MTG Schedule Report template
|
|
- Mildred Craig
- 6 years ago
- Views:
Transcription
1 1/13 MTG Schedule Report template [DRL code : ] N/A [AD code : AD-07C-04] [ PT code : I10000/S10000] Written by F.THEVENIN Responsibility + handwritten signature if no electronic workflow tool MTG TAS Schedule controller Verified by T.SCHAEFER A.SMOLDERS T.GRASSIN Approved by OHB Approved by TASF OHB Schedule controller TAS AIV Responsible Satellite PA Manager OHB Project Manager TASF Project Manager Approval evidence is kept within the documentation management system.
2 2/13 CHANGE RECORDS ISSUE DATE CHANGE RECORDS AUTHOR /11/2011 First issue of the template following BDR action F.THEVENIN
3 3/13 DISTRIBUTION LIST Company ESA OHB Name R.CARLI T.SCHAEFER
4 4/13 TABLE OF CONTENTS 1. INTRODUCTION Applicable Documents Reference documents OVERALL MTG-I/S SCHEDULE Assumptions Main reviews CFI need dates Deliverable dates Satellite models Deliverable elements to Subcontractors Overall summarized barchart SCHEDULE FOR P/F Significant Events & assumptions Milestones Tables Schedule analysis General schedule Platform LLI list SCHEDULE MTG-I/S Instruments SYSTEM PLANNING MTG-I/S Significant Events Milestones Tables Schedule analysis General schedule... 13
5 5/13 LIST OF FIGURES FIGURE 1. SCHEDULE COMMITMENTS... 7 FIGURE 2. SCHEDULE OVERVIEW... 9 FIGURE 3. MILESTONES WITH ASSOCIATED MARGINS FIGURE 4. PROCUREMENT TABLE... 11
6 6/13 1. INTRODUCTION This chapter should describe the aim of the document. This should be the place to explain how the necessary reporting themes are covered (including LLI for MTG-I). 1.1 Applicable Documents This part should give a table recalling the documents that are applicable for the Schedule reporting. ID Title Reference Applicable issue AD1 Schedule Management MTG-TAF-SA-MN-0181 Meeting MoM AD-07C-03 Schedule Architecture MTG-TAF-SA-SC Description Document AD-3 MTG-ESA-SA-RS-0072 MTG Management Requirements (MARD) Reference documents This part should give a table recalling the documents the Schedule report refers to. The table below states the documents that should be present at minimum : ID Title Reference Applicable TAS OHB issue RD1 ECSS Project Planning & Implementation ECSS-M-ST-10C X X RD2 ECSS Cost & Schedule Management ECSS-M-ST-60C X X RD3 MTG-I Satellite AIT Plan MTG-TAF-SA-PL X RD3 MTG-S Satellite AIT Plan MTG-OHB-SAS-PL-0026 X RD4 MTG-I GSE Design and Development Plan MTG-TAF-SA-PL X RD4 MTG-S GSE Design and Development Plan MTG-OHB-SY-PL-0028 X RD5 MTG FCI TA PROGRESS REPORT #n MTG-KT-CI-RP-0013 n X RD5 IRS PROGRESS REPORT #n MTG-KT-IR-RP-0016 n X RD6 LLI list for MTG platforms MTG-OHB-PF-LI-0009 X X RD7 FCI-TA LLI MTG-KT-II-LI-0012 X RD8 Evaluation reports for items in open competition TAS-F proposal V6 part 2 X RD9 MTG Risk Register MTG-TAF-SY-TN X RD9 MTG-S Risk Register MTG-OHB-SAS-LI-0062 X RD10 MTG-I Schedule structure PM-8_MTG-TAF-SAI-SC-0577 X RD10 MTG-S Schedule MTG-OHB-SY-SC-0001 X RD11 PF Schedule MTG-OHB-PF-SC-0002 X X
7 7/13 2. OVERALL MTG-I/S SCHEDULE 2.1 Assumptions This chapter should describe the perimeter used to build the schedule and the schedule report This way, there should give first a short description of the context in which the schedule report is made. Then it recalls the rhythm of work and days off-work foreseen in the schedule : As an example, for MTG-I, it is stated that the plannings have been built with a working rhythm of 5 days per week. In addition the following days are considered off work : Eastern Monday Ascension day Whitsun 14th July 2 weeks break at beginning of August 15th August End of the year break (from Christmas Eve to New Year s day included) The working rhythm is enhanced to 2 shifts by day in AIT Satellite and for FCI (even 3x8 for vacuum tests). Then a paragraph should deal with the technical document used to issue the schedule report : Procurement status (date of revision of the procurement table) P/F schedule issue or simulation Payloads schedules or SOWs revision if no schedule available It should also be the place to make major warnings concerning some slippages (if any). When a discrepancy exists between a date arose by a supplier and a date used in the schedule (for example when a negotiation is in progress at the time of the schedule report edition), a table recalling the date arose by the supplier and the commitment used to perform the planning is necessary. Sub-system 1 event Sub-system 2 event Contractual date (SOW) DRB Date assumed by TAS/OHB Dates given by the supplier Shift from SOW (months) Comment Figure 1. Schedule commitments
8 8/ Main reviews Here are recalled the major review dates at MTG-I or S system level : Review SRR System DP delivery BDR collocation PDR System DP delivery PDR System collocation System Satellite CDR QR Satellite Delta QR Satellite MTG-I/S Customer Request TAS/OHB current T0 + T0 + Date N/A N/A 2.3 CFI need dates Here a recalled the CFI need date with requested date and current/committed date. This chapter should exist but with no table if no CFI are foreseen. 2.4 Deliverable dates Satellite models Here are recalled the major deliverable dates at MTG-I or S system level : Model End of STM-I/S End of EM-I/S FAR MTG-I/S 1 CTS MTG-I/S 2 CTS MTG-I 3 * CTS MTG-I 4 * Customer Request TAS/OHB current T0 + T0 + Date N/A N/A * relevant only for MTG-I Deliverable elements to Subcontractors This chapter should give the view of the deliverable dates of elements as written in the SOWs of subcontractors. This should be the case for MTG-I documents awaited as inputs for the Platform (AD-24PF issues, AD-25PF issues )
9 9/ Overall summarized barchart This chapter should present an overview of the MTG-I or S project. This scheme is given to have a general overview of the program. There should be a sentence to warn that if a discrepancy is found between this scheme and the detailed schedules, the detailed schedules supersede the general overview. Example of overview used for MTG-I : Figure 2. Schedule overview
10 10/13 3. SCHEDULE FOR P/F 3.1 Significant Events & assumptions This chapter should describe the major facts happened in the reporting period that impacts the planning. Moreover, it should give the assumptions used to build the P/F schedule ie AVM development philosophy, recall of technical baseline if different options may be considered 3.2 Milestones Tables This chapter should give the tables of the review dates and delivery dates concerning the Platform. As per ESA request, this should also present in some way the software review dates. Customer Request Review in SOW OHB current in TAS schedule T0 + T0 + Date PDR PF (DP out) /02/2012 Software PDR /04/2012 Software DDR /10/2012 Software DDR2 N/A 28 18/03/2013 Software DDR3 N/A 30 18/05/2013 Software CDR /11/2013 CDR PF /03/2014 Software QR /11/2014 Customer Request P/F Model in SOW OHB current in TAS schedule T0 + T0 + Date PF STM /10/2013 PF EM /06/2014 PF MTGI PFM /05/2015 PF MTGI FM /11/2016 PF MTGI FM /03/2018 PF MTGI FM /05/2019 Then a view of these milestones with the associated margins should be present. (For example a view of the milestone schedule as hereunder).
11 11/13 Figure 3. Milestones with associated margins 3.3 Schedule analysis This chapter should deal with the critical path for platform models and the trend graph of the reviews and the delivery dates. Any mitigation plan should be presented here in relationship with the Risk Register if relevant. 3.4 General schedule Here are presented : 1) The procurement table related to P/F items. As per ESA request, this table should present the following information : ITT dates KOM date Actual delivery date for each model procured Recall for the delivery date presented at the previous report Recall of contractual date (when KOM preformed) or the SOW date Recall of the need date for the model Example of table presenting these informations for the EPS subsystem : Figure 4. Procurement table
12 12/13 A discussion related to the GSE procurement should also be present. 2) A view of the engineering schedule with a discussion consolidating the P/F PDR date. 3) A section concerning the software development 4) A section dealing with the models development (AVM, STM, EM, PFM and FMs AITs) 3.5 Platform LLI list As for MTG-I DRL, the PA-12 document is merged with the schedule report, this section is specific to MTG-I unless another agreement. 4. SCHEDULE MTG-I/S This part concerns the extract of instrument schedule reports significant at system level. For MTG-I, the schedule reporting of the FCI and the System are merged. Therefore the FCI section is more detailed. 4.1 Instruments Here are described the reporting concerning the instruments. For MTG-S, this should be the reporting of UVN and IRS developments. For MTG-I, this section reports for FCI, LI and DCS/GEOSAR. The sub-sections needed are : Significant Events Milestones Tables Schedule analysis (with critical path discussion and appropriate trend graph). When an important slippage is presented by the supplier, a discussion on the reasons of the slippage and a mitigation plan should be present. If a decision at management level is awaited, the section should present the mitigation scenario and refer to progress report in which the appropriate scenario shall be selected. General schedule (with a view on procurement if relevant containing GSE procurement, the engineering schedule discussion consolidating the instrument PDR date and then a view of models AIT) LLI list (for MTG-I payloads only) 4.2 SYSTEM PLANNING MTG-I/S Significant Events This section deals with the significant progress done at schedule level concerning the System schedules. Here are presented eventual improvements on schedule or modification of perimeters (for example BDR integration in the schedule and explanation why the subsequent milestones don t move) Milestones Tables Here are recalled the tables of reviews and delivery dates for models. The view of the margins is awaited in this section.
13 13/ Schedule analysis This sections should deal with critical paths, delays/margins discussion and trend graphs related to MTG-I/S system schedule General schedule Here is given the view of : 1. the engineering schedule (specification process, progress of analysis, plans ). 2. Then a view of procurement at system level when relevant (System ITTs, GSEs ). 3. By the end, a view of AITs of the different models of satellite should be presented (one page per model in order to have a resolution on tasks) END OF DOCUMENT
CONTROLLED DISTRIBUTION REFERENCE
ISSUE : 01 PAGE: 2/14 CHANGE RECORDS ISSUE DATE CHANGE RECORDS AUTHOR 01 26/05/09 First issue MS - PF ISSUE : 01 PAGE: 3/14 TABLE OF CONTENTS 1. PURPOSE... 4 2. DOCUMENTS... 5 2.1 Normative Documents...5
More informationEuropean Ground Systems - Common Core (EGS-CC) ASI Italian Information Day
European Ground Systems - Common Core (EGS-CC) ASI Italian Information Day The next generation Functional Verification Test facilities (EGSE, ATB, SVF) & Mission Control Systems (MCS) K. Hjortnaes/N. Peccia
More informationDOCUMENT CHANGE LOG. Date Modified Chapters Observations. 1/0 29 June 2007 New document first release
Issue: 2 Date: 15/2/10 Page: 2/20 DOCUMENT CHANGE LOG Issue/ Revision Date Modified Chapters Observations 1/0 29 June 2007 New document first release 1.1 19 Jan 2010 Cover References and Organisation Code
More informationSpace project management
ECSS-M-ST-40C Rev. 1 Space project management Configuration and information management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is
More informationINTERNAL THALES ALENIA SPACE STANDARD : DATE : CHANGE RECORDS. Paragraphs Change Record (List of paragraphs modified, new or deleted)
ISSUE : 01 PAGE : 2/10 CHANGE RECORDS Paragraphs Change Record (List of paragraphs modified, new or deleted) Issue Date Change Record Description Author Draft 17/09/10 First preliminary issue 01 First
More informationMOST (Modelling of SpaceWire Traffic): MTG-I simulation presentation
MOST (Modelling of SpaceWire Traffic): MTG-I simulation presentation PART 1 2 1 INTRODUCTION, HISTORY and CONTEXT MTG SpaceWire Network MOST presentation (1/5) 3 MOST (Modelling of SpaceWire Traffic) was
More informationMBSE in the System Design and Verification Process
MBSE in the System Design and Verification Process Joachim Fuchs (ESA/ESTEC) also inspired from industry and organisations like OMG, INCOSE Astrium, TAS, ADSE What Is Systems? A Consensus of Senior Systems
More informationJuly 4th, 2011, Rome. AIPAS International Workshop Marco Fuchs
July 4th, 2011, Rome AIPAS International Workshop Marco Fuchs THE GROUP New OHB Group structure with two Business Units ESA- OHB 20110701 CONFIDENTIAL Page 2 THE GROUP Total staff: 2,206 Status: 2011/03/31
More informationAdvanced Validation Strategies for On-Board Satellite Software in the Galileo IOV Programme
Olivier Croatto, Michael Uemminghaus Garching, Oct. 7th, 2008 Advanced Validation Strategies for On-Board Satellite Software in the Galileo IOV Programme Astrium Proprietary Information Agenda 1 - Overview
More informationQuestion & Answer #3
DARPA Blackjack Reference: HR001118S0032 Link: https://www.fbo.gov/spg/oda/darpa/cmo/hr001118s0032/listing.html Question & Answer #3 Question 80: Is there any guidance on how to plan for material procurement?
More informationDATA ITEM DESCRIPTION TITLE: INTEGRATED MASTER SCHEDULE (IMS) NUMBER: DI-MGMT APPROVAL DATE:
DATA ITEM DESCRIPTION TITLE: INTEGRATED MASTER SCHEDULE (IMS) NUMBER: APPROVAL DATE: 20050330 AMSC NUMBER: D7544 LIMITATION: DTIC APPLICABLE: GIDEP APPLICABLE: PREPARING ACTIVITY: OUSD(AT&L)ARA/AM(SO)
More informationState of Nevada Legislative Counsel Bureau 401 S. Carson Street Carson City, NV voice facsimile
State of Nevada Legislative Counsel Bureau 401 S. Carson Street Carson City, NV 89701 775.684.1310 voice 775.684.1333 facsimile REQUEST FOR PROPOSAL for: PROFESSIONAL WEB DEVELOPMENT SERVICES AND RELATED
More information<PROJECT> WORK BREAKDOWN STRUCTURE
WORK BREAKDOWN STRUCTURE Version Number: 1.0 Version Date: Notes to the Author [This document is a template of a Work Breakdown Structure document for a project. The template includes
More informationSGEO: Overview and Product Offering. Marco R. Fuchs. Marco R. R. Fuchs. DLR-ESA Workshop on ARTES 11. Marco R. Fuchs OHB Technology AG
DLR-ESA Workshop on ARTES 11 SGEO: Overview and Product Offering Marco R. R. Fuchs June June29, 29, 2006 2006 Tegernsee, Tegernsee, Germany Germany Marco R. Fuchs Marco R. Fuchs OHB Technology AG OHB Technology
More informationMilk Support Service Level Agreement
Milk Support Service Level Agreement Document Owner: Milk (Student Planner System) Service Level Agreement (SLA) for: (CUSTOMER NAME) Revision History Version Date Contributor Modifications 1.0 May 2018
More informationDoctoral Dissertation Template
Doctoral Dissertation Template Template User Guide Revision: Version 4.0 January 2017 January, 2016 Version 3.1 (Superseded by Version 4.0) July, 2015 Version 3.0 (Superseded by Version 3.1) April, 2014
More informationT2S PROGRAMME STATUS AS OF MID-SEPTEMBER
T2S PROGRAMME OFFICE ECB-PUBLIC AG Meeting 18/19 September 2012 Item 2 09.04.01/2012/007820 T2S PROGRAMME STATUS AS OF MID-SEPTEMBER 2012-1. Introduction In this note the T2S Programme Office provides
More informationCRITICAL DESIGN REVIEW
STUDENTS SPACE ASSOCIATION THE FACULTY OF POWER AND AERONAUTICAL ENGINEERING WARSAW UNIVERSITY OF TECHNOLOGY CRITICAL DESIGN REVIEW November 2016 Issue no. 1 Changes Date Changes Pages/Section Responsible
More informationQuestion & Answer #2
DARPA Blackjack Reference: HR001118S0032 Link: https://www.fbo.gov/spg/oda/darpa/cmo/hr001118s0032/listing.html Question & Answer #2 Question 9: Table 5 Thermal requirement shows a Nominal Requirement
More informationCompany Presentation. Alessio Di Iorio, Managing Director
Company Presentation Alessio Di Iorio, Managing Director 06 October 2015 1 1 Profile ALMA Sistemi sas di Di Iorio Alessio & C is an Italian SME established in 2005 providing high level consultancy in the
More informationGeneric Requirements Management and Verification Process for Ground Segment and Mission Operations Preparation
Generic Requirements Management and Verification Process for Ground Segment and Mission Operations Preparation Dr. Frank Wallrapp 1 and Andreas Lex 2 German Space Operations Center, DLR Oberpfaffenhofen,
More informationNew Space, small and pocket spacecraft
New Space, small and pocket spacecraft Chris Brunskill 01 July 2016 What is New Space? Nano and microsatellites provide easy access to space, trading reduced costs for greater risks Cost reduction The
More informationThe Main Concepts of the European Ground Systems Common Core (EGS-CC)
The Main Concepts of the European Ground Systems Common Core (EGS-CC) Mauro Pecchioli, ESA/ESOC Juan María Carranza, ESA/ESTEC Presentation to GSAW March 2013 2013 by esa. Published by The Aerospace Corporation
More informationGOES R Ground Segment Project Update
GOES R Ground Segment Project Update Vanessa Griffin Giffi Project Manager, GOES R Ground Segment Project Atlanta, Georgia 2010 GOES R Ground Segment Objectives Support the primary mission operations goals
More informationImplementation Plan for Newly Identified Critical Cyber Assets and Newly Registered Entities
Implementation Plan for Newly Identified Critical Cyber Assets and Newly Registered Entities This Implementation Plan applies to Cyber Security Standards CIP-002-2 through CIP-009-2 and CIP-002-3 through
More informationSystem Approach for a SpaceWire Network Template reference : C-EN
System Approach for a SpaceWire Network Template reference : 100181700C-EN Prepared by Stephane DETHEVE / Bruno MASSON PLAN Page 2 SYSTEM APPROACH FOR A SPACEWIRE NETWORK INTRODUCTION SIMULATION BREADBOARDING
More informationesa-p EXTENDED GUIDE How to SUBMIT and APPROVE a MAC Confirmation
esa-p EXTENDED GUIDE How to SUBMIT and APPROVE a MAC Confirmation esa-p Extended Guide How to SUBMIT and APPROVE a MAC Confirmation CHANGE LOG REASON FOR CHANGE VERSION DATE PARAGRAPH(S) Update of the
More informationesa-p GUIDE Tracking and Reporting Guide on Tracking and Reporting 1 Page
esa-p GUIDE Tracking and Reporting 1 Page esa-p Guide Tracking and Reporting CHANGE LOG REASON FOR CHANGE VERSION DATE PARAGRAPH(S) Update of the esa-p user documentation for supplier 1.0 30/09/2015 All
More informationUnofficial Comment Form Project Modifications to CIP Standards Requirements for Transient Cyber Assets CIP-003-7(i)
Unofficial Comment Form Project 2016-02 Modifications to CIP Standards Requirements for Transient Cyber Assets CIP-003-7(i) Do not use this form for submitting comments. Use the electronic form to submit
More informationOHB System AG International Conference on Space Optics ICSO 2016 Prepared by Raffello MIGLIORE Date , Biarritz.
International Conference on Space Optics ICSO 2016 Prepared by Raffello MIGLIORE Date 19.10.2016, Biarritz Outlook on EDRS-C EDRS-C / European Data Relay System EDRS-C, designed and developed by OHB System,
More informationBusiness Requirements Specification (BRS)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Business Requirements Specification (BRS) Business Domain: Contract Management Business
More informationStandardisation of PF/PL interfaces TAS point of view
ADCSS-2014 workshop Day 3 ESTEC October 29, 2014 30/10/2014 Standardisation of PF/PL interfaces TAS point of view 83230352-DOC-TAS-EN-002 Ref.: Agenda For Proteus, H/P, Sentinel 3, Telecom, the following
More informationOE-PM Project Charter Document
Enter Project Name Here Enter Department Name OE-PM Project Charter Document Status: (Draft or Published) Version: (0.# or 1.#) Prepared by: Date Created: Date Last Revised: OE-PM Artifact ID: P01.00 Internal
More informationSOLAR ORBITER ENERGETIC PARTICLE DETECTOR
Page: 1 of 19 SOLAR ORBITER ENERGETIC PARTICLE DETECTOR EPT-HET-2 FM Physical Document ID: SO-EPD-KIE-TP-0030 Issue: 1 Revision: 0 Date: 15/02/2016 Signature not needed if electronically approved by route
More informationI&T&C Organization Chart
I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS 4.1.9 I&T Engineer B. Grist WBS 4.1.9.1 Reliability & QA D. Marsh WBS 4.1.9.2 Mechanical Ground Support Equipment TBD Instrument Operations Coordinator
More informationATTACHMENT 2, EXHIBIT 3 Deliverable Expectation Document Template For [Deliverable Title]
ATTACHMENT 2, EXHIBIT 3 Expectation Document Template For [ Title] [This template provides a sample of the required contents of a Expectation Document (DED). Work plans that support the activity summary
More informationAn Overview of the WMKO Development Phases By Sean Adkins December 8, 2005
By Sean Adkins INTRODUCTION This document provides a brief description of the objectives and deliverables for each of the development phases in the new instrument development process at WMKO. THE DEVELOPMENT
More informationQuarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan
Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability
More informationIEC Test Equipment Requirements
OMICRON K02 03 20060309 IEC 61850 Test Equipment Requirements Dr. Alexander Apostolov K02 03 20060309 Page: 1 Intelligent Substation Automation Systems OMICRON K02 03 20060309 Page: 2 Intelligent Sensor
More informationThe Internet Society. on behalf of. The IETF Administrative Oversight Committee REQUEST FOR PROPOSALS. for
The Internet Society on behalf of The IETF Administrative Oversight Committee REQUEST FOR PROPOSALS for Requirements Development for Working Group Charter Tools Date of Issuance: September 20, 2010 Proposal
More informationJIRA User Manual [JIRA SUM] Issue: 2.1 Date: 01/05/2010 PMT MA ACS JI Project Management. Doc. No.: Issue: Date: Page:
i [JIRA SUM] 01/05/2010 ii Document Signature Table APPROVAL TABLE Date 01/09/2007 Name Function Signature R. Medri ACS Managing Director A.Vollono G.Pace Head of Space Application Department Head of Environmental
More informationC H A N G E R E C O R D
Page : 2 C H A N G E R E C O R D ISSUE / REVISION DATE PAGES MODIFICATIONS 1/- August 13 All Initial issue D I S T R I B U T I O N L I S T COMPANY NAME QUANTITY ESA : Roland Weigand 1 SYDERAL : Ph. Voisin
More informationThe S1000D Specification Year in Review Capstone Panel
It shall not be communicated to any third party without the owner s written consent. All rights reserved. The S1000D Specification Year in Review Capstone Panel S1000D Council & S1000D Steering Committee
More informationFault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc.
Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation Purpose: To establish an equitable process for allocating fault current margin, where available, to applicants
More informationSAVOIR Industrial Consultation
SAVOIR Industrial Consultation Jean-Loup TERRAILLON TEC-S Giorgio MAGISTRATI TEC-EDD Specification production scheme. Under SAG agreement; 1. A draft version is produced; By a SAG working group Output
More informationWashington State Emergency Management Association (WSEMA) Olympia, WA
Washington State Emergency Management Association (WSEMA) Olympia, WA Request for Proposals Website Redesign and Content Management and Maintenance System Proposal Submittal Deadline: I. Introduction and
More informationMapping of FedRAMP Tailored LI SaaS Baseline to ISO Security Controls
Mapping of FedRAMP Tailored LI SaaS Baseline to ISO 27001 Security Controls This document provides a list of all controls that require the Cloud Service Provider, Esri, to provide detailed descriptions
More informationDate of publication: 11/07/2017
Questions & Answers INVITATION TO SHIFT2RAIL JU ASSOCIATED MEMBERS TO SUBMIT AN ANSWER IN VIEW OF THE REALIGNMENT OF THEIR ACTIVITIES AND ADDITIONAL COMMITMENT TO THE SHIFT2RAIL PROGRAMME Date of publication:
More informationREAD ME for the Agency ATO Review Template
READ ME for the Agency ATO Review Template Below is the template that the FedRAMP Program Management Office (PMO) uses when reviewing an Agency ATO package. Agencies and CSPs should be cautious to not
More informationThe Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft
The Project Charter Project Title: VDI Data Center Design and Build Project Sponsor: South Alberta Data Centers Inc. (SADC Inc.) Project Customer: The City of Calgary Project Manager: Moe Yousof Document
More informationQUALITY SYSTEM PROCEDURE CONTROL OF RECORDS
Page : 1 of 11 0 01.04.17 Issued for Implementation S. Chauhan A. Bhargava (COO) Rev. Date Description Prepared Checked & No. By Approved By D.N.Pal (MR) Authorized By This document is exclusive property
More informationUK EPR GDA PROJECT. Name/Initials Date 30/06/2011 Name/Initials Date 30/06/2011. Resolution Plan Revision History
RP unique number: GI-UKEPR-CI-01-RP 0 30/06/2011 1 of 19 Approved for EDF by: A. PETIT Approved for AREVA by: C. WOOLDRIDGE Name/Initials Date 30/06/2011 Name/Initials Date 30/06/2011 Resolution Plan History
More informationService Description: Cisco Security Implementation Services. This document describes the Cisco Security Implementation Services.
Page 1 of 12 Service Description: Cisco Security Implementation Services This document describes the Cisco Security Implementation Services. Related Documents: This document should be read in conjunction
More informationSmart Metering Implementation Programme. Consultation on transitional arrangements in the Smart Energy Code
Smart Metering Implementation Programme Consultation on transitional arrangements in the Smart Energy Code Page 1 of 9 Contents 1 Executive Summary... 3 2 Communications Hubs... 5 3 Service Management...
More informationSecurity Control Mapping of CJIS Security Policy Version 5.3 Requirements to NIST Special Publication Revision 4 4/1/2015
U. S. Department of Justice Federal Bureau of Investigation Criminal Justice Information Services Division Security Control Mapping of CJIS Security Policy Version 5.3 s to NIST Special Publication 800-53
More informationTransition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007
Data Center Operations Outsourcing Transition Plan Implementation: Final Page 1 of 15 DOCUMENT CONTROL SHEET Schedule/Exhibit Amendment Control Sheet Title of Amended Document: Section 4 Transition Plan
More informationService Level Agreements Category 7 Network Based Managed Security
Service Level Agreements Category 7 Network Based Managed Security TROUBLE TICKET STO CLOCK CONDITIONS The following conditions shall be allowed to stop the trouble ticket Outage Duration for CALNET 3
More informationOpening New DOORS to Managing JSF Gun System Requirements Renee I. Bellack
Opening New DOORS to Managing JSF Gun System Requirements Renee I. Bellack 26 April 2005 Opening New DOORS Outline Entrance Evolution of Systems Previous Programs Current Challenge DOORS JSF Approach Exit
More informationCIP Cyber Security Security Management Controls. Standard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationSOLAR ORBITER ENERGETIC PARTICLE DETECTOR
Page: 1 of 19 SOLAR ORBITER ENERGETIC PARTICLE DETECTOR STEP FM Physical Properties Document ID: SO-EPD-KIE-TP-0033 Issue: 1 Revision: 0 Signature not needed if electronically approved by route Written
More informationDevelopment and Experimentation With a Small Satellite Bus Standard
OFFICE OF FORCE TRANSFORMATION Development and Experimentation With a Small Satellite Bus Standard 19 th Conference on Small Satellites 9 August 2005 Col. Jay Raymond John.Raymond@vandenburg. af.mil CDR
More informationCreate Service Contract
Create Service Contract This guide will cover: The process of creating service contracts with suppliers. This process replaces the Office of General Counsel Checklist (specifically the Overview tab). However,
More information<PROJECT NAME> IMPLEMENTATION PLAN
IMPLEMENTATION PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Implementation Plan was controlled and tracked.
More informationNational Smart Metering Program Testing Framework Work Stream Actions Log
- ustomer section of the table Description / Progress Source/Origin Workstream/ owner Who By When Status Reporting 20090923 4 TFWG need to feed into the BPPWG the issues about service levels and performance
More informationDoc Express Roles and Access. September 2016
Doc Express Roles and Access September 2016 Address: 5700 SW 34th Street, Suite 1235, Gainesville, Florida 32608-5371 Web: www.infotechfl.com Customer support is available by phone or email Monday through
More information<Project Name> Scope Management Plan. <Author> <Date> Name Date Reason For Changes Version <author> initial draft 1.0 draft1
Scope Management Plan 1.0 Revision History Name Date Reason For Changes Version initial draft 1.0 draft1 2.0 Statement of Purpose The purpose of this document
More informationVMware vcloud Air Accelerator Service
DATASHEET AT A GLANCE The VMware vcloud Air Accelerator Service assists customers with extending their private VMware vsphere environment to a VMware vcloud Air public cloud. This Accelerator Service engagement
More informationSERVICE LEVEL AGREEMENT
GMES TYPE 1 SLA ESRIN/Contract no. 19366/05/I-EC SERVICE LEVEL AGREEMENT V7 23 rd September 2005 An agreement between the SUPPLIER, the RECIPIENT and the Project Co-ordinator of Terrafirma services For
More informationQuestion & Answer #3
DARPA Blackjack Pit Boss Reference: HR001119S0012 Question & Answer #3 Question 53: Please clarify the WBS level the cost volume and Excel file should presented. Page 8 says Phase 1 should be broken down
More informationService Description: Identity Services Engine Implementation-Subscription Service
Page 1 of 6 Service Description: Identity Services Engine Implementation-Subscription Service Services Summary This document describes the Identity Services Engine Implementation. Subscription Service.
More informationPK0-003 Q&As. Project+ (2009) Pass CompTIA PK0-003 Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from:
PK0-003 Q&As Project+ (2009) Pass CompTIA PK0-003 Exam with 100% Guarantee Free Download Real Questions & Answers PDF and VCE file from: 100% Passing Guarantee 100% Money Back Assurance Following Questions
More informationAdmin Reporting: Citation Reporting
Admin Reporting: Citation Reporting Citation reporting is used to aggregate data from your organization s issued citations. Bringing your desired data together can help gain insight into the citation issuance
More informationEXHIBIT A: PROJECT SCOPE AND SCHEDULE The Project consists of the activities and delivery dates identified in this Exhibit A, implemented in accordance with the Agreement. The Parties have included a schedule
More information<Project Name> Configuration Management/Data Management Plan
[TYPE THE COMPANY NAME] Configuration Management/Data Management Plan Written By: Approved By: 4/28/2011 [Type the abstract of the document here. The abstract is typically a short summary
More informationThese Leased Lines Specific Terms and Conditions of Supply are to be read in conjunction with our General Terms and Conditions of Supply.
Leased Lines Specific Terms and Conditions 1 DEFINITIONS These Leased Lines Specific Terms and Conditions of Supply are to be read in conjunction with our General Terms and Conditions of Supply. All definitions
More informationUser guide - VIM plus AOG & RG - V1. New VIM plus AOG & RG. User guide
New VIM plus AOG & RG User guide What is it? (1/2) The Vendor Information Manual plus Aircraft On Ground and Repair Guide is a web-based tool enabling relevant Supplier Support contact details, including
More informationExhibit A1-1. Risk Management Framework
Appendix B presents the deliverables produced during the execution of the risk management approach to achieve the assessment and authorization process. The steps required by the risk management framework
More informationa ESRIN Via Galileo Galilei - Casella Postale Frascati - Italy Tel. (39) Fax (39)
D O C U M E N T document title/ titre du document RELIMINARY EQUIREMENTS RE EQUISITES FOR THE ARTH BSERVATION ATA AND NFORMATION ERVICES ORTAL prepared by/préparé par Marco Trovatello reference/réference
More informationExoMars Rover Vehicle
Page: 2 of 21 PAGE INTENTIONALLY LEFT BLANK Page: 3 of 21 TABLE OF CONTENTS 1 INTRODUCTION... 5 1.1 Purpose and Scope... 5 1.2 Priority of requirements... 5 1.3 Guidelines and Traceability... 5 2 DOCUMENTS...
More informationThis section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 CIP-012-1 Cyber Security Communications between Control Centers This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity:
More informationApril 2017: Information for TecDoc Data User and Data Supplier
: Content 0. Preface 1. General information concerning Data Release 0517 a. Update of Reference Data / Reference Data Version (DU) b. Pre announcement: Discontinuation of Table 402 (DU) c. Hint on Data-Delta-Distribution
More informationThe Geostationary Operational Satellite R Series (GOES-R) SpaceWire Implementation
The Geostationary Operational Satellite R Series (GOES-R) SpaceWire Implementation Session: SpaceWire Missions and Applications William H. Anderson NASA Goddard Space Flight Center/MEI Technologies E-mail:
More informationImplementation Plan for Newly Identified Critical Cyber Assets and Newly Registered Entities
Implementation Plan for Newly Identified Critical Cyber Assets and Newly Registered Entities This Implementation Plan applies to Cyber Security Standards CIP-002-2 through CIP-009-2 and CIP-002-3 through
More informationADDENDUM #001. Medical Supplies. July 24, 2018 at 2:00 p.m., Eastern Time
ADDENDUM #001 Solicitation : Solicitation Title: Opening Date/Time: Medical Supplies July 24, 2018 at 2:00 p.m., Eastern Time Addendum : 001 Failure to file a protest within the time prescribed in Section
More informationRTU presentation. Torbjörn Hult Chief Engineer, Digital Products RUAG SPACE ADCSS 2015, ESTEC
RTU presentation Torbjörn Hult Chief Engineer, Digital Products RUAG SPACE ADCSS 2015, ESTEC RUAG Space at a Glance Leading European space product supplier to the industry Acquisition of Saab Space and
More informationOnce your Project Plan Document is completed check the document against the following Quality Criteria:
HOW TO USE THIS TEMPLATE: Introduction The template reflects the steps set out in the PRINCE2 Method and is designed to prompt the Project Manager and help in the creation of the. The information for the
More informationCS 501- Software Engineering Legal Data Markup Software Release (V.1.0) Feasibility Report
CS 501- Software Engineering Legal Data Markup Software Release (V.1.0) Feasibility Report Version (1.1) Key Stakeholders/Organizations: Project Sponsors: Professor Thomas Bruce, Professor William Arms
More informationThe Copernicus Sentinel-3 Mission: Getting Ready for Operations
The Copernicus Sentinel-3 Mission: Getting Ready for Operations Susanne Mecklenburg ESA Sentinel-3 Mission Manager Sentinel-3 ESA development & operations teams Sentinel-3A Status S-3A Satellite on stand
More informationEA-ISP-002 Business Continuity Management and Planning Policy
Technology & Information Services EA-ISP-002 Business Continuity Management and Planning Policy Owner: Nick Sharratt Author: Paul Ferrier Date: 06/03/2018 Document Security Level: PUBLIC Document Version:
More informationAmendment #4 to the STRATUS MASTER CHANNEL PARTNER AGREEMENT ( Agreement ) Number dated July 8, 2014
Amendment #4 to the STRATUS MASTER CHANNEL PARTNER AGREEMENT ( Agreement ) Number 00004616 dated July 8, 2014 This amendment ( Amendment #4 ) is made as of August 29, 2017 (the Amendment #4 Effective Date)
More informationSilicon Valley Power Data Center Program Rebate Application
Contact Information Tax Status (check one) Sole Proprietor Contact Name Phone Corporation Partnership Company Email address Government Not-For-Profit Customer/Facility Information Company Name SVP Account
More informationSaving the Project Brief document under its own name
HOW TO USE THIS TEMPLATE: Introduction The template reflects the steps set out in the PRINCE2 Method and is designed to prompt the Project Manager and help in the creation of the. The information for the
More informationWindows 7 Deployment Key Milestones
Windows 7 Deployment Key Milestones 2012 2013 2014 Client Deployment and Management Tool Windows 7 Deployment Select Tool (3-6 months) Deployment Tool Architecture (1-2 months) Assess Hardware (1-2 months)
More informationStatement of Work (SOW) RFX Response Training guide
Updated: September 2016 Statement of Work (SOW) RFX Response Training guide Hewlett Packard Enterprise Global Procurement End to end process workflow SOW Request Evaluate & Source Engage (SOW) Implement
More informationTown of Gilmanton, New Hampshire SELECTMENS OFFICE
TOWN OF GILMANTON SELECTMEN S OFFICE PO Box 550, Gilmanton, NH 03237 Ph. 603-267-6700 Fax 603-267-6701 townadministrator@gilmantonnh.org Town of Gilmanton, New Hampshire SELECTMENS OFFICE REQUEST FOR PROPOSAL
More informationIEEE NEA Agenda and General Information. John D Ambrosia, Futurewei, a subsidiary of Huawei IEEE Jan 2018 Interim Geneva, CH
IEEE 802.3 NEA Agenda and General Information John D Ambrosia, Futurewei, a subsidiary of Huawei IEEE 802.3 Jan 2018 Interim Geneva, CH Agenda Wednesday 6:00 pm to 7:30pm a) Accumulated switch latency
More informationPBS Aligned with IMS. David E Black, Structnet. Notice: Data on this page is controlled by restrictions listed on the title page
PBS Aligned with IMS Notice: Data on this page is controlled by restrictions listed on the title page 1 Defined Process Tasks Requirements & Architecture 1. Work Authorization Complete 2. Requirements
More informationThis addendum is to provide all potential proponents with the information to the various questions received.
Addendum Number: 1 Request for Proposal: 2014-006 Multifunctional Devices and Print Services Date Issued: January 20, 2015 Issued by: Li Lei This addendum is to provide all potential proponents with the
More informationCompTIA Project+ (2009 Edition) Certification Examination Objectives
CompTIA Project+ (2009 Edition) Certification Examination Objectives DRAFT INTRODUCTION The Project + examination is designed for business professionals involved with projects. This exam will certify that
More information