CUSTOMER. Data Center Functional Testing [location] Data Center. Prepared by: Leading Edge Design Group. Prepared For: [CUSTOMER] [address] [address]

Size: px
Start display at page:

Download "CUSTOMER. Data Center Functional Testing [location] Data Center. Prepared by: Leading Edge Design Group. Prepared For: [CUSTOMER] [address] [address]"

Transcription

1 CUSTOMER Data Center Functional Testing [location] Data Center Prepared by: Leading Edge Design Group Prepared For: [CUSTOMER] [address] [address] [date]

2 [DATE] [CUSTOMER] [NAME] [ADDRESS] [ADDRESS] Project: [CUSTOMER] Data Center Functional Testing I. EXECUTIVE SUMMARY We are pleased to provide the enclosed Data Center Functional Testing Report associated with the new [CUSTOMER] data center in [LOCATION]. The objective of the functional testing initiative is to analyze the performance of the data center physical infrastructure to verify the equipment operates as expected and in consistent with design conditions. To perform this testing, active equipment was installed in the data center racks to simulate live IT load. II. METHODOLOGY Based on the data provided by [CUSTOMER] and [PROJECT STAKEHOLDER] the following field conditions were utilized as the basis of testing: 1. 3 (three) data center rows are installed in the new facility. Only Row 1 and 2 are expected to be populated with equipment on day 1 and functional testing was conducted on Row 1 and Row 2 only. 2. The basis of design for IT load per rack was 5.5kW per rack. 3. (model xxxxxx) is installed as the primary cooling methodology in the data center. The cooling has been designed with N+1 redundancy such that a single in row cooling unit can fail without compromising the environmental conditions in the data center. 4. [CUSTOMER] seeks to maintain inlet rack temperatures within ASHRAE Tc9.9 recommendations. The cooling setpoint (measured at the server inlet) established for the data center was 68degF. To administer the functional testing under these conditions, the following methodology was employed: 1. 1 (one) Microstar 17.1kW load bank was installed in each data center rack being tested. Load banks were factory tested for performance prior to arrival onsite (six) power cords for each load bank were installed and separated across the redundant 0U rack PDUs (rpdu) installed in each rack. 3 (three) power cords were connected to each 0U rpdu to simulate expected data center conditions and balance power across phases during testing. 3. During all testing, dry bulb temperature readings were gathered in 3 (three) locations across the vertical face of the rack to validate cooling system performance in all rack U positions. These temperature readings are represented on the enclosed reports as Temp F Top, Temp F Middle, and Temp F Bottom 86 Chosen Vale Lane Suite 201 Enfield, NH info@ledesigngroup.com ledesigngroup.com

3 4. All testing was completed in coordination with onsite APC field service technicians who were responsible for operating data center equipment. 5. A pass condition represents that the cooling equipment successfully maintained rack inlet temperature conditions within ASHRAE Tc9.9 conditions. III. FUNCTIONAL TESTS All functional testing was completed onsite by Leading Edge Design Group on [DATE]. The table below represents each of the 11 (eleven) functional tests performed. Please reference enclosed drawing T1.0 for further information on rack nomenclature utilized during testing and enclosed functional test reports for detailed information on each test. FUNCTIONAL TEST SUMMARY Row Test Test 1 Objective Status Number 1 1 Normal 5.5kW Validate performance under normal Pass cooling conditions 1 2 Normal load cooling Validate N+1 redundancy requirement Pass redundancy test under failure condition at unit #1 1 3 Normal load cooling Validate N+1 redundancy requirement Pass redundancy test under failure condition at unit #3 1 4 Normal load cooling Validate N+1 redundancy requirement Pass redundancy test under failure condition at unit #5 1 5 Upper Limit 7.5kW Validate performance under expected Pass upper rack loading limit of 7.5kW Upper limit cooling Validate N+1 redundancy requirement Pass redundancy test at upper rack load limit under failure of cooling unit #4 2 1 Normal 5.5kW Validate performance under normal Pass cooling conditions 2 2 Normal load cooling Validate N+1 redundancy requirement Pass redundancy test under failure condition at unit #1 2 3 Normal load cooling Validate N+1 redundancy requirement Pass redundancy test under failure condition at unit #3 2 4 Normal load cooling Validate N+1 redundancy requirement Pass redundancy test 2 5 Upper limit cooling redundancy test 3 under failure condition at unit #5 Validate N+1 redundancy requirement at upper rack load limit under failure of cooling unit #4 1 It was noted that no blanking panels were installed onsite during the time of testing. It is recommended that these are installed to optimize cooling performance 2 7.5kW upper limit was defined onsite by customer 3 Cooling unit #4 failure simulation was conducted in Row 1. Measurements taken at server inlet during this condition were in Row 2. Pass

4 IV. SUMMARY Based on the basis of testing outlined in Section II and the data collected onsite by Leading Edge Design Group on [DATE], the cooling equipment in the [CUSTOMER] data center is functioning in a manner consistent with the design conditions and owner expectations. It was noted that under redundancy verification in upper limit testing (7.5kW per rack), some in row cooling units generated alarm conditions that the cooling set point of 68degF was unable to be maintained. Test data demonstrates that, although the set point could not be maintained, the server inlet temperatures in this test scenario were maintained within ASHRAE TC9.9 standards. Thank you for the opportunity to collaborate with you on your data center project needs. We are grateful for the chance to work with you and the entire team at [CUSTOMER]. Respectfully Submitted, Todd Boucher, Principal Leading Edge Design Group

5 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 1 - Row 2 Normal 5.5kW Row 2 Cold Aisle RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 1, Row 2 - Rack Inlet Temperatures

6 Date/Time Project Number Test FUNCTIONAL TESTING REPORT [DATE][TIME] [CUSTOMER] Functional Testing [NUMBER] Test 2 - Row 2 Failure Simulation - Cooling Unit #1 5.5kW Row 2 Cold Aisle RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 2, Row 2 - Rack Inlet Temperatures

7 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 3 - Row 2 Failure Simulation - Cooling Unit #3 5.5kW Row 2 Cold Aisle RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 3, Row 2 - Rack Inlet Temperatures

8 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 4 - Row 2 Failure Simulation - Cooling Unit #5 5.5kW Row 2 Cold Aisle RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 4, Row 2 - Rack Inlet Temperatures

9 Date/Time Project Number Test FUNCTIONAL TESTING REPORT [DATE][TIME] [CUSTOMER] Functional Testing [NUMBER] Test 5 - Row 2 Failure Simulation - Cooling Unit #4 (failed unit in Row 1) 7.5kW Row 2 Cold Aisle RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 5, Row 2 - Rack Inlet Temperatures

10 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 2 - Row 1 Failure Simulation - Cooling Unit #1 5.5kW RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 2, Row 1 - Rack Inlet Temperatures 70.2

11 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 3 - Row 1 Failure Simulation - Cooling Unit #3 5.5kW RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 3, Row 1 - Rack Inlet Temperatures

12 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 4 - Row 1 Failure Simulation - Cooling Unit #5 5.5kW RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 4, Row 1 - Rack Inlet Temperatures

13 FUNCTIONAL TESTING REPORT Date/Time [DATE][TIME] Project [CUSTOMER] Functional Testing Number [NUMBER] Test Test 5 - Row 1 Normal 7.5kW RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 5, Row 1 - Rack Inlet Temperatures

14 Date/Time Project Number Test FUNCTIONAL TESTING REPORT [DATE][TIME] [CUSTOMER] Functional Testing [NUMBER] Test 6 - Row 1 Failure Simulation - Cooling #4 7.5kW RACK A RACK B RACK C RACK D RACK E RACK F RACK G RACK H Test 6, Row 1 - Rack Inlet Temperatures

1.0 Executive Summary

1.0 Executive Summary Statement of Work - 1 - Power and Cooling Assessment for Data Center Professional Services Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service

More information

1.0 Executive Summary. 2.0 Features and Benefits

1.0 Executive Summary. 2.0 Features and Benefits Table of Contents 1.0 EXECUTIVE SUMMARY 2.0 FEATURES AND BENEFITS 3.0 DETAILS OF SERVICE 4.0 Deliverable 5.0 Exclusions 6.0 SCOPE OF RESPONSIBILITY 7.0 PROJECT WORK DETAILS 8.0 ORDERING INFORMATION 9.0

More information

Recapture Capacity for Existing. and Airflow Optimization

Recapture Capacity for Existing. and Airflow Optimization Recapture Capacity for Existing Data Centers Through Cooling and Airflow Optimization Introduction Challenges and Trends Agenda Cooling & Airflow Optimization Takeaways Learning Objectives Recognize opportunities

More information

Close Coupled Cooling for Datacentres

Close Coupled Cooling for Datacentres Close Coupled Cooling for Datacentres Dr Fathi Tarada Mosen Ltd fathi.tarada@mosenltd.com www.mosenltd.com Agenda Increasing Power Densities Raised Floor Limitations Hot and Cold Aisle Enclosures Close

More information

18 th National Award for Excellence in Energy Management. July 27, 2017

18 th National Award for Excellence in Energy Management. July 27, 2017 18 th National Award for Excellence in Energy Management July 27, 2017 ICICI Bank, Data Centre, August Hyderabad 30 & 31, 2017 ICICI Bank - Revolution in Digital Banking Over 100,000 Digital POS in 4 months

More information

1.0 Executive Summary. 2.0 Available Features & Benefits

1.0 Executive Summary. 2.0 Available Features & Benefits Statement Of Work Energy Management Services Table of Contents 1.0 Executive Summary 2.0 Available Features & Benefits 3.0 Assessment Deliverables Selection 4.0 On Site Assessment Activities 5.0 Exclusions

More information

Power and Cooling for Ultra-High Density Racks and Blade Servers

Power and Cooling for Ultra-High Density Racks and Blade Servers Power and Cooling for Ultra-High Density Racks and Blade Servers APC White Paper #46 Richard L. Sawyer Director of Data Center Technology American Power Conversion Company 2005 APC corporation What has

More information

APC InRow Cooler Prototype Initial Report - Test Setup Verification. H. Coles, S. Greenberg Contributing: J. Bean (APC) November 18, 2011

APC InRow Cooler Prototype Initial Report - Test Setup Verification. H. Coles, S. Greenberg Contributing: J. Bean (APC) November 18, 2011 APC InRow Cooler Prototype Initial Report - Test Setup Verification H. Coles, S. Greenberg Contributing: J. Bean (APC) November 18, 2011 1 Introduction Contents Technology Description/Attributes Installation

More information

84 kw, Tier 3, Direct Expansion, 937 ft 2

84 kw, Tier 3, Direct Expansion, 937 ft 2 [Reference Design 42] 84 kw, Tier 3, Direct Expansion, 937 ft 2 DESIGN OVERVIEW Data Center IT Capacity 84 kw Target Availability Tier 3 Annualized PUE at 100% Load 1.712 Total Racks and Average Density

More information

Mission Critical Facilities & Technology Conference November 3, 2011 Cooling 101. Nick Gangemi Regional Sales Manager Data Aire

Mission Critical Facilities & Technology Conference November 3, 2011 Cooling 101. Nick Gangemi Regional Sales Manager Data Aire Mission Critical Facilities & Technology Conference November 3, 2011 Cooling 101 Nick Gangemi Regional Sales Manager Data Aire Agenda Exactly what are we talking about ASHRAE TC 9.9 Design best practices

More information

Data Center Energy Savings By the numbers

Data Center Energy Savings By the numbers Data Center Energy Savings By the numbers Chris Kurkjian, PE HP Critical Facility Services provided by EYP Mission Critical Facilities 2008 Hewlett-Packard Development Company, L.P. The information contained

More information

Air Containment Design Choices and Considerations

Air Containment Design Choices and Considerations Air Containment Design Choices and Considerations Brad J. Murphy, A.Sc.T., ATS, DCDC, DCEP, Principal Racon Data Centres Introduction Introduction Air containment design must consider many different factors

More information

Power & Cooling Considerations for Virtualized Environments

Power & Cooling Considerations for Virtualized Environments Power & Cooling Considerations for Virtualized Environments Cisco Data Center Day 2008 31-01-2008 APC-MGE Vision & Mission OUR VISION APC-MGE products ensure availability wherever data is created, transmitted

More information

Running Your Data Center Under Ideal Temperature Conditions

Running Your Data Center Under Ideal Temperature Conditions TECHNICAL BRIEF Mastering Data Center Environmental Controls to Help Drive Your Bottom Line Running Your Data Center Under Ideal Temperature Conditions Challenge Many data centers waste energy using inefficient

More information

Future of Cooling High Density Equipment. Steve Madara Vice President and General Manager Liebert Precision Cooling Business Emerson Network Power

Future of Cooling High Density Equipment. Steve Madara Vice President and General Manager Liebert Precision Cooling Business Emerson Network Power Future of Cooling High Density Equipment Steve Madara Vice President and General Manager Liebert Precision Cooling Business Emerson Network Power Agenda Issues facing the Data Center Managing the explosive

More information

APC APPLICATION NOTE #74

APC APPLICATION NOTE #74 #74 Configuration of InfraStruXure for Data Centers to Support Dell PowerEdge 1855 Abstract Many companies are making plans to incorporate Dell PowerEdge Blade Servers into their data center applications.

More information

Creating an Energy-Efficient, Automated Monitoring System for Temperature and Humidity at a World-Class Data Center

Creating an Energy-Efficient, Automated Monitoring System for Temperature and Humidity at a World-Class Data Center About CyrusOne CyrusOne is a world-renowned enterprise data center provider that offers 40 data centers across the U.S., Europe and Asia with a three million-plus square feet of total net rentable space.

More information

Introducing the Heat Wheel to the Data Center

Introducing the Heat Wheel to the Data Center Introducing the Heat Wheel to the Data Center Robert (Dr. Bob) Sullivan, Ph.D. Data Center Infrastructure Specialist KyotoCooling International Critical Facilities Round Table 1 A New Free Cooling Technique

More information

Trends in Data Center Energy Efficiency

Trends in Data Center Energy Efficiency Trends in Data Center Energy Efficiency Presented by: Todd Boucher Better Building by Design 2012 1 Efficiency Vermont is a Registered Provider with The American Institute of Architects Continuing Education

More information

Optimizing Cooling Performance Of a Data Center

Optimizing Cooling Performance Of a Data Center ASHRAE www.ashrae.org. Used with permission from ASHRAE Journal. This article may not be copied nor distributed in either paper or digital form without ASHRAE s permission. For more information about ASHRAE,

More information

APC APPLICATION NOTE #114

APC APPLICATION NOTE #114 APPLICATION NOT #4 Using the Rack Air Containment System with the InfraStruXure InRow SC By David Roden Abstract The InfraStruXure InRow SC (ACSC00 and ACSC0) is a self-contained air conditioner for server

More information

CyrusOne Case Study About CyrusOne

CyrusOne Case Study About CyrusOne CyrusOne Case Study About CyrusOne CyrusOne is a world-renowned enterprise data center provider that offers 31 data centers across the U.S., Europe and Asia with a three million-plus square feet of total

More information

Efficiency of Data Center cooling

Efficiency of Data Center cooling Efficiency of Data Center cooling Comparison of data room layouts and cooling systems Bohumil Cimbal Product manager for Cooling Systems in CONTEG Company Objective Basic questions between investor and

More information

Tripp Lite PDUs POWER DISTRIBUTION UNITS. Reliable rack power distribution for high-density IT environments. Introduction 2-3.

Tripp Lite PDUs POWER DISTRIBUTION UNITS. Reliable rack power distribution for high-density IT environments. Introduction 2-3. POWER DISTRIBUTION UNITS Tripp Lite rack power distribution for high-density IT environments. Introduction 2-3 Basic 4 Metered 5 Monitored 6 Switched 7 ATS 8 Hot-Swap 8 INTRODUCTION Tripp Lite Rack increase

More information

Planning for Liquid Cooling Patrick McGinn Product Manager, Rack DCLC

Planning for Liquid Cooling Patrick McGinn Product Manager, Rack DCLC Planning for Liquid Cooling -------------------------------- Patrick McGinn Product Manager, Rack DCLC February 3 rd, 2015 Expertise, Innovation & Delivery 13 years in the making with a 1800% growth rate

More information

Cooling. Highly efficient cooling products for any IT application. For More Information: (866) DATA CENTER SOLUTIONS

Cooling. Highly efficient cooling products for any IT application. For More Information: (866) DATA CENTER SOLUTIONS Cooling > Highly efficient cooling products for any IT application. DATA CENTER SOLUTIONS For More Information: (866) 787-3271 Sales@PTSdcs.com End-to-End Cooling Solutions from the Closet to the Data

More information

Data Centre Optimisation Services

Data Centre Optimisation Services Data Centre Solutions Expertly Engineered Current Total Energy Consumption *14 Tera Watt Hours Estimated Energy Saving 5.6 Tera Watt Hours Potential Energy Consumption 8.4 Tera Watt Hours Average PUE1.8

More information

Smart Data Centres. Robert M Pe, Data Centre Consultant HP Services SEA

Smart Data Centres. Robert M Pe, Data Centre Consultant HP Services SEA Smart Data Centres Robert M Pe, Data Centre Consultant Services SEA 2006 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice Content Data center

More information

APC InfraStruXure Solution Overview

APC InfraStruXure Solution Overview APC InfraStruXure Solution Overview We re waiting for your call or email. 800--0 uptime@uptimeu.com Wiring Closets ( Racks) Small Server Rooms ( Racks) Small Data Centers ( 0 Racks) Medium Data Centers

More information

APC APPLICATION NOTE #146

APC APPLICATION NOTE #146 #146 Hot Aisle Containment Application Guidelines and Approved Configurations By Kevin Lemke Abstract The Hot Aisle Containment System (HACS) is a modular ceiling panel and door system for use in isolating

More information

15 Ways Belden Helps Reduce Human Error to Improve Uptime

15 Ways Belden Helps Reduce Human Error to Improve Uptime 15 Ways Belden Helps Reduce Human Error to Improve Uptime Up to 75% of data center downtime is caused by human error. While no data center is capable of being completely immune to mistakes, implementing

More information

Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency

Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency A White Paper from the Experts in Business-Critical Continuity TM Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency Executive Summary Energy efficiency

More information

SmartRow Intelligent, Integrated Infrastructure in a Self-Contained Line-Up. Solutions For Business-Critical Continuity

SmartRow Intelligent, Integrated Infrastructure in a Self-Contained Line-Up. Solutions For Business-Critical Continuity SmartRow Intelligent, Integrated Infrastructure in a Self-Contained Line-Up Solutions For Business-Critical Continuity Deploy a Fully Configured Data Center in Just Weeks Efficiency. Capacity. Availability.

More information

Innovative Data Center Efficiency Techniques. Michael K Patterson, PhD PE Eco-technology Program Office Intel Corporation

Innovative Data Center Efficiency Techniques. Michael K Patterson, PhD PE Eco-technology Program Office Intel Corporation Innovative Data Center Efficiency Techniques Michael K Patterson, PhD PE Eco-technology Program Office Intel Corporation 1 Alternate titles.. Crisis or opportunity? Never build a new data center! Improve

More information

Ten Cooling Solutions to Support High-density Server Deployment. Schneider Electric Data Center Science Center White Paper #42

Ten Cooling Solutions to Support High-density Server Deployment. Schneider Electric Data Center Science Center White Paper #42 Ten Cooling Solutions to Support High-density Server Deployment Schneider Electric Data Center Science Center White Paper #42 1 Introduction 2 Introduction This paper provides 10 approaches for increasing

More information

Solutions Guide for Cisco UCS B and C Series Servers

Solutions Guide for Cisco UCS B and C Series Servers Solutions Guide for Cisco UCS B and C Series Servers The Cisco Unified Computing System is a next-generation data center platform that unites compute, network, storage access, and virtualization into a

More information

APC by Schneider Electric Elite Data Centre Partner

APC by Schneider Electric Elite Data Centre Partner Data Centre Solutions...energy efficient by design APC by Schneider Electric Elite Data Centre Partner APC s leading Elite Data Centre Solutions Partner providing customers with expert advice, integration

More information

APC by Schneider Electric Solutions for Cisco Unified Computing System (UCS) Blade Applications

APC by Schneider Electric Solutions for Cisco Unified Computing System (UCS) Blade Applications APC by Schneider Electric Solutions for Cisco Unified Computing System (UCS) Blade Applications The Cisco Unified Computing System is a next-generation data center platform that unites compute, network,

More information

Performance Evaluation for Modular, Scalable Cooling Systems with Hot Aisle Containment in Data Centers. Final Report

Performance Evaluation for Modular, Scalable Cooling Systems with Hot Aisle Containment in Data Centers. Final Report Performance Evaluation for Modular, Scalable Cooling Systems with Hot Aisle Containment in Data Centers Final Report To The California Energy Commission May 2009 Tengfang Xu Environmental Energy Technologies

More information

MEASURE MONITOR UNDERSTAND

MEASURE MONITOR UNDERSTAND MEASURE MONITOR UNDERSTAND Presented by Alistair Hunt Energy Monitoring, Measurement metrics Where and What 1 History & Background Company Timeline 18 Years Comrac & Sinetica founded 15 Years Raritan Integration

More information

Installation Service. 1.0 Executive Summary. Factory Trained Technician Train Customer Support Staff On Basic Operation Of The Equipment

Installation Service. 1.0 Executive Summary. Factory Trained Technician Train Customer Support Staff On Basic Operation Of The Equipment Installation Service Statement of Work Start-up Service for Cooling Start-up - 1 - Service for Cooling Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0

More information

APC Next Generation Rack ATS

APC Next Generation Rack ATS APC Next Generation Rack ATS Automatic switching power redundancy for single corded equipment. Next Generation Rack ATS with multiple outlets eliminate the need for a secondary Rack PDU downstream of Rack

More information

Avoidable Mistakes that Compromise Cooling Performance in Data Centers and Network Rooms

Avoidable Mistakes that Compromise Cooling Performance in Data Centers and Network Rooms Avoidable Mistakes that Compromise Cooling Performance in Data Centers and Network Rooms Problem Several cooling system mistakes are very common and avoidable Mistakes compromise availability and increase

More information

Frequently Asked Questions

Frequently Asked Questions Q. What is the power metering accuracy on CPI econnect PDUs? A. The power metering accuracy on CPI econnect PDUs is ±1% for each breaker. Meters are included in Monitored, Monitored, Switched and Switched

More information

Reclaim Wasted Cooling Capacity Now Updated with CFD Models to Support ASHRAE Case Study Data

Reclaim Wasted Cooling Capacity Now Updated with CFD Models to Support ASHRAE Case Study Data White Paper EC9005A Reclaim Wasted Cooling Capacity Now Updated with CFD Models to Support ASHRAE Case Study Data Peer reviewed case study data from ASHRAE now updated with CFD model analysis revealing

More information

Power Monitoring in the Data Centre

Power Monitoring in the Data Centre Power Monitoring in the Data Centre Fixed or Wireless Steve Strange RCDD ANIXTER INTERNATIONAL Agenda Energy Consumption Case Study Reasons to Monitor Power Monitoring Environmental Monitoring Asset Tags

More information

<Insert Picture Here> Austin Data Center 6Sigma DC CFD Model

<Insert Picture Here> Austin Data Center 6Sigma DC CFD Model Austin Data Center 6Sigma DC CFD Model Keith Ward Keith Ward Data Center Facilities Engineering and Logistics Design Austin Data Center Statistics - Space Original AT&T Designed and

More information

Current Data Center Design. James Monahan Sept 19 th 2006 IEEE San Francisco ComSoc

Current Data Center Design. James Monahan Sept 19 th 2006 IEEE San Francisco ComSoc Current Data Center Design James Monahan Sept 19 th 2006 IEEE San Francisco ComSoc What is the biggest facility problem in your data center? 35% 30% 25% 20% 15% Series1 10% 5% 0% Excessive heat Insufficient

More information

Density in the Data Center

Density in the Data Center Density in the Data Center INDUSTRY BRIEF Aug 2014 Density in the datacenter refers to the electric power consumed per square foot of floor space (or unit volume of space), number of servers, and the cooling

More information

How to Increase Data Center Efficiency

How to Increase Data Center Efficiency How to Increase Data Center Efficiency Shivani Shukla Potkar Product Marketing Manager Pentair Electronics Protection High cooling efficiency & and reduced power consumption enhances the balance between

More information

ANCIS I N C O R P O R A T E D

ANCIS I N C O R P O R A T E D Thermal Design of Data Centers to Safeguard Electronic Equipment Presentation at the Thermal Design Center Santa Clara, CA, March 9, 2010 Magnus K. Herrlin, Ph.D. President Incorporated mherrlin@ancis.us

More information

Moving Containment Inside the Enclosure. Jeff Markle Great Lakes Case & Cabinet

Moving Containment Inside the Enclosure. Jeff Markle Great Lakes Case & Cabinet Moving Containment Inside the Enclosure Presented by Jeff Markle Great Lakes Case & Cabinet Containment Containment : To put constraint upon; to restrain; to confine; to keep within bounds Containment

More information

Enabling Business Critical Continuity for Unified Communications. Andy Liu Product Manager, Asia Pacific

Enabling Business Critical Continuity for Unified Communications. Andy Liu Product Manager, Asia Pacific Enabling Business Critical Continuity for Unified Communications Andy Liu Product Manager, Asia Pacific Emerson Creating Technology and Solutions for a World in Action #1 AC & DC Power System #1 OEM Embedded

More information

Impact of Air Containment Systems

Impact of Air Containment Systems White Paper June 2012 WP-20 Impact of Air Containment Systems Reducing Energy Consumption Introduction: The Importance of Maintaining Data Center Cooling Energy Efficiency Data centers are mission-critical

More information

Total Modular Data Centre Solutions

Total Modular Data Centre Solutions Sector Data Centre Total Modular Data Centre Solutions www.airedale.com BRITISH MANUFACTURER ENERGY EFFICIENCY CONTROLS SERVICE TRAINING 01 Standardised Modular Designs to fit your needs Our modular system

More information

DCIM Data Center Infrastructure Management

DCIM Data Center Infrastructure Management DCIM Data Center Infrastructure Management Part 2 Implementation Challenges & Strategic Advantages - Predictive Analysis August 8, 2013 Presented by Julius Neudorfer Sponsored by Today s Topics Implementation

More information

ASHRAE IRELAND HVAC FOR DATA CENTRES. Michael Geraghty Building Services Engineer (DipEng) Company owner and managing director

ASHRAE IRELAND HVAC FOR DATA CENTRES. Michael Geraghty Building Services Engineer (DipEng) Company owner and managing director ASHRAE IRELAND HVAC FOR DATA CENTRES Michael Geraghty Building Services Engineer (DipEng) Company owner and managing director michael@entropic.ie OVERVIEW OF THE MARKET SITUATION IN IRELAND Relative Data

More information

Google s Green Data Centers: Network POP Case Study

Google s Green Data Centers: Network POP Case Study Google s Green Data Centers: Network POP Case Study Table of Contents Introduction... 2 Best practices: Measuring. performance, optimizing air flow,. and turning up the thermostat... 2...Best Practice

More information

Green Sustainable Data Centres. Checklist - EU Code of Conduct on Data Centres. Annex

Green Sustainable Data Centres. Checklist - EU Code of Conduct on Data Centres. Annex Green Sustainable Data Centres Checklist - EU Code of Conduct on Data Centres Annex This course is produced under the authority of e-infranet: http://e-infranet.eu/ Course team prof. dr. Colin Pattinson,

More information

1.1 ANNUAL DATA CENTER HEALTH CHECK

1.1 ANNUAL DATA CENTER HEALTH CHECK Statement of Work Maintenance Service 1.0 Executive Summary - 1 - Service Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service 4.0 Assumptions 5.0 Scope of Responsibility

More information

Case study on Green Data Center. Reliance Jio Infocomm Limited

Case study on Green Data Center. Reliance Jio Infocomm Limited Case study on Green Data Center 2 What is data center? Use and functions of Data Center. Basic Infrastructure requirement for data center. Energy consumption heads in data center. 3 What is Data Center

More information

AisleLok Modular Containment vs. Legacy Containment: A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings

AisleLok Modular Containment vs. Legacy Containment: A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings WHITE PAPER AisleLok Modular Containment vs. : A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings By Bruce Long, Upsite Technologies, Inc. Lars Strong, P.E., Upsite Technologies, Inc.

More information

2016 COOLING THE EDGE SURVEY. Conducted by Vertiv Publication Date: August 30, 2016

2016 COOLING THE EDGE SURVEY. Conducted by Vertiv Publication Date: August 30, 2016 2016 COOLING THE EDGE SURVEY Conducted by Vertiv Publication Date: August 30, 2016 TWO STAGE POWER DISTRIBUTION Table of Contents Section I: Methodology Section II: Key Findings 1. Strategic Importance

More information

Experimental Study of Airflow Designs for Data Centers

Experimental Study of Airflow Designs for Data Centers Experimental Study of Airflow Designs for Data Centers Takashi Tsuchiya*, Yoshihide Suwa 2 and Ryozo Ooka 3 Technical Research Institute, Obayashi Corporation, M. Eng., Japan 2 Technical Research Institute,

More information

Symmetra PX. Symmetra PX 48kW Scalable from 16kW to 48kW. Modular, Scalable, High-Efficiency Power Protection for Data Centers

Symmetra PX. Symmetra PX 48kW Scalable from 16kW to 48kW. Modular, Scalable, High-Efficiency Power Protection for Data Centers Modular, Scalable, High-Efficiency Power Protection for Data Centers Symmetra PX 48kW Scalable from 16kW to 48kW > High Performance, Right-Sized 3-Phase Power Protection with Industry-Leading Efficiency,

More information

Capacity and Power Management: The Forgotten Factors in Disaster Recovery Planning Presented by: Clemens Pfeiffer CTO Power Assure, Inc.

Capacity and Power Management: The Forgotten Factors in Disaster Recovery Planning Presented by: Clemens Pfeiffer CTO Power Assure, Inc. Capacity and Power Management: The Forgotten Factors in Disaster Recovery Planning Presented by: Clemens Pfeiffer CTO Power Assure, Inc. The Purpose of a Data Center Provide IT equipment a healthy environment

More information

Server Technology Inc.

Server Technology Inc. Server Technology Inc. Power Efficiency Gains by Deploying 415 VAC Power Distribution in North American Data Centers White Paper STI-100-008 2011-Sept-22 Headquarters Server Technology, Inc. 1040 Sandhill

More information

Customizable Colocation: Building for the Future

Customizable Colocation: Building for the Future Customizable Colocation: Building for the Future IronGate Data Centers meets the exact needs of customers with flexible Data Center Infrastructure solutions from Schneider Electric IronGate Data Centers

More information

Overcoming the Challenges of Server Virtualisation

Overcoming the Challenges of Server Virtualisation Overcoming the Challenges of Server Virtualisation Maximise the benefits by optimising power & cooling in the server room Server rooms are unknowingly missing a great portion of their benefit entitlement

More information

Practical Lessons from Data Centre Design and Testing Zac Potts

Practical Lessons from Data Centre Design and Testing Zac Potts Practical Lessons from Data Centre Design and Testing Zac Potts Associate Director of Data Centre Design Introduction and Overview of Data Centre Design and Engineering Principles Tier Ratings and Standards

More information

Evaporative free air cooling technology Providing evaporative free air cooling solutions.

Evaporative free air cooling technology Providing evaporative free air cooling solutions. Evaporative free air cooling technology Providing evaporative free air cooling solutions. Creating an effective workspace environment data centre free air cooling technology FreeCool - Evaporative Free

More information

3300 kw, Tier 3, Chilled Water, 70,000 ft 2

3300 kw, Tier 3, Chilled Water, 70,000 ft 2 [Reference Design 22] 3300 kw, Tier 3, Chilled Water, 70,000 ft 2 DESIGN OVERVIEW Data Center IT Capacity 1100 kw per Data Hall 3 Independent Data Halls Design Application Range This design can be applied

More information

Energy Logic: Emerson Network Power. A Roadmap for Reducing Energy Consumption in the Data Center. Ross Hammond Managing Director

Energy Logic: Emerson Network Power. A Roadmap for Reducing Energy Consumption in the Data Center. Ross Hammond Managing Director Energy Logic: A Roadmap for Reducing Energy Consumption in the Data Center Emerson Network Power Ross Hammond Managing Director Agenda Energy efficiency Where We Are Today What Data Center Managers Are

More information

Trellis TM Quick Start Thermal Management Guide Specifications

Trellis TM Quick Start Thermal Management Guide Specifications Trellis TM Quick Start Thermal Management Guide Specifications 1.0 General 1.1 Overview This document includes the specifications and features of the Trellis Quick Start Thermal Management package. These

More information

Data Center Checklist

Data Center Checklist Data Center Checklist The use of colocation and services has continued to increase, rapidly becoming the solution of choice for organizations requiring an efficient, secure, cost-effective way to manage

More information

Powering Change in the Data Center. A White Paper from the Experts in Business-Critical Continuity TM

Powering Change in the Data Center. A White Paper from the Experts in Business-Critical Continuity TM Powering Change in the Data Center A White Paper from the Experts in Business-Critical Continuity TM Executive Summary Increases in data center density and diversity are driving change in the power and

More information

How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions

How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions Intel Intelligent Power Management Intel How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions Power savings through the use of Intel s intelligent

More information

Close-coupled cooling

Close-coupled cooling Close-coupled cooling Intelligently controlled high-performance InRow cooling for the IT environment APC TM by Schneider Electric close-coupled cooling products provide a modular, scalable, and predictable

More information

How to Configure a Micro DC Xpress in Local Edge Configurator

How to Configure a Micro DC Xpress in Local Edge Configurator How to Configure a Micro DC Xpress in Local Edge Configurator Table of Contents. Create a New Solution on designportal.apc.com.... Open the Catalog and Choose the Micro DC Xpress You Want... 3. Configure

More information

Virtualization and consolidation

Virtualization and consolidation Virtualization and consolidation Choosing a density strategy Implementing a high-density environment Maximizing the efficiency benefit Anticipating the dynamic data center Schneider Electric 1 Topical

More information

Case Study Leicester City Council

Case Study Leicester City Council Data Centre Solutions...energy efficient by design Case Study Leicester City Council Leicester City Council Deploys New Sub 1.1 PUE3 Data Centre Infrastructure. Designed & Installed by Workspace Technology

More information

Green IT. Finding Practical Efficiencies. Infrastructure Planning and Facilities. Green IT: Finding Practical Efficiencies

Green IT. Finding Practical Efficiencies. Infrastructure Planning and Facilities. Green IT: Finding Practical Efficiencies Green IT Finding Practical Infrastructure Planning and Facilities Dan Francis dfrancis@ipf.msu.edu David Graff dsgraff@ipf.msu.edu William Lakos wjlakos@ipf.msu.edu 1 2 MSU Historical Energy Efficiency

More information

APC APPLICATION NOTE #126

APC APPLICATION NOTE #126 #16 Selection Procedure for Inow Chilled Water Products By Greg Uhrhan, P.E. and Scott Buell Abstract Proper selection of Inow chilled water cooling systems requires an engineer or technical salesperson

More information

Trading TCO for PUE? A Romonet White Paper: Part I

Trading TCO for PUE? A Romonet White Paper: Part I Trading TCO for PUE? A Romonet White Paper: Part I Executive Overview Most data center vendors claim to improve Power Usage Effectiveness (PUE). The problem with this is that focusing on reducing PUE makes

More information

SmartAisle Intelligent, Integrated Infrastructure Using Row-based Building Blocks. Solutions For Business-Critical Continuity

SmartAisle Intelligent, Integrated Infrastructure Using Row-based Building Blocks. Solutions For Business-Critical Continuity SmartAisle Intelligent, Integrated Infrastructure Using Row-based Building Blocks Solutions For Business-Critical Continuity Deploy An Efficient and Flexible Row-Based Infrastructure Efficiency. Capacity.

More information

Scalable, Secure. Jason Rylands

Scalable, Secure. Jason Rylands Energy Efficient, Modular, Scalable, Secure Jason Rylands The planning, construction and operation of IT infrastructure for mission critical applications in reliable Datacentres represents a real challenge.

More information

Survey and Audit Service Schedule. Airflow and Thermal Imaging Survey Service Schedule. Data Centre Solutions Expertly Engineered

Survey and Audit Service Schedule. Airflow and Thermal Imaging Survey Service Schedule. Data Centre Solutions Expertly Engineered Survey and Audit Service Schedule Airflow and Thermal Imaging Survey Service Schedule Data Centre Solutions Expertly Engineered Consult optimisation, audit and survey services Data Centre Services Workspace

More information

Improving Rack Cooling Performance Using Blanking Panels

Improving Rack Cooling Performance Using Blanking Panels Improving Rack Cooling Performance Using Blanking By Neil Rasmussen White Paper #44 Revision 1 Executive Summary Unused vertical space in open frame racks and rack enclosures creates an unrestricted recycling

More information

Existing Building Commissioning Guidelines (ASHRAE Guidelines 0.2 & 1.2) Mark F. Miller, PE, CCP Principal - Strategic Building Solutions, LLC

Existing Building Commissioning Guidelines (ASHRAE Guidelines 0.2 & 1.2) Mark F. Miller, PE, CCP Principal - Strategic Building Solutions, LLC Existing Building Commissioning Guidelines (ASHRAE Guidelines 0.2 & 1.2) Mark F. Miller, PE, CCP Principal - Strategic Building Solutions, LLC Overview ASHRAE Guidelines for EBCX Best Practices General

More information

LANL High Performance Computing Facilities Operations. Rick Rivera and Farhad Banisadr. Facility Data Center Management

LANL High Performance Computing Facilities Operations. Rick Rivera and Farhad Banisadr. Facility Data Center Management Slide-1 LANL High Performance Computing Facilities Operations Rick Rivera and Farhad Banisadr Facility Data Center Management Division Slide-2 Outline Overview - LANL Computer Data Centers Power and Cooling

More information

Where s the Heat Coming From. Leland Sparks Global Account Technical Consultant Belden

Where s the Heat Coming From. Leland Sparks Global Account Technical Consultant Belden Where s the Heat Coming From Leland Sparks Global Account Technical Consultant Belden What is the greatest DC challenge you face? Air Flow to Heat Load Relation Server Inlet Fans Chips Outlet LOAD Dell

More information

Green IT and Green DC

Green IT and Green DC Green IT and Green DC Alex SL Tay Regional Service Product Line Manager Site & Facilities Services, IBM ASEAN 1 What our clients are telling us We are running out of space in our data center We have environmental

More information

Thermal management. Thermal management

Thermal management. Thermal management Thermal management Thermal management Managing thermal loads is a major challenge for all Data Centre operators. Effecting proper control of the thermal environment drives energy consumption and ultimately

More information

How to Configure a Micro DC Xpress in Local Edge Configurator as a Partner

How to Configure a Micro DC Xpress in Local Edge Configurator as a Partner How to Configure a Micro DC Xpress in Local Edge Configurator as a Partner Table of Contents. Login to Your Partner Page.... Create a New Solution... 4 3. Open the Catalog and Choose the Micro DC Xpress

More information

Retro-Commissioning of Data Centers

Retro-Commissioning of Data Centers Retro-Commissioning of Data Centers Agenda Unique traits of Data Centers (DCs) Benefits of Retro-Cx DCs Suitable candidates for Retro-Cx Phases of Retro-Cx Additional considerations for DCs 2 Unique Traits

More information

Industry leading low energy evaporative fresh air cooling.

Industry leading low energy evaporative fresh air cooling. Industry leading low energy evaporative fresh air cooling. Freecool Evaporative Free Air Cooling by Workspace Technology delivers innovative low energy cooling for a range of applications including data

More information

Metered Rack PDU Rack PDU, Metered, Zero U, 20A, 120V, (24) NEMA 5-20R

Metered Rack PDU Rack PDU, Metered, Zero U, 20A, 120V, (24) NEMA 5-20R Metered Rack PDU Rack PDU, Metered, Zero U, 20A, 120V, (24) NEMA 5-20R APC Metered Rack PDU, Input: 120V, Input Connections: NEMA L5-20P, Cord Length: 10 feet ( 3.05 meters ), Output: 120V, Output Connections:

More information

QuickSpecs. HP Performance Optimized Datacenter (POD) 20ce. Overview. Retired

QuickSpecs. HP Performance Optimized Datacenter (POD) 20ce. Overview. Retired Overview The HP Performance-Optimized Data Center (HP POD) is a containerized datacenter equipped with power infrastructure, cooling and IT power distribution. The HP POD can be deployed within weeks instead

More information

Energy Efficiency Best Practice Guide Data Centre and IT Facilities

Energy Efficiency Best Practice Guide Data Centre and IT Facilities 2 Energy Efficiency Best Practice Guide Data Centre and IT Facilities Best Practice Guide Pumping Systems Contents Medium-sized data centres energy efficiency 3 1 Introduction 4 2 The business benefits

More information

Data center cooling evolution. The hottest way to save energy. Lucio Bustaffa: Product Development Manager BlueBox Group

Data center cooling evolution. The hottest way to save energy. Lucio Bustaffa: Product Development Manager BlueBox Group Data center cooling evolution. The hottest way to save energy Lucio Bustaffa: Product Development Manager BlueBox Group Data Center overview What s happening in the web? 2 Data Center overview What s happening

More information