LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

Size: px
Start display at page:

Download "LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update"

Transcription

1 July 11, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update PacifiCorp d/b/a Pacific Power provides the attached report to the Public Utility Commission of Oregon (Commission) and staff, in compliance with Order No , to provide quarterly updates to the Commission and staff as the development of the new wind projects from the 2017R Request for Proposals and transmission projects proceed. Please direct any questions regarding this report to Natasha Siores, Manager, Regulatory Affairs, at (503) Sincerely, Etta Lockey Vice President, Regulation cc: Caroline Moore, OPUC Staff

2 New Wind & Transmission Projects Quarterly Update Public Utility Commission of Oregon First Quarter

3 2017 IRP OPUC Acknowledgement Order 2017 IRP Acknowledgement Order, Docket LC 67, Appendix A: Provide quarterly updates to the Commission and Staff as development of the projects chosen in the 2017R RFP and the transmission projects proceed (through the date the projects go into service). 2

4 2017R RFP Final Shortlist Status Update Project Name Bidder Location Structure Capacity (MW) TB Flats I & II PacifiCorp self-build benchmark; developed by Invenergy Carbon County, WY Balance of plant EPC; stand-alone TSA 500 Cedar Springs NextEra development acquisition (Orion) and construction Converse County, WY 50% buildtransfer / 50% power purchase 400 Ekola Flats PacifiCorp self-build benchmark; developed by Invenergy Carbon County, WY Balance of plant EPC; stand-alone TSA 250 Uinta 1 Invenergy development and construction Uinta County, WY Build-transfer The Uinta project has been removed from consideration as part of the 2017R RFP and the Energy Vision 2020 projects in PacifiCorp's various regulatory proceedings. The project developer has been advised of this outcome and will independently determine its most appropriate development path going forward. 3

5 2017R RFP Wind Project Locations WYOMING 4

6 2017R RFP Wind Projects Status Update Interconnection TB Flats I & II (PacifiCorp) Shirley Basin POI; SIS complete; LGIA in process Ekola Flats (PacifiCorp) Aeolus POI; LGIA executed Safe Harbor Turbines Assigned and documented Assigned and documented Cedar Springs (NextEra) Windstar POI; SIS complete Assigned and documented, site identification verification in progress Site Control 50,000 acres private/state leases acquired; gen-tie right-of-way in progress 17,000 acres private/state leases acquired; gen-tie right-of-way in progress 70,000 acres private leases acquired; gen-tie right-of-way in progress Permitting Status Permitting in process and on schedule; industrial siting and conditional use permits received Permitting in process and on schedule; conditional use permit received; industrial siting application filed Permitting in process and on schedule; conditional use permit application expected to be filed Q3 2018; industrial siting permit application expected to filed Q Avian Data Collection / Permitting Underway (24 Months); agency consultation underway Underway (24 Months); agency consultation underway Underway (24 Months); agency consultation underway Contracts Balance of plant EPC contract execution ready mid-july; TSA agreement execution ready late-july Balance of plant EPC contract execution ready mid-july; TSA agreement execution ready late-july Build-transfer agreement and power purchase agreement execution ready late-july Upcoming Milestones EPC full notice to proceed April 1, 2019 EPC full notice to proceed April 1, 2019 Submit ISC permit application March 25, 2019; BTA firm date before March 31, 2020 Outreach / Community Engagement Public meetings for permit applications Aeolus bridge dedication (Carbon County, WY) July 31, 2018 Wyoming state fair sponsor 5

7 6 Transmission Projects Map

8 New Transmission/New Wind - Wyoming Naughton 719 MW Utah Wyoming PacifiCorp Aeolus West/TOT 4B Wyoming Chimney Butte < 230 kv Existing 230 kv Existing 345 kv Existing 500 kv Proposed Pinedale Jonah Field Trona Q542 Bowler Flats (240 MW) Frannie TOT 4B AEOLUS WEST Atlantic City Oregon Basin Grass Creek Garland Thermopolis Mustang Bridger Anticline Firehole Wyoming Utah Wyopo Colorado Riverton AEOLUS WEST Yellowtail Bairoil n.o. Badwater WAPA owned 115 kv Platte Sheridan (MDU) Buffalo TOT 4B Spence Kaycee Decker Midwest WAPA owned Shirley Basin Casper Difficulty AEOLUS WEST /TOT 4B Limit: Simultaneous Nomogram 1 Amasa Aeolus Freezeout 7 Standpipe Dry Fork 3 Windstar 4 DJ Q706 Ekola Flats (250 MW) Montana Wyoming Wyodak Osage South Dakota Converse County Line Lookout Q712 Cedar Springs I (520 MW) 5 Q707/708 TB Flats I & II (2x250 MW) Chevron Wind 16.5 MW 3 Buttes 99 MW Glenrock/ Rolling Hill MW ea. T.O.W MW Root Creek 80 MW Dunlap 111 MW 7 Mile Hill MW Foote Creek 135 MW High Plains 99 MW McFadden Ridge 28.5 MW 7

9 New Transmission Aeolus-to-Bridger/Anticline (Energy Gateway, Segment D2) New 140-mile, 500 kilovolt transmission line and new Aeolus and Anticline substations New 5-mile, 345 kilovolt Anticline-to-Jim Bridger line; including modifications at Jim Bridger substation New voltage control device at Latham substation Network Upgrades New 16-mile, 230 kilovolt line from Shirley Basin to proposed Aeolus substation, with substation modifications (TB Flats I & II) Reconstruction of 16-mile, 230 kilovolt Shirley Basin-Freezeout-Aeolus line, with substation modifications (Cedar Springs) Reconstruction of 15-mile, 230 kilovolt Freezeout-Standpipe-Aeolus line, with substation modifications (Cedar Springs) 8

10 Transmission Status Update Complete Preliminary technical studies evaluating a wide range of system conditions to support integration of new wind, focusing on Segment D2 facilities. Demonstrated Aeolus West path 1829 MW with 1510 MW of new wind Interconnection studies evaluating TB Flats I&II, Cedar Springs and Ekola Flats, including assessment of updated wind models (power flow and dynamic stability) Technical studies demonstrating expected performance of the Latham Static VAr Compensator (SVC) for a wide range of system conditions and supporting SVC specification development efforts Subsynchronous resonance (SSR) and subsynchronous control interaction (SSCI) study In-Process Detailed PSCAD modeling of wind facilities and new transmission Design of new Aeolus remedial action scheme (RAS) & modification of Bridger (C/D) RAS SVC specification development, including PSCAD modeling Future Aeolus West Path Rating: Western Electricity Coordinating Council FAC transfer capability assessment studies Peak Reliability Coordinator (RC) System Operating Limit (SOL) studies 9

11 Wyoming Permitting Overview National Environmental Policy Act Element of Gateway West segment D, Record of Decision November 2013 Plan of Development and Mitigations, currently in final development Certificate of Public Convenience and Necessity Filed June 30, 2017, Bench Order approval issued April 12, 2018 Conditional Use Permit (Carbon County) Application submitted May 22, 2018 Wyoming Industrial Siting Permit Planned application Summer 2018; decision expected October 2018 Anticipated Construction award December 2018 Construction to start April 1,

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update January 7, 2019 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

PacifiCorp Transmission Energy Gateway Update. John Cupparo Vice President, Transmission January 2010

PacifiCorp Transmission Energy Gateway Update. John Cupparo Vice President, Transmission January 2010 PacifiCorp Transmission Energy Gateway Update John Cupparo Vice President, Transmission January 2010 Topics Overview and current status Rightsizing Challenges and opportunities Summary 2 Energy Gateway

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator Assembly Standing Committee on Energy Kevin A. Cahill, Chairman Assembly Standing Committee on Corporations, Authorities and Commissions James F. Brennan, Chairman Assembly Standing Committee on Cities

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

This report is printed on recycled paper

This report is printed on recycled paper This 2015 Integrated Resource Plan Update Report is based upon the best available information at the time of preparation. The IRP action plan will be implemented as described herein, but is subject to

More information

TransWest Express and Gateway South

TransWest Express and Gateway South TransWest Express and Gateway South Co-developed by four leading entities: Arizona Public Service PacifiCorp National Grid Wyoming Infrastructure Authority Regional Stakeholder Meeting January 23, 2008

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re The Narragansett Electric Company : : Docket No. SB-2017-01 () : Pre-Filed Testimony of Daniel Ewan, Clear River Energy

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

NTTG 2019 Annual Interregional Information

NTTG 2019 Annual Interregional Information NTTG 2019 Annual Interregional Information Annual Interregional Coordination Meeting Salt Lake City February 19, 2019 Topics NTTG s Planning Process Overview NTTG s 2018-2019 Draft Regional Transmission

More information

ENVIRONMENTAL ASSESSMENT WORKSHEETS EAW Comment Deadline: June 17, 2009

ENVIRONMENTAL ASSESSMENT WORKSHEETS EAW Comment Deadline: June 17, 2009 Next Publication: June 1, 2009 Vol. 33, No.10 Submittal Deadline: May 22, 2009 Project Title: ENVIRONMENTAL ASSESSMENT WORKSHEETS EAW Comment Deadline: June 17, 2009 Project Title: Pierce Butler Route

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 17-035-36 Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Kelcey A. Brown August 2017 1 2 3 4

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION

STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION In the Matter of the Application of Getty Wind Company, LLC for a Site Permit for a Large Wind Energy Conversion System in Stearns County, Minnesota In the

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Integrated Resource Planning April 20, 2010

Integrated Resource Planning April 20, 2010 Integrated Resource Planning April 20, 2010 Judy Stokey, Executive Government and External Affairs Jack McGinley, Development Director, Renewables Gary Smith, Project Director-Smart Technologies Presentation

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 Mark Buchholz WAPA Upper Great Plains Region Compliance Manager What is Western? One of four Power Marketing Administration within

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) PHASE II REBUTTAL TESTIMONY KURTIS W. CASTLEBERRY DIRECTOR, RESOURCE PLANNING

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) PHASE II REBUTTAL TESTIMONY KURTIS W. CASTLEBERRY DIRECTOR, RESOURCE PLANNING BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF ENTERGY ARKANSAS, INC. S REQUEST FOR APPROVAL OF CERTAIN WHOLESALE BASE LOAD CAPACITY TO SERVE EAI CUSTOMERS AND A PROPOSED RIDER RECOVERY

More information

WIND. Representing clients across the renewable energy industry. Troutman Sanders LLP. troutman.com

WIND. Representing clients across the renewable energy industry. Troutman Sanders LLP. troutman.com WIND Representing clients across the renewable energy industry Troutman Sanders renewable energy attorneys offer innovative legal solutions to help clients succeed in the wind energy industry. Our deep

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

February 25, Subject: Southern California Edison 2015 Annual Progress Report

February 25, Subject: Southern California Edison 2015 Annual Progress Report February 25, 2015 Mr. Tracy Rolstad, Chair WECC Technical Studies Subcommittee Avista Corp. 1411 East Mission Avenue Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff Salt Lake City, UT 84103-1114

More information

Reston Town Center North Development. Community Update

Reston Town Center North Development. Community Update Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

American Transmission Company U.P. Energy Summit

American Transmission Company U.P. Energy Summit American Transmission Company U.P. Energy Summit John Flynn Vice President Strategic Planning & Business Development October 26, 2011 Helping to keep the lights on, businesses running and communities strong

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 Varuna A. Singh August 17, 2018 NHHIP OVERVIEW Project divided into three segments: Segment 1: I-45: from Beltway 8 to I-610 (9 mi) 45 Segment

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Review of Generator Interconnection Agreements and Procedures American Wind Energy Association Docket No. RM16-12-000 Docket No. RM15-21-000

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Specific topics covered in this brief include:

Specific topics covered in this brief include: April 2008 Summary Welcome to the Fifteenth National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 28, 2008, Transmission Update conference

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

ERO Enterprise Strategic Planning Redesign

ERO Enterprise Strategic Planning Redesign ERO Enterprise Strategic Planning Redesign Mark Lauby, Senior Vice President and Chief Reliability Officer Member Representatives Committee Meeting February 10, 2016 Strategic Planning Redesign Current

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Benbow 397S Substation Upgrade Needs Identification Document

Benbow 397S Substation Upgrade Needs Identification Document APPENDIX C AESO PIP Benbow 397S Substation Upgrade Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to December 2015, the AESO conducted a Participant Involvement Program

More information

Compliance Enforcement Initiative

Compliance Enforcement Initiative Compliance Enforcement Initiative Filing and Status Update November 2, 2011 Rebecca Michael Status of the Filings NERC filed several components of the Compliance Enforcement Initiative on September 30,

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,

More information

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document Decision 2014-271 Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014 The Alberta Utilities Commission Decision 2014-271: Alberta Electric System Operator

More information

Low Impact Generation CIP Compliance. Ryan Walter

Low Impact Generation CIP Compliance. Ryan Walter Low Impact Generation CIP Compliance Ryan Walter Agenda Entity Overview NERC CIP Introduction CIP-002-5.1, Asset Classification What Should Already be Done CIP-003-7, Low Impact Requirements Tri-State

More information

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS

More information

Balance of Power in the Hudson Valley

Balance of Power in the Hudson Valley 1 Balance of Power in the Hudson Valley Chris Hogan, NYSDEC Major Project Management Unit May 3, 2017 2 Objective Provide an overview of the various state and federal processes by which energy projects

More information

WISP. Western Interconnection Synchrophasor Program. Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012

WISP. Western Interconnection Synchrophasor Program. Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012 WISP Western Interconnection Synchrophasor Program Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012 1 Acknowledgement and Disclaimer Acknowledgment: This material is based

More information

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

Planning for the Future

Planning for the Future Gas/Electric Partnership Conference Planning for the Future February 1, 2018 Entergy Texas, Inc. Entergy Texas, Inc. Staci Meyer Manager, Resource Planning Jeff Dicharry Manager, Transmission Planning

More information

Unified Development Code. Public Workshop No. 3 November 7, 2017

Unified Development Code. Public Workshop No. 3 November 7, 2017 Unified Development Code Public Workshop No. 3 November 7, 2017 Purpose of the Project 2 The overall goal of the project is to bring together the County s Land Development Regulations (Chapter 74 of the

More information

Energy.

Energy. Briggs and Morgan provides full-service representation to a broad range of energy providers, public utilities, independent power producers, regional entities and other energy-sector participants. We work

More information

Boardman to Hemingway Project Advisory Team

Boardman to Hemingway Project Advisory Team Boardman to Hemingway Project Advisory Team Central Project Advisory Team Meeting 5 Tonight s Objectives Review progress of the Community Advisory Process and discuss next steps Present analysis of revised

More information

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES P AGE 129 A-1 A-2 A-3 A-4 A-5 A-6 A-7 A-8 A-8 A-9 B-1 B-2 B-3 B-4 B-6 B-5 March 24, 2015 Scott Johnson Community

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Posted October 17, 2006 QWEST CORPORATION COMPARABLY EFFICIENT INTERCONNECTION PLAN FOR ENHANCED DIRECTORY ASSISTANCE

Posted October 17, 2006 QWEST CORPORATION COMPARABLY EFFICIENT INTERCONNECTION PLAN FOR ENHANCED DIRECTORY ASSISTANCE Posted October 17, 2006 QWEST CORPORATION COMPARABLY EFFICIENT INTERCONNECTION PLAN FOR ENHANCED DIRECTORY ASSISTANCE I. INTRODUCTION Qwest Corporation ( Qwest ) hereby posts its Comparably Efficient Interconnection

More information

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9 THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental

More information

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9 THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

Audit and Compliance Committee - Agenda

Audit and Compliance Committee - Agenda Audit and Compliance Committee - Agenda Board of Trustees Audit and Compliance Committee April 17, 2018, 1:30 2:30 p.m. President s Board Room Conference Call-In Phone #1-800-442-5794, passcode 463796

More information

Presentation to Local/State/Federal Agency Mtg November 10, 2015

Presentation to Local/State/Federal Agency Mtg November 10, 2015 Presentation to Local/State/Federal Agency Mtg November 10, 2015 Summary Proposed 114 mile 500 kv transmission project that will connect with Delaney Substation near Palo Verde Nuclear Generating Station,

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 July 30, 2010 Re: Q2 Quarterly

More information

ENMAX Generation Portfolio Inc.

ENMAX Generation Portfolio Inc. Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. September 5, 2017 Alberta Utilities Commission Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. Proceeding 22192 Application 22192-A002 September

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

EB CDM Exemption Hydro One Networks' Undertaking Responses ONLY HYDRO ONE UNDERTAKINGS Undertaking Description Filed Date Note

EB CDM Exemption Hydro One Networks' Undertaking Responses ONLY HYDRO ONE UNDERTAKINGS Undertaking Description Filed Date Note CDM Exemption Hydro One Networks' s ONLY HYDRO ONE S Description Filed Date Note J. J. J. TO PROVIDE NUMBERS OF NON-COMPLIANT APPLICATIONS REQUIRING AND NOT REQUIRING SITE ASSESSMENTS TO PROVIDE STAFFING

More information

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Self-Monitoring:

More information

10. Unbundled Dark Fiber 10.1 General

10. Unbundled Dark Fiber 10.1 General Verizon New England Inc. Page 1 Second Revision Canceling First Revision 10.1 General 10.1.1 Description A. For purposes of this Part B, Section 10, the terms business line, fiber-based collocator, and

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m. AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting July 9, 2014 Executive Director Approval

More information

Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013

Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Mark W. Maher Chief Executive Officer Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Agenda WECC Overview WECC Strategic Planning Initiative Western Interconnection Synchrophasor

More information

National Load Despatch Centre Power System Operation Corporation

National Load Despatch Centre Power System Operation Corporation Module on Procedure for Data Collection National Load Despatch Centre Power System Operation Corporation Background Algorithms/ Processes AC Load flow and transmission losses Slack bus determination- Average

More information

Electrification - Infrastructure Construction activities in Segment 2:

Electrification - Infrastructure Construction activities in Segment 2: Peninsula Corridor Electrification Project (PCEP) Q1 Quarterly Update #12 July 1 September 30, 2017 JPB Board Meeting November 2, 2017 Agenda Item # 8a Electrification - Infrastructure Construction activities

More information

Community Update. June 8, 2011

Community Update. June 8, 2011 Community Update June 8, 2011 Presented to: Scarborough Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

ERO Enterprise IT Projects Update

ERO Enterprise IT Projects Update ERO Enterprise IT Projects Update Stan Hoptroff, Vice President, Chief Technology Officer and Director of Information Technology Technology and Security Committee Meeting November 6, 2018 Agenda ERO IT

More information

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax: B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: 0-- E-mail: janet.fraser@bctc.com October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street,

More information