Third Party 18,646 3, ,739 14,907 Right of Way 274,085 13,712 13, ,373 Construction 13, ,524 Construction Services 45,672 5,065 5,065 40,607 Vehicles Total Current Budget $412,625 $75,087 $260 $75,347 $337,278 Phase Detail - Third Party City of Des Moines $1,488 $307 $260 $567 $921 Other Third Party 17,158 3,173 3,173 13,985 Total Phase $18,646 $3,479 $260 $3,739 $14,907 City of Des Moines Agreement Detail Proposed Total for Board Approval Board Approvals to Date Current Approved Agreement Status Proposed Action Agreement Amount $279 $279 $237 $515 Contingency Total Agreement Amount $307 $307 $260 $567 Percent Contingency 10% 10% 10% 10% Notes: Amounts are expressed in Year of Expenditure $000s. Board Approvals = Committed To-Date + Contingency as of Jan 2018, and includes pending Board actions. For detailed project information, see page 26 of the Proposed 2018 Transit Improvement Plan (TIP). Motion No. M Page 2 of 3 Staff Report
3 SMALL BUSINESS/DBE PARTICIPATION AND APPRENTICESHIP UTILIZATION Not applicable for this action. PUBLIC INVOLVEMENT Throughout the development of the Federal Way Link Expansion, Sound Transit has conducted extensive public involvement including mailings, community open houses, presentations and meetings with individuals and neighborhood groups. TIME CONSTRAINTS Delaying Task Order 2 could impact the City s availability to work with Sound Transit on the various RFP Finalization and Design-Build Selection activities defined in the task order. PRIOR BOARD/COMMITTEE ACTIONS Motion No. M : Authorized the chief executive officer to execute (1) a City Services Agreement with the City of Des Moines for expedited design, design review, permitting and construction services for the Federal Way Link Extension and (2) Task Order 1, for the design-build Request for Proposal preparation phase, in the amount of $165,000, and a 10% contingency of $16,500, for a total authorized amount not to exceed $181,500. ENVIRONMENTAL REVIEW PW 3/2/18 LEGAL REVIEW AJP 3/2/18 Motion No. M Page 3 of 3 Staff Report
4
5 MOTION NO. M A motion of the Capital Committee of the Central Puget Sound Regional Transit Authority authorizing the chief executive officer to increase Task Order 2 under the City Services Agreement between the City of Des Moines and Sound Transit for the Federal Way Link Extension in the amount of $236,700, with a 10% contingency of $23,670, for a total not to exceed amount of $385,370 for Task Order 2 and $566,870 for the City Services Agreement. BACKGROUND: The Federal Way Link Extension adds approximately 7.8 miles of light rail from the Angle Lake light rail station at South 200th Street in the City of SeaTac to the Federal Way City Center area in Federal Way. The extension generally parallels State Route 99 (SR 99) and Interstate 5 (I-5), with stations at Kent/Des Moines, S 272nd Star Lake park and ride and the Federal Way Transit Center. New parking structures will be constructed at each of the three stations. Notice to proceed for the design-build contract is anticipated in 2019 and the project is planned to open for service in The Federal Way Link Final Environmental Impact Statement was issued on November 18, 2016 pursuant to the State Environmental Policy Act (SEPA) and National Environmental Policy Act (NEPA), completing the SEPA process. The Sound Transit Board selected the project route, profile, and stations on January 26, The Federal Transit Administration issued a Record of Decision on March 6, 2017 and the Federal Highway Administration issued a Record of Decision on March 9, 2017, completing the NEPA process. In May 2017, the Capital Committee authorized 1) an umbrella City Services Agreement with the City of Des Moines to support expedited design, design review, permitting and construction services for the Federal Way Link Extension and 2) Task Order 1 for the Design-Build Request for Proposals Preparation Phase. The original Task Order 2 was authorized under the Executive Director s authority in the amount of $125,000. The proposed action increases funding for services to be provided by the City of Des Moines for the Federal Way Link Extension during the Request for Proposals (RFP) finalization and the selection phase for the design-build contractor. This amendment covers the City s participation in the design-build contractor selection process as requested by Sound Transit, completion of a mutually agreeable staffing plan to support the project schedule and an option to fill key functions/positions needed for design review and permitting after notice to proceed is given to the design-build contractor to support the project schedule. The amendment revises the schedule for Task Order 2 through notice to proceed to the design-build contractor, currently anticipated for August Sound Transit will manage each task order under the agreement separately. Costs authorized under this action are for city staff and city consultant time. Staff will return to the Board, currently anticipated for Q3 of 2019, for approval of additional task orders relating to permitting and construction services to be provided by the City.
6
MOTION NO. M Contract Amendment for Technology Software, Hardware, and Related Maintenance Services
MOTION NO. M2017-67 Contract Amendment for Technology Software, Hardware, and Related Maintenance Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee 05/04/2017
More informationRecommendation to Board. Final Action
MOTION NO. M2017-59 City of Seattle Center City Mobility Plan Agreement MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 05/04/2017 05/25/2017 Recommendation
More informationMOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension
MOTION NO. M2014-79 Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital
More informationRecommendation to Board. Final Action
MOTION NO. M2017-142 Ratification and contract for Tukwila traction power sub-station repairs MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee Board 12/7/2017 12/21//2017
More informationMEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE:
MOTION NO. M2014-04 Contract for On-call Sustainability Consulting Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: Operations and Administration Committee PROPOSED ACTION 03/06/14 Final Action
More informationFigure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended
Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public
More informationS-03-SegB: South Federal Way to Fife LRT
Project Number S-03-SegB Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 4.0 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE
More informationCorridor Management Committee. January 12, 2017
Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major
More informationCITY OF VANCOUVER ADMINISTRATIVE REPORT
CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting
More informationMVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014
MVTA-Prior Lake-Shakopee Merger SCALE Presentation, October 10, 2014 MVTA Commitment Our Vision The Minnesota Valley Transit Authority is a trusted partner in transportation, serving as an innovative leader
More informationMetropolitan Council. Transportation Division Proposed Transit Capital Program
Metropolitan Council Transportation Division Proposed 2015-2020 Transit Capital Program Transportation Committee October 27, 2014 Goals of the 2015 Capital Program Simplify the process Standardize the
More informationStaff Report City of Manhattan Beach
Staff Report City of Manhattan Beach TO: Honorable Mayor Montgomery and Members of the City Council THROUGH: Geoff Dolan, City Manager FROM: Jim Arndt, Director of Public Works Dana Greenwood, City Engineer
More informationDallas Streetcar Central Link Locally Preferred Alternative Selection
Dallas Streetcar Central Link Locally Preferred Alternative Selection Mobility Solutions, Infrastructure & Sustainability Committee August 28, 2017 Tanya Brooks, Assistant Director Mobility and Street
More informationDulles Area Transportation Association
Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements
More informationSystem Expansion Implementation Plan. Board Meeting, April 2017
System Expansion Implementation Plan Board Meeting, April 2017 2016: A record-breaking year Opened 3 new light rail stations. Completed tunneling for 3 more. Broke ground on our longest extension to date.
More informationSUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17
Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11
More informationCONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT
35 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net CONSTRUCTION COMMITTEE NOVEMBER 20, 2014 SUBJECT: ACTION: CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT INCREASE
More informationSECTION 106 ACTIVITIES ANNUAL REPORT
SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The
More informationReston Town Center North Development. Community Update
Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive
More informationNORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance
NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY ITEM: 6B SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance Jacobs Engineering has completed Task 1 with amendment
More informationSECTION 106 ACTIVITIES ANNUAL REPORT
SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 11, 2016 SUBJECT: Request to ratify advertisement of public hearings by the Planning Commission and the County
More informationAGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.
AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting July 9, 2014 Executive Director Approval
More information12 Approval of a New PRESTO Agreement Between York Region and Metrolinx
Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO
More informationAGENDA 5. ALBERT ROBLES CENTER (ARC) DESIGN-BUILD PROJECT PROGRESS REPORT 6. ALBERT ROBLES CENTER (ARC) OUTREACH PROGRAMS UPDATE
CAPITAL IMPROVEMENT PROJECTS (CIP) COMMITTEE WATER REPLENISHMENT DISTRICT OF SOUTHERN CALIFORNIA 4040 PARAMOUNT BLVD., LAKEWOOD, CA. 90712 11:00 AM, WEDNESDAY, JULY 11, 2018 AGENDA Each item on the agenda,
More informationThe Blue Line Extension
The Blue Line Extension NORTH CAROLINA JOINT TRANSPORTATION OVERSIGHT COMMITTEE Presented by Carolyn Flowers CATS Chief Executive Officer Raleigh, NC February 10, 2012 Overview Charlotte Area Transit System
More informationCITY COUNCIL AGENDA REPORT
K.4 CITY COUNCIL AGENDA REPORT TYPE OF ITEM: Report AGENDA ITEM NO.: 4 DATE: November 13, 2018 TO: FROM: SUBJECT: City Council Rosemarie Gaglione Public Works Director Approval of First Amendment to Agreement
More informationCHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016
TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER SHIFT RAPID
More informationClick to edit Master title style Click to edit Master title style
Southwest Chief & Front Range Passenger Rail Commission Overview for Transportation Legislative Review Committee November 2, 2017 Presented by: Sal Pace Jacob Riger, AICP November 2, 2017 FIRST WE WERE
More informationVTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association
VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for
More informationBEVRLYRLY STAFF REPORT. Meeting Date: August 4, 2015 Item Number: To: From:
BEVRLYRLY STAFF REPORT Meeting Date: August 4, 215 Item Number: To: From: Honorable Mayor & City Council Mark Cuneo, City Engineer Aaron Kunz, Deputy Director of Transportation Subject: Update on Metro
More informationDue Diligence Checklist #20
INDEX Page Summary Implementation of TTC & Coroner s Jury Recommendations...i Coroner s Jury Recommendations... 1 Signals Design... 4 Note: This updated checklist contains updates to recommendations that
More information5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket
Clause 5 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 28, 2018. 5 Servicing Capacity Assignment
More informationMoving Forward with Transit Oriented Communities
Moving Forward with Transit Oriented Communities Planning & Development Committee October 7, 2014 Packet Pg. 33 History of TOD at RTD Mid 1990s - Local jurisdictions start planning for TOD 2000 RTD hires
More informationport Ager1da March 3, 2014 TO: Honorable Mayor and City Council FROM: Department of Information Technology
Ager1da port TO: FROM: SUBJECT: Honorable Mayor and City Council Department of Information Technology AUTHORIZATION TO ENTER INTO A CONTRACT WITH ARNOLD AND WALTERS TELECOMMUNICATIONS CONSULTANTS FOR FIBER
More informationPROJECT TIMELINE. Next steps. Plan. Start of Service
PROJECT TIMELINE 2018 2019 2020 2021 2022 2023 WE ARE HERE Plan Develop Build Develop design options for termini, station locations, and transit operations Conduct environmental research Assess funding
More informationATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n
RFP P5413 Contract No. 200703566 Work Order No. -07 ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n Prepared for: Metropolitan Atlanta Rapid Transit Authority Prepared by: DMJM Harris/JJG Joint
More informationCITY COUNCIL AGENDA REPORT
K.5 CITY COUNCIL AGENDA REPORT TYPE OF ITEM: Info/Consent AGENDA ITEM NO.: 5 DATE: December 6, 2016 TO: City Council THROUGH: Greg Nyhoff City Manager FROM: SUBJECT: Darwin Base Fire Chief Additional Appropriation
More informationITEM 43. Simpson dba Basecamp Environmental
ITEM 43 CITY MANAGER S REPORT MARCH 2 2015 CITY COUNCIL MEETING ITEM APPROVE TASK ORDERS 4 AND 5 TO THE MASTER AGREEMENT WITH CHARLES R SIMPSON DBA BASECAMP ENVIRONMENTAL RECOMMENDATION Adopt a Resolution
More informationMeeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.
TO WHOM IT MAY CONCERN: NOTICE OF RE-SCHEDULED BOARD MEETINGS This is notice that the re-scheduled meetings of the Board of Directors of the New Jersey Transit Corporation, NJ Transit Rail Operations,
More informationRESOLUTION NO Adopted by the Housing Authority of the City of Sacramento. December 3, 2013
RESOLUTION NO. 2013-0020 Adopted by the Housing Authority of the City of Sacramento December 3, 2013 WASHINGTON PLAZA APARTMENTS REHABILITATION ( PROJECT ): APPROVAL OF TERMINATION OF GROUND LEASE WITH
More informationSECTION 10 CONTRACTING FOR PROFESSIONAL SERVICES CONSULTANT COMPETITIVE NEGOTIATION ACT (CCNA)
SECTION 10 CONTRACTING FOR PROFESSIONAL SERVICES CONSULTANT COMPETITIVE NEGOTIATION ACT (CCNA) 10.0 INTRODUCTION The purpose of this procedure is to provide guidance for hiring professional firms for architectural,
More informationBicycle Access & Parking Plan Project List Review
Bicycle Access & Parking Plan Project List Review Bicycle Advisory Committee September 19th, 2013 Strategy Overview New Bicycle Issues and Ideas (BAC, staff, public) Funding External Agency Lead BAPP s
More informationCouncil of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013
Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility
More informationCity of Toronto Accessibility Design Guidelines 2015
RE: DI3.2 City of Toronto Accessibility Design Guidelines 2015 Update to Disability Issues Committee Presented By: Facilities Management Division June 2 nd, 2015 Presenters: Sunil Sharma, General Manager,
More informationProgram Management Office January, 2012
Program Management Office January, 2012 Clarify the Project Delivery Process (PDP) What is it? Why did it change? How were the changes determined? How was it approved? Show you where to get guidance Answer
More informationANNUAL ACCESSIBILITY STATUS REPORT
The Ontarians with Disabilities Act, 2001 The Accessibility for Ontarians with Disabilities Act, 2005 ANNUAL ACCESSIBILITY STATUS REPORT 2017 Township Council Accessibility Policy C-PD-03 Administrative
More informationGDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010
GDOT PowerPoint Title Page MMPT Technical Committee April 6, 2010 Introduction Senate Bill 200, enacted in May2009, revamped existing P3 enabling legislation This new legislative direction provides an
More informationDART s Program of Inter-Related Projects. Joint DART and Transportation and Trinity River Project Committee 10 November 2014
DART s Program of Inter-Related Projects Joint DART and Transportation and Trinity River Project Committee 10 November 2014 Outline Dallas CBD Second Alignment (D2) What s Changed Since 2006 Core Capacity
More informationMINNEAPOLIS PARK & RECREATION BOARD COMMUNITY ENGAGEMENT PLAN
Board Plan Approval/Review Date: 9/19/2017 Last Plan Revision Date: 9/5/2017 MINNEAPOLIS PARK & RECREATION BOARD COMMUNITY ENGAGEMENT PLAN Project Title: MPRB Division: Planning Project Manager: Dana Murdoch
More informationCONTRACT AWARD TO UDC, INC. FOR FIBER MANAGEMENT SOFTWARE IMPLEMENTATION AND DATA MIGRATION SERVICES
Agenda Report! TO: Honorable Mayor and City Council FROM: SUBJECT: Department of nformation Technology CONTRACT AWARD TO UDC, NC. FOR FBER MANAGEMENT SOFTWARE MPLEMENTATON AND DATA MGRATON SERVCES RECOMMENDATON:
More informationSCOPE OF SERVICES FIBER OPTIC NETWORK DESIGN CITY OF OVERLAND PARK, KANSAS
1.0 PROJECT ADMINISTRATION SCOPE OF SERVICES FIBER OPTIC NETWORK DESIGN CITY OF OVERLAND PARK, KANSAS Project Administration services shall consist of project management and other support services for
More informationA RESOLUTION. WHEREAS, On January 20, 2017, the inauguration of the 47th President of the United States of
RESOLUTION 2016-130 APPROVING AN AGREEMENT WITH WASHINGTON METROPOLITAN TRANSIT AUTHORITY TO PROVIDE UP TO TEN POLICE OFFICERS IN SUPPORT OF SECURITY MEASURES FOR THE 2017 PRESIDENTIAL INAUGURATION; AND
More informationAgenda Item No. AGENDA ITEM BRIEFING
AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval to Amend the FY 2016-FY 2020 Texas A&M University
More informationCITY OF VANCOUVER ADMINISTRATIVE REPORT
CITY OF VANCOUVER A11 ADMINISTRATIVE REPORT Report Date: May 3, 2007 Author: Dale Bracewell Phone No.: 604.871.6440 RTS No.: 06720 VanRIMS No.: 03-1200-11 Meeting Date: May 15. 2007 TO: FROM: SUBJECT:
More informationCITY OF MONTEBELLO SYSTEMS MANAGER
CITY OF MONTEBELLO 109A DEFINITION Under general administrative direction of the City Administrator, provides advanced professional support to departments with very complex computer systems, programs and
More informationNeutral Host Reimbursable Capital Project
Finance & Administration Committee Action Item III-E November 4, 2010 Neutral Host Reimbursable Capital Project Page 37 of 161 Washington Metropolitan Area Transit Authority Board Action/Information Summary
More informationMinutes - Standing Policy Committee on Finance - April 9, 2015 REPORTS
Minutes - Standing Policy Committee on Finance - April 9, 2015 REPORTS Item No. 4 Water Supervisory Control and Data Acquisition (SCADA) Upgrade Financial Status Report No. 1 for the Period from November
More informationC Line Rapid Bus 90% Design
C Line Rapid Bus 90% Design Karyssa Jackson, Community Outreach Coordinator Shawn Walding, Senior Engineer Metro Transit TAAC August 2, 2017 1 Today s Discussion Informational Feedback from February Project
More informationScoping Information Report
Scoping Information Report February 2019 To request accommodations for persons with disabilities or information in alternative formats, call 1-800-201-4900/TTY Relay: 711 or email accessibility@soundtransit.org.
More informationMetrolinx / Toronto Transit Plan April 28, Jack Collins Vice President, Rapid Transit Implementation
Metrolinx / Toronto Transit Plan April 28, 2011 Jack Collins Vice President, Rapid Transit Implementation 1 Overview 1. Principles in Developing the Plan 2. Metrolinx / Toronto Transit Plan 3. The Plan
More informationEILEEN WAGLEY (fka Hiltner/Pavlik) ParaCruz Eligibility Coordinator SANTA CRUZ METROPOLITAN TRANSIT DISTRICT
EILEEN WAGLEY (fka Hiltner/Pavlik) ParaCruz Eligibility Coordinator SANTA CRUZ METROPOLITAN TRANSIT DISTRICT Eileen has been working with the METROs ADA application and eligibility process since its inception
More informationCorridor Management Committee. December 17, 2014
Corridor Management Committee December 17, 2014 1 Today s Topics Technical Issues/Issue Resolution Process Environmental Consultant Contract Update Advisory Committees Community Advisory Committee Business
More informationExtract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017
Extract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017 Agenda Item 10.1 Scheduled Business 7. Funding for The Richmond Hill Centre for High-Tech Business Development (Staff
More informationTotal Grant Solution (TGS) Training Webinar for Grantees and Contractors. Office of Economic and Workforce Development San Francisco August 3, 2018
Total Grant Solution (TGS) Training Webinar for Grantees and Contractors Office of Economic and Workforce Development San Francisco August 3, 2018 Welcome Setup for today s Webinar: As you join the Webinar,
More informationAgenda Item Cover Sheet Agenda Item N o.
Agenda Item Cover Sheet Agenda Item N o. Meeting Date B-5 August 02, 2017 Consent Section x Regular Section Public Hearing Subject: Approve the recommended award of "Transportation Impact Fee Solicitation
More information# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:
BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: March 13, 2018 # 7 SUBJECT: ELECTION DISTRICT: Contract Award/Roadway and Civil Design
More informationMetrobus 30s Line Enhancements
Customer Service, Operations and Safety Committee Action Item III-C February 14, 2008 Metrobus 30s Line Enhancements Washington Metropolitan Area Transportation Authority Board Action/Information Summary
More informationPREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT
PREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT HOUSE TRANSPORTATION & INFRASTRUCTURE SUBCOMMITTEE ON RAILROADS Oversight Hearing on Railroad Security
More informationCLAYTON COUNTY TRANSIT INITIATIVE. Technical Advisory Committee/ Stakeholder Advisory Committee Webinar August 29, 2017
CLAYTON COUNTY TRANSIT INITIATIVE Technical Advisory Committee/ Stakeholder Advisory Committee Webinar August 29, 2017 AGENDA Welcome! Introduction of Speakers Webinar Housekeeping Project Overview & Status
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Assistant GM Customer Resources. From: Meredith Owens Approved by: /s/
AGENDA ITEM NO.: 5.B.1 MEETING DATE: 12/14/2015 ADMINISTRATIVE REPORT NO.: 2016-49 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Assistant GM Customer Resources From: Meredith Owens
More informationStanislaus County Fire Warden. Authority Business Plan
Stanislaus County Fire Authority ---------------------------- Business Plan 2017-2018 The (Fire Authority) is a Joint Powers Agreement established in November 2005 by the fire agencies in Stanislaus County
More informationNovember 28, 2012 ALTERNATIVES ANALYSIS PUBLIC MEETING
November 28, 2012 ALTERNATIVES ANALYSIS PUBLIC MEETING Project Background Description of the Project Alternatives Analysis Process Project Progress Activity Stations Comments Adjourn 2 VIA spent 2 years
More informationORA DATA REQUEST ORA-SCG-122-LMW SOCALGAS 2019 GRC A SOCALGAS RESPONSE DATE RECEIVED: FEBRUARY 6, 2018 DATE RESPONDED: FEBRUARY 23, 2018
Exhibit Reference: SCG-23 - Capital SCG Witness: Herrera Subject: Fleet Services & Facilities Please provide the following: ORA DATA REQUEST 1. In response to data request ORA-SCG-037-LMW Q4f, SCG provided
More informationCapital Program Support
Capital Program Support June 2013 Prepared by Project Control l Design, Engineering & Construction Management June 2013 Page 120 of 130 This page intentionally left blank. June 2013 Page 121 of 130 Environmental
More informationA Litter and Fly Tip Action Plan for Chichester District
Against Litter A Litter and Fly Tip Action Plan for Chichester District - 2017 2020 Year 2 - Revised September 2018 1 The Action Plan The responsibility to monitor the delivery of the action plan lies
More informationALBEMARLE COUNTY SERVICE AUTHORITY
ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA ITEM EXECUTIVE SUMMARY AGENDA TITLE: FY 2017 CIP Authorizations STAFF CONTACT(S)/PREPARER: Peter C. Gorham, P.E., Director of Engineering AGENDA DATE: March 16,
More informationCopiers, Printers & Related Devices # Initial Contract Rollout Webinar
Copiers, Printers & Related Devices #3091 2014-2019 Initial Contract Rollout Webinar Shannon Berry (sberry@admin.nv.gov) State of Nevada Contract Lead Paul Stembler (pstembler@wsca-naspo.org) Cooperative
More information1. Significant Changes
Security Upgrades Project (NMSSUP) Phase II, Los Alamos National Laboratory (LANL), Los Alamos, New Mexico Project Data Sheet is for Construction 1. Significant Changes The most recent DOE O 413.3B approved
More informationAPPROVE CONTRACT WITH COUNTY OF LOS ANGELES SHERIFF'S DEPARTMENT
Metro Los Angeies County One Gateway Plaza z3.gzz.zooo Tel Metropolitan Transportation Authority Los Angeles, CA goaz-2952 rnetro.net REVISED SYSTEMS SAFETY AND OPERATIONS COMMITTEE MAY 7,202 SUBJECT:
More informationSTATE STREET CORRIDOR
CITY OF WEST LAFAYETTE AND PURDUE UNIVERSITY STATE STREET CORRIDOR March 11, 2015 1 March 11, 2015 2 STATE STREET CORRIDOR AGENDA STATE STREET CORRIDOR 1. Project Fundamentals Project History Project Goals
More informationRequest For Proposals. Information Technology (IT) Services. General: The City of Bishop requests proposals from consultants to provide IT services.
Release: 10 June 2014 Closes: 27 June 2014 CITY OF BISHOP 377 West Line Street - Bishop, California 93514 Post Office Box 1236 - Bishop, California 93515 760-873-8458 publicworks@ca-bishop.us www.ca-bishop.us
More informationBEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) PHASE II REBUTTAL TESTIMONY KURTIS W. CASTLEBERRY DIRECTOR, RESOURCE PLANNING
BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF ENTERGY ARKANSAS, INC. S REQUEST FOR APPROVAL OF CERTAIN WHOLESALE BASE LOAD CAPACITY TO SERVE EAI CUSTOMERS AND A PROPOSED RIDER RECOVERY
More informationDowntown Boise Multimodal Center
Treasure Valley High Capacity Transit Study Downtown Boise Multimodal Center Environmental Assessment June 2009 Prepared by the Federal Transit Administration and Valley Regional Transit. U.S. Department
More informationMissouri Airport Owners Airport Sponsors Guide to Submitting Capital Improvement Program Requests (CIP) Online
Missouri Airport Owners Airport Sponsors Guide to Submitting Capital Improvement Program Requests (CIP) Online GCR & Associates, Inc. 2021 Lakeshore Drive Suite 500 New Orleans, LA 70122 504.304.2500 800.259.6192
More informationARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of September 22, 2018
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 22, 2018 ATE: September 12, 2018 SUBJECT: Award of Contract ITB-18-273 to Crown Construction Co. for the construction of playground
More informationAiM CPPM Construction Contract
AiM Navigation icons Budget Manager Date Manager Budget Revision The project delivery method for a capital project affects the construction contract more than any other factor. Often the types defined
More informationMetropolitan Council meeting: February 22, 2012
Business Item T Transportation Committee Item: 202-29 Meeting date: January 23, 202 REVISED Metropolitan Council meeting: February 22, 202 ADVISORY INFORMATION Date: February 2, 202 Subject: Light Rail
More informationTIER Program Funding Memorandum of Understanding For UCLA School of
TIER Program Funding Memorandum of Understanding For UCLA School of This Memorandum of Understanding is made between the Office of Information Technology (OIT) and the School of ( Department ) with reference
More informationMEMORANDUM. Board Members Alaska Industrial Development and Export Authority
MEMORANDUM To: From: Board Members Alaska Industrial Development and Export Authority John Springsteen CEO/Executive Director Date: January 9, 2019 Subject: Information Technology Capital Request Resolution
More informationNorthern Virginia Transportation Authority
IV Northern Virginia Transportation Authority March 23, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation 66 Outside the Beltway Project Scope Multimodal improvements to
More informationMETRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS
METRO SHORT RANGE TRANSIT PLAN FY 2010 2014 2014 Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS OVERVIEW Purpose of Metro SRTP Develop multi year strategic plan to improve transit quality,
More informationRCMP First Nations Community Policing Service
RCMP First Nations Community Policing Service The First Nations Policing Policy, announced by the federal government in June of 1991, provides First Nations communities with control over the policing services
More informationAUGUST 14, 2013 FINAL AGENDA PUBLIC COMMENTS ON AGENDA ITEMS AND OTHER MATTERS
NEW JERSEY TRANSIT CORPORATION NJ TRANSIT BUS OPERATIONS, INC. NJ TRANSIT RAIL OPERATIONS, INC. NJ TRANSIT MERCER, INC. NJ TRANSIT MORRIS, INC. REGULARLY SCHEDULED BOARD OF DIRECTORS MEETINGS CALL TO ORDER
More informationSOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************
SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 6 P DATE: December 5-7, 2017 ****************************************************************************** SUBJECT USD National Music Museum
More informationMetro REVISED SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE MARCH 19, 2015 SUBJECT: METRO RED LINE SCADA REPLACEMENT APPROVE CONTRACT MODIFICATION
Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA gooiz-2952 2~3 9zz z000 Tel rnetro.net REVISED SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE MARCH 19,
More informationReporting Contracts in the LBB Contracts Database
LEGISLATIVE BUDGET BOARD Reporting Contracts in the LBB Contracts Database Instructions for State Agencies and Institutions of Higher Education LEGISLATIVE BUDGET BOARD STAFF REVISED DECEMBER 2015 Table
More informationTRANSIT CENTER DISTRICT PLAN
TRANSIT CENTER DISTRICT PLAN Informational Presentation Planning Commission 04.19.2012 San Francisco Planning Department In partnership with: San Francisco Redevelopment Agency Transbay Joint Powers Authority
More informationTHE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM
THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM SFMTA s current Central Control Center is severely outdated and under staffed. The lack of proper functional
More informationREVIEW OF MANAGEMENT AND OVERSIGHT OF THE INTEGRATED BUSINESS MANAGEMENT SYSTEM (IBMS) January 16, 2009
APPENDIX 1 REVIEW OF MANAGEMENT AND OVERSIGHT OF THE INTEGRATED BUSINESS MANAGEMENT SYSTEM (IBMS) January 16, 2009 Auditor General s Office Jeffrey Griffiths, C.A., C.F.E. Auditor General City of Toronto
More information