Data Preparation Tools and Dynamic Models for System Studies with Distributed Series Impedances and Distributed Static Series Compensators

Size: px
Start display at page:

Download "Data Preparation Tools and Dynamic Models for System Studies with Distributed Series Impedances and Distributed Static Series Compensators"

Transcription

1 Data Preparation Tools and Dynamic Models for System Studies with Distributed Series Impedances and Distributed Static Series Compensators Presentation of Part 1 and Part 2 studies to MVWG Chifong Thomas Director, Transmission Planning and Strategy Smart Wires Inc. USA Anatoliy Meklin

2 Recent Developments for Smart Wires Completed installation of 90 PowerLine Guardian units as part of California EPIC Program in December 2015 using a helicopter installation method. Piloting our second-generation product, the Tower Router, at four utility partners in Energized installation under development Tower Router units on H-Frame Structure Helicopter installation tool PowerLine Guardians installed on 115 kv line Slide 2

3 Models and tools for Smart Wires System Performance Studies Models for Steady State Analysis The model for Steady State Simulations was developed by PowerWorld in the core of the PowerWorld Simulator. The program derives the number of modules to satisfy given objectives. DSR.p for PSLF, developed by USE. The program derives the number of modules to satisfy given objective, complying with the aggregated limitations for max/min impedances (for current limitation and regulation) and for max/min currents (for given impedance injection). A Python routine, also developed by USE for PSS/E. This Python routine provides similar functions as the DSR.p for PSLF. Steady State analyses to deploy Smart Wires technology can be performed with ordinary models of series reactors or phase shifting transformers. However, the process can be tedious and the specialized tools are developed to simply the studies. All steady state models and tools are indifferent to a dynamic process. Slide 3

4 Models and tools for Smart Wires System Performance Studies Dynamic Modeling Dynamic Models are needed for the SW devices, when accurate and fast module engagement is implemented, using the response-based control with local current relays and timers. Part 1 of the study justifies one possible local control setup with principals similar to the UFLS system. Due to the dynamic fluctuation prior to current settlement, the module engagement can be non-simultaneous, if module current and time settings are different. Furthermore, if some modules are injected a little earlier, other modules would be exposed to reduced current and may not trigger. Special dynamic models should be used to simulate the impact of module engagement on system performance. Development of the Dynamic Model is the urgent task for facilitating performance studies for systems with Smart Wire devices. The PSLF EPCMOD prototype of such a dynamic model was developed by SW and presented at the MVWG meeting in November The Part 2 of the SW study takes into account the MVWG recommendations. Slide 4

5 Recap - Detailed Dynamic Model Presented in November MVWG Meeting This model is for the most accurate studies and with a plenty of output. Requires appreciable additions in power flow and dynamic data for separate modeling of each module and surrounding line sections. Supported by the developed Data Builders. MVWG concern: The additions in PF cases could become critical in the future, when more lines will be equipped with the SW devices. MVWG recommendation: consider more generic modeling for ordinary studies to minimize data additions and eliminate convergence problems. Slide 5

6 Part 2 Study Generic Models (March 2016) Descriptions of the Model A and Model B types of local generic models. Working PSLF EPCMOD prototypes for both local models. Validity of the prototypes is verified by conducting many simulations, identical to conducted earlier (in Part 1) for the detailed model. Specifications of input and output parameters in the traditional form of specifications, used for PSLF dynamic models. Description, prototype program and specification for the remote control model. Modifications of the Excel based Data Builders to make them consistent with new dynamic models. The data preparation process is much simpler for the generic models, but the modified Data Builders could be still useful for the preparation of the initial set of data records. Comparison of the Detailed, A and B models and recommendations for their application. Slide 6

7 Generic Model A Model A does not need sectionalizing and changes in a PF case. All modules are fed by the same current, and each module insertion is modeled by changing line impedance or angle. Model A preserves the potential for counting irregularities of module setup and electrical parameters in the individual for each module invocations. Modules can be aggregated to switch in groups. Populating dynamic files by multiple invocations should not be critical with the increasing level of module aggregation. Model A does not have capability for monitoring flows and voltages in the points near actual individual module locations. Slide 7

8 Generic Model A Invocation Records for 13 Modules (11 arresting, 2 anti-stalling) EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #9 "SW-inject-A.p" 39 "time_hold " 2.0 / (anti-stalling 2) "level_up" "level_down" "time_up" 20.0 "time_down" 80 "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #0 "SW-inject-A.p" 39 "time_hold " 2.0/ (anti-stalling 1) "level_up" "level_down" "time_up" 15.0 "time_down" 75 "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #0 "SW-inject-A.p" 39 "time_hold " 2.0 / (arresting 11) "level_up" 1000 "level_down" "time_up" 5.0 "time_down" 70 "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #0 "SW-inject-A.p" 39 "time_hold " 2.0 / (arresting 10) "level_up" "level_down" "time_up" 5.0 "time_down" 65 "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #0 "SW-inject-A.p" 39 "time_hold " 2.0 / (arresting 2) "level_up" "level_down" "time_up" 5.0 "time_down" 25 "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #0 "SW-inject-A.p" 39 "time_hold " 2.0 / (arresting 1) "level_up" "level_down" "time_up" 5.0 "time_down" 20 "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" Slide 8

9 Generic Model B Model B also does not need sectionalizing and changes in a PF case. Contrary to Model A, it does not include separate invocations for each module. The multi-module model is used for sequential module logic execution. Module setup and electrical parameters are calculated in Model B prior to execution for particular module, based on the generic setup, reflected in only one invocation record. Generic Model B invocation record (single record) EPCMOD "ROUND_MT" 230 "1 " "COTWD_E" 230 "1 " 1 : #9 "SW-inject-B.p" 39 / "arrest#" 11 "ar_levelmax" 1000 "ar_levelmin" 900 "ar_time" 5 / "an-stall#" 2 "an-stall_level" 900 "an-stall_tmax" 20 "an-stall_tmin" 15 / "rstr_level" 850 "rstr_tmax" 80.0 "rstr_tmin" 20.0 / "rmodule" 0 "xmodule" 0 "angmodule" 0.1 "counter_#" "time_hold" 2.0 Slide 9

10 Generic Model B Simplest data preparation process for the SW control system with uniform structure and identical types of modules Absence of the editable invocation records makes impossible accommodation of irregularities in module types and control system configuration. Model B limitation might be caused by the need of retaining time counting data for many modules. That is necessary for reactivation of the time counting process with data from previous integration steps. That is particularly important for the timers of the arresting modules, which can start in different moments due to differences in current settings. Five specific variables per module should be retained to facilitate the sequential execution. For module N: storage1-n - module status; storage2-n - time-up" timer triggering time; storage3-n - time_up" timer triggering flag; storage4-n - time_up timer start time, sec. storage5-n - time_down timer start time, sec. About 100 storage variables, available for EPCMODs in the existing versions of GE PSLF can accommodate only 20 modules (or groups of modules). Model A with separate EPCMOD invocations does not have such a limitation. This limitation, probably, would not exist for the models functioning in the core of GE PSLF, or with PSS/E and PowerWorld. Slide 10

11 Remote Control Model The remote model is for joint operation of local and remote control, providing additional loading of a line, which is in the same path with the overloaded line. The remote actions are specified in switching sequences along with disturbances and ordinary RAS. Remote model may allow flow increasing module engagement, if 1) there is a sufficient room for flow increase and 2) some modules are engaged on the overloaded line. Slide 11

12 Recommendation Based on the model comparison, Smart Wires recommends primary implementation of Generic Model A, which is applicable with any irregularities in module control setup and parameters, and a mixture of module types. Inclusion of both types of generic models in the core of the stability packages should be also considered because that would give the user a choice of using a model, which is more consistent with a study type, a control system structure and its irregularities. Data preparation for Model A is much simpler than for the Detailed Model. The modified Data Builders could be still useful for the preparation of the initial set of invocation records to be corrected to reflect irregularities and a mixture of module types. There is no need for a Model B Data Builder. Slide 12

13 Additional Steps As the WECC Criteria for Acceptance of New Dynamic Models guideline suggest, SW has developed working model prototypes with modifications, recommended by MVWG; conducted validation studies for different operating conditions, and submitted the required documents and descriptions. SW requests a final MVWG review of the presented materials and identification of additional SW actions for model inclusion in the WECC Approved Dynamic Model Library. SW expects that MVWG descriptions of the necessary actions would include answers to the following questions: Can a completely functional EPCMOD type of PSLF dynamic model be included in the Library, or should it be incorporated in the core of the program? If using EPCMOD is acceptable, what tasks of the GE PSLF team might be needed for model inclusion in the Library? (a GE PSLF expert review certainly can reveal more elegant construction of some model fragments). Are EPCMOD review or inclusion in the core activities a part of the PSLF maintenance or should it be financed separately? Can the PSLF version of the model be included in the Library prior to model development completion for PSS/E and PowerWorld? Slide 13

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents

More information

WECC Load Modeling Task Force Updates

WECC Load Modeling Task Force Updates WECC Load Modeling Task Force Updates Irina Green California ISO, WECC LMTF Chair NERC Load Modeling Task Force Meeting November 1, 2017 Composite Load Model with Distributed Generation Composite Load

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (x) Guideline ( ) Report or other ( ) Charter M&VWG. Physical location: Web URL:

( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (x) Guideline ( ) Report or other ( ) Charter M&VWG. Physical location: Web URL: Document name Cross-Current Compensation Model Specification Category Document date June 18, 2015 Adopted/approved by ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (x) Guideline (

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models Problem Statement With the proliferation of distributed energy resources (DER), Transmission Planners must adapt

More information

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Steve Rutty Director, Grid Assets Lou Fonte Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Lead Engineer, Grid Assets September 3, 2014 Transmission Planning

More information

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY PURPOSE: The purpose of this lab is to introduce PSS/E. This lab will introduce the following aspects of PSS/E: Introduction to

More information

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Background Power Grid has evolved from a vertically integrated

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION

USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION H USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION Use Case Title Adaptive Transmission Line Protection Use Case Summary The requirements for improvement in the performance of protection relays under

More information

July 26, Dear Mr. Millar:

July 26, Dear Mr. Millar: July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 Dear Mr. Millar: As you are aware, Clean

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

10 th Annual University of Pittsburgh Electric Power Industry Conference

10 th Annual University of Pittsburgh Electric Power Industry Conference 10 th Annual University of Pittsburgh Electric Power Industry Conference System Studies for Grid Level Integration of Power Electronic Devices Presentation November 16, 2015 1:30 PM Session Adam R. Sparacino

More information

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused Keeping the Lights on for the Long Term The Basics Bonneville Power

More information

System Studies for American Transmission Co. s Benson Lake SVC Project

System Studies for American Transmission Co. s Benson Lake SVC Project Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC Outline Introduction

More information

Record Specification and File Format for Specifying Contingency Definitions and Remedial Actions Schemes

Record Specification and File Format for Specifying Contingency Definitions and Remedial Actions Schemes Record Specification and File Format for Specifying Contingency Definitions and Remedial Actions Schemes Matt Davis matt@powerworld.com 217 384 6330 Ext. 20 2001 South First Street Champaign, Illinois

More information

Grid Operations - Program 39

Grid Operations - Program 39 Grid Operations - Program 39 Program Description Program Overview In many ways, today's power system must be operated to meet objectives for which it was not explicitly designed. Today's transmission system

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

EMS / DMS. DISTRIBUTION MANAGEMENT SYSTEM- Functional Description

EMS / DMS. DISTRIBUTION MANAGEMENT SYSTEM- Functional Description EMS / DMS DISTRIBUTION MANAGEMENT SYSTEM- Content 1. INTRODUCTION... 4 2. MODES OF INTERACTION WITH THE SCADA SYSTEM... 5 2.1 Simulation Mode... 5 2.2 State Estimation Mode (See functional description

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Project Data Update Package Instruction Manual (PDUP-IM)

Project Data Update Package Instruction Manual (PDUP-IM) Project Data Update Package Instruction Manual (PDUP-IM) Date: April 11, 2018 Prepared by: Reviewed by: Approved by: Khalid Rafiq, P. Eng. Modelling Engineer, Transmission Project Delivery Christopher

More information

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines 1 B.T.RAMAKRISHNA RAO, 2 N.GAYATRI, 3 P.BALAJI, 4 K.SINDHU 1 Associate Professor, Department

More information

Multicomputer Research Desks for Simulation and Development of Control Systems

Multicomputer Research Desks for Simulation and Development of Control Systems Proceedings of the 17th World Congress The International Federation of Automatic Control Multicomputer Research Desks for Simulation and Development of Control Systems M.Kh. Dorri A.A. Roshchin Institute

More information

Denmarks Cable Policy

Denmarks Cable Policy Denmarks Cable Policy Landsnet Annual meeting 2014 March 20th 2014 Jens Møller Birkebæk Director, International Affairs 1 About Energinet.dk 3 Interconnector capacity 3 Agenda Danish Cable Policy 1. Political

More information

Proposals for the 2018 JHAQ data collection

Proposals for the 2018 JHAQ data collection EUROPEAN COMMISSION EUROSTAT Directorate F: Social statistics Unit F-5: Education, health and social protection DOC 2017-PH-02.2 Proposals for the 2018 JHAQ data collection Item 2.2 of the Agenda Meeting

More information

Modeling of RAS and Relays in Power Flow Contingency Analysis. Jamie Weber

Modeling of RAS and Relays in Power Flow Contingency Analysis. Jamie Weber Modeling of RAS and Relays in Power Flow Contingency Analysis Jamie Weber weber@powerworld.com 217 384 6330 ext. 13 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Proposed Improvements for NERC MOD Standards July 10, 2012

Proposed Improvements for NERC MOD Standards July 10, 2012 Agenda Item 3.6 Planning Committee Meeting September 18-19, 2012 Proposed Improvements for NERC MOD Standards July 10, 2012 Background This paper outlines proposed improvements for NERC Reliability Standards

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

N-1-1 Reactive Upgrades

N-1-1 Reactive Upgrades N-1-1 Reactive Upgrades Previous Analysis Discussed at November 2011 TEAC Voltage collapse for multiple 500 kv N-1-1 contingency pairs A number of reactive upgrade locations evaluated to determine a optimal

More information

Preparing for the Dynamic Grid of Future

Preparing for the Dynamic Grid of Future Preparing for the Dynamic Grid of Future Peter Hoffman, P.E. Duke Energy, Grid Solutions Engineering & Technology POWERING LIVES & COMMUNITIES Environmental Stewardship Reliable Service Affordable Rates

More information

CIP Standards Update. SANS Process Control & SCADA Security Summit March 29, Michael Assante Patrick C Miller

CIP Standards Update. SANS Process Control & SCADA Security Summit March 29, Michael Assante Patrick C Miller CIP Standards Update SANS Process Control & SCADA Security Summit March 29, 2010 Michael Assante Patrick C Miller Background FERC s Cyber Security Order 706 directed extensive modifications of CIP-002

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

WECC and Base Case Development Process D E C E M B E R 1 2, J O N AT H A N Y O U N G

WECC and Base Case Development Process D E C E M B E R 1 2, J O N AT H A N Y O U N G WECC and Base Case Development Process D E C E M B E R 1 2, 2 0 1 8 J O N AT H A N Y O U N G How Base Cases are Built for the Biennial Transmission Expansion Plan? Study Assumptions & Case Selection Case

More information

ECC Chaining Modules

ECC Chaining Modules Union Switch & Signal Inc., an Ansaldo Signal company 1000 Technology Drive, Pittsburgh, PA 15219 645 Russell Street, Batesburg, SC 29006 SM 9488 ECC Chaining Modules Input Isolation Module Bipolar Output

More information

STCP22-1 Issue 003 Production of Models for GB System Planning

STCP22-1 Issue 003 Production of Models for GB System Planning STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission

More information

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides

More information

Joint Transmission Planning Base Case Preparation Process

Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Southern California Edison Joint Transmission Planning Base Case Preparation Process NERC Reliability Standard MOD-032-1 Version 1.2 August 31, 2017 INTENTIONALLY

More information

Dynamic Load Models in PowerWorld Simulator

Dynamic Load Models in PowerWorld Simulator Dynamic Load Models in PowerWorld Simulator Jamie Weber (weber@powerworld.com) Director of Software Development 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

University of California, Santa Cruz Baskin Engineering School Electrical Engineering Department

University of California, Santa Cruz Baskin Engineering School Electrical Engineering Department Lab-2 Intro, rev2.0, page 1 University of California, Santa Cruz Baskin Engineering School Electrical Engineering Department Laboratory 2 Tutorial Addendum Introduction to POWERWORLD Simulator EE175L Power

More information

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

PowerWorld Tutorial. Yen-Yu Lee The University of Texas at Austin Jan 18, Updated December 26, 2012, by Ross Baldick

PowerWorld Tutorial. Yen-Yu Lee The University of Texas at Austin Jan 18, Updated December 26, 2012, by Ross Baldick PowerWorld Tutorial Yen-Yu Lee The University of Texas at Austin Jan 18, 2010 Updated December 26, 2012, by Ross Baldick 1 Introduction PowerWorld is one of the most popular power system simulation tools.

More information

Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool. Eleanor Ewry

Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool. Eleanor Ewry Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool Eleanor Ewry Engineer October 21, 2014 Overview Introduction to Composite Load Model Introduction to Time Step Simulation (TSS)

More information

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY Inverter Based Generators 25 kw and This document contains the interconnection requirements for inverter based generators, 25 kw and smaller, that operate

More information

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013 Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently

More information

POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER

POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER Puranik Sahu 1, Arun Pachori 2 1 puranik1987@gmail.com Abstract: To transmit or distribute fixed amount of power at fixed voltage, the conductor

More information

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

Overview of the Multi-Payer Claims Database (MPCD)

Overview of the Multi-Payer Claims Database (MPCD) Overview of the Multi-Payer Claims Database (MPCD) Genesis of the MPCD The MPCD project is one of a number of initiatives related to comparative effectiveness research (CER) funded by the American Recovery

More information

Training Workshop Identification and Evaluation of Environmental and Social Risks in Credit Processes

Training Workshop Identification and Evaluation of Environmental and Social Risks in Credit Processes Training Workshop Identification and Evaluation of Environmental and Social Risks in Credit Processes Melissa Makwarimba Moscow, 14 th December 2011 Introduction Part of UNEP FI s support to build capacity

More information

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region Kuwait - November 2011 GCC Cigre, is pleased to announce its 7 th International Conference GCC

More information

Requirements for Model Validation

Requirements for Model Validation Draft Need Requirements Application for Model Validation Reporting Requirements for Model Validation Reporting for Generators and Generator Control Systems Revision 0 Wednesday 16 November 2005 Prepared

More information

NEW PROTECTION COORDINATION SYSTEM ACCORDING TO ESS AND RENEWABLE ENERGY EXPANSION

NEW PROTECTION COORDINATION SYSTEM ACCORDING TO ESS AND RENEWABLE ENERGY EXPANSION NEW PROTECTION COORDINATION SYSTEM ACCORDING TO ESS AND RENEWABLE ENERGY EXPANSION Kang-se, LEE Jong-myung, KIM Boo-hyun, SHIN KEPCO-HQ, Korea KEPCO-HQ, Korea KEPCO-HQ, Korea accent@kepco.co.kr aimhigh@kepco.co.kr

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 978 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE MP 1.1 Objective

More information

Specifics of Implementation

Specifics of Implementation Specifics of Implementation Defining Criteria Filtering ModelCondition ModelFilter Conditional Contingency Actions CriteriaStatus = POSTCHECK ModelExpression (lookup tables) RemedialAction Complexity of

More information

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, 2018 1:00 p.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 1:00-1:10 Stakeholder Process and Schedule Kristina Osborne

More information

Distribution Static Var Compensators and Static Synchronous Compensators for Suppressing Voltage Fluctuation

Distribution Static Var Compensators and Static Synchronous Compensators for Suppressing Voltage Fluctuation Distribution Static Var Compensators and Static Synchronous Compensators for Suppressing Voltage Fluctuation KOJIMA, Takehiko * ISOTANI, Hitoshi * YAMADA, Makoto * A B S T R A C T The rapidly expanding

More information

Smart Grids, Telecontrol and the New Standards. Reliable and secure communication with zenon Process Gateway

Smart Grids, Telecontrol and the New Standards. Reliable and secure communication with zenon Process Gateway Smart Grids, Telecontrol and the New Standards Reliable and secure communication with zenon Process Gateway Smart Grids, Telecontrol and the New Standards Reliable and secure communication with zenon Process

More information

MISO Transmission Planning BPM 020 Updates February 16, 2016

MISO Transmission Planning BPM 020 Updates February 16, 2016 MISO Transmission Planning BPM 020 Updates February 16, 2016 Purpose Present final updated BPM 20 language Objectives for Today Purpose and Objectives Briefly discuss posted stakeholder comments and MISO

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

ISO New England Data Modeling Requirements

ISO New England Data Modeling Requirements A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Comparison of Shunt Facts Devices for the Improvement of Transient Stability of Two Machine

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50 BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50 VOLTAGE STABILITY OPERATING LIMITS AND PROCEDURES FOR USING THE REAL TIME VOLTAGE STABILITY APPLICATION (RTVSA) Supercedes 7T-50 dated 02 May

More information

National Pooling Administration Contract #FCC13C nd Revised Change Order Proposal #3B

National Pooling Administration Contract #FCC13C nd Revised Change Order Proposal #3B National Pooling Administration Contract #FCC13C0007 2 nd Revised Change Order Proposal #3B (Development and Support of the PAS NPAC API) March 8, 2017 Neustar, Inc. 21575 Ridgetop Circle Sterling VA,

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia Page 1 of 15 British Columbia Utilities Reliability Standards with s adopted in British Columbia BAL-001-2 Standard Real Power Balancing Control Performance R-14-16 July 1, 2016 BAL-002-1 1 Disturbance

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Automated Firewall Change Management Securing change management workflow to ensure continuous compliance and reduce risk

Automated Firewall Change Management Securing change management workflow to ensure continuous compliance and reduce risk Automated Firewall Change Management Securing change management workflow to ensure continuous compliance and reduce risk Skybox Security Whitepaper January 2015 Executive Summary Firewall management has

More information

Supplemental Programmatic Environmental Assessment (SPEA) for the Proposed

Supplemental Programmatic Environmental Assessment (SPEA) for the Proposed This document is scheduled to be published in the Federal Register on 12/15/2016 and available online at https://federalregister.gov/d/2016-30187, and on FDsys.gov 9110-9P DEPARTMENT OF HOMELAND SECURITY

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

Ch 5 Industrial Control Systems

Ch 5 Industrial Control Systems Ch 5 Industrial Control Systems Sections: 1. Process Industries vs. Discrete Manufacturing Industries 2. Continuous vs. Discrete Control 3. Computer Process Control Industrial Control - Defined The automatic

More information

Simulation of Power System Faults for Protection Performance Analysis -Case Studies of Tata Power

Simulation of Power System Faults for Protection Performance Analysis -Case Studies of Tata Power Simulation of Power System Faults for Protection Performance Analysis -Case Studies of Tata Power By S G Patki M V Kini P K Jain G T Jawale Presented at: International Conference on Power System Protection,

More information

SECTION SPECIAL SYSTEMS. Website and Construction Cameras

SECTION SPECIAL SYSTEMS. Website and Construction Cameras PART 1 GENERAL SECTION 01121 SPECIAL SYSTEMS 1.01 WORK INCLUDED A. Project Construction Site Cameras and Video Streaming Servers B. Project Web site C. Network & Infrastructure D. Internet Connectivity

More information

Industry Classification Methodology Guide. ISE Cyber Security Industry Classification

Industry Classification Methodology Guide. ISE Cyber Security Industry Classification Industry Classification Methodology Guide ISE Cyber Security Industry Classification 1 Table of Contents Chapter 1. Introduction... 3 Chapter 2. Industry Classification... 4 2.1. Structure and Changes...

More information

Application Guideline for BOP/Volume Zone Business Support Coordinator UZBEKISTAN in FY 2015

Application Guideline for BOP/Volume Zone Business Support Coordinator UZBEKISTAN in FY 2015 Application Guideline for BOP/Volume Zone Business Support Coordinator UZBEKISTAN in FY 2015 April 7, 2015 Manabu Shimoyashiro President Director JETRO Tashkent The Japan External Trade Organization, JETRO

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

WEB ACCESSIBILITY. I. Policy Section Information Technology. Policy Subsection Web Accessibility Policy.

WEB ACCESSIBILITY. I. Policy Section Information Technology. Policy Subsection Web Accessibility Policy. WEB ACCESSIBILITY I. Policy Section 15.0 Information Technology II. Policy Subsection 15.2 Web Accessibility Policy III. Policy Statement Grand Rapids Community College is actively committed to providing

More information

Final Project Report

Final Project Report 16.04.02 Final Project Report Document information Project Title HP Tool Repository of SESAR standard HP methods and tools Project Number 16.04.02 Project Manager DFS Deliverable Name 16.04.02 Final Project

More information

DeviceNet of Things Use Cases, Value Proposition and Status of Specification. John Caspers Rockwell Automation. February 22, 2017

DeviceNet of Things Use Cases, Value Proposition and Status of Specification. John Caspers Rockwell Automation. February 22, 2017 DeviceNet of Things Use Cases, Value Proposition and Status of Specification John Caspers Rockwell Automation February 22, 2017 DeviceNet of Things The increased popularity of EtherNet/IP and the Internet

More information

Executive Summary for deliverable D6.1: Definition of the PFS services (requirements, initial design)

Executive Summary for deliverable D6.1: Definition of the PFS services (requirements, initial design) Electronic Health Records for Clinical Research Executive Summary for deliverable D6.1: Definition of the PFS services (requirements, initial design) Project acronym: EHR4CR Project full title: Electronic

More information

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM 52 CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM 4.1 INTRODUCTION Flexible AC Transmission System (FACTS) controllers have been used in power systems with the objective of improving system

More information

APPENDIX F THE TCP/IP PROTOCOL ARCHITECTURE

APPENDIX F THE TCP/IP PROTOCOL ARCHITECTURE APPENDIX F THE TCP/IP PROTOCOL ARCHITECTURE William Stallings F.1 TCP/IP LAYERS... 2 F.2 TCP AND UDP... 4 F.3 OPERATION OF TCP/IP... 6 F.4 TCP/IP APPLICATIONS... 10 Copyright 2014 Supplement to Computer

More information

Alberta Reliability Standards Compliance Monitoring Program. Version 1.1

Alberta Reliability Standards Compliance Monitoring Program. Version 1.1 Version 1.1 Effective: January 14, 2011 Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Applicability... 1 4. Definitions... 1 5. Compliance Monitoring Overview... 2 6. Monitoring Tools... 1

More information

SDG&E s Accomplishments and Future Plans

SDG&E s Accomplishments and Future Plans SDG&E s Accomplishments and Future Plans Tariq Raman and Subbu Sankaran San Diego Gas & Electric Work Group Meeting October 23-24, 2018 San Diego Gas & Electric San Francisco SDG&E Los Angeles San Diego

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY POLICY P-22 TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY Preamble It is recognized that while reliable and sophisticated telecommunication facilities are a benefit to the citizens of (CSRD),

More information

ERO Enterprise Strategic Planning Redesign

ERO Enterprise Strategic Planning Redesign ERO Enterprise Strategic Planning Redesign Mark Lauby, Senior Vice President and Chief Reliability Officer Member Representatives Committee Meeting February 10, 2016 Strategic Planning Redesign Current

More information

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017

More information