Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Size: px
Start display at page:

Download "Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group"

Transcription

1 Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

2 Table of Contents 1. Introduction Purpose Customer Eligibility Obtain Required Documentation from EPE Website New Mexico Customers Texas Customers Application Process New Mexico Renewable Energy Interconnection Process Flow New Mexico Application Process Texas Renewable Energy Interconnection Process Flow Texas Application Process Technical Requirements Sample One-Line Diagram Checklists New Mexico Checklist Texas Checklist EPE Field Inspection System Expansion Expansion Application Process Renewable Energy System Ownership Change Ownership Change Application Process Downloading Required Documentation from EPE Website Appendix A: Sample Forms 11. Appendix B: Simplified Interconnections Terms and Conditions 12. Appendix C: Safety Recommendations (Please make sure Blue Books Standards are followed) 13. Appendix D: Type of Service Voltages 14. Appendix E: Technical Requirements for Interconnections and Parallel Operation of Qualifying Facilities 10 kw or Less

3 1. Introduction El Paso Electric (EPE) is committed to providing its customers with reliable and high quality electric power; as part of this commitment, EPE is supporting and promoting the development of renewable energy projects in its service territory. EPE actively seeks to further develop renewable energy programs and partnerships that will help increase the electric generation from renewable energy projects. Conveniently, the fast development of technology has made the use of natural resources accessible for the production of electrical power at a lower price than it was a decade ago. The EPE Renewable Energy Interconnection program enables EPE s customers that have a renewable system installed at their residence or business to interconnect with EPE s grid. The installation and interconnection of a renewable system to EPE s grid will not only reduce the customer s kwh consumption from EPE, but will also help the environment to be less impacted by electric generation using non-renewable resources. 2. Purpose The purpose of this manual is to provide EPE s customers with the necessary information to successfully complete the Interconnection Packet for a renewable system. This packet must be processed prior to any system interconnection to EPE s grid. This manual includes the required forms and completion guidelines for an accurate inclusion of all pertinent information in the Interconnection packet. Additionally, this manual includes a brief description of the procedure that the Interconnection Application Packet follows in order to be processed by EPE, as well as the roles and responsibilities of the customer and EPE. 3. Customer Eligibility 3.1 Obtain Required Documentation from EPE Website Customers may find all necessary forms and additional information by visiting EPE s website. Please click on the following link to be directed to EPE s website: Note: Section 9 Downloading Required Documents from EPE Website provides additional guidelines for obtaining these documents. 3.2 New Mexico Customers All EPE New Mexico customers are eligible to interconnect their renewable energy system to EPE s grid as long as the EPE established requirements for interconnection are met. The customer is 1 P age

4 required to submit an Interconnection Packet to EPE which consists of the following documents that must be accurately completed (Customers may download the forms at the website address listed below): TWO originals of the Simplified Interconnection Application Forms completely and accurately filled out; /Simplified_Interconnection_Application-Form_40.pdf A one-line diagram (please include the side and top view) that includes the location of the meters and the A/C Disconnect and all necessary technical data; Line_Diagram_2011.pdf ONE $50 checks, one for the Simplified Interconnection Applications processing fee (please make checks payable to EPE); ONE original NM Renewable Energy Facility Ownership Status form, completely and accurately filled out wable_energy_facility_ownership_status.pdf ONE W-9 Form accurately filled out and signed by the customer applying for interconnection; and, ONE Form 35 Notice of Self Certification Technical Specifications or Technical Data Sheets. The documents previously mentioned must be included in order to process the Interconnection Packet. The customer may submit the Interconnection Application forms with original electronic signature but please note that no copies will be accepted. Additional and optional documents include: An Authorization Agreement for Direct Deposit Form; Note: Customer applying for interconnection must be one of the EPE s account owner of record. 2 P age

5 eement_for_direct_deposits_customers.pdf For more information on the Purchase Power Service Rate, please refer to Rate 16 on EPE s website or follow the link below: d_power_stamped.pdf For more information on the Small Renewables Energy Certificate Purchase, please refer to Rate 33 on EPE s website or follow the link below: The Interconnection Packet and/or related documentation must be mailed to: 3.3 Texas Customers Renewables Development El Paso Electric (loc. 131) P.O Box 982 El Paso, Texas All EPE Texas customers are eligible to interconnect their renewable energy system to EPE s grid as long as the EPE established requirements for interconnection are met. The customer is required to submit an Interconnection Packet to EPE that consists of the following documents accurately completed: TWO originals of the Interconnection and Parallel Operation of Distributed Generation with the Utility System Applications; ction Parallel_Operation_of_DG_.pdf A one-line diagram (side view and top view too) that includes the location of the meters and the A/C Disconnect and all necessary technical data; and, Line_Diagram_2011.pdf Technical Specifications or Technical Data Sheets. The documents previously mentioned must be included in order to process the Interconnection Packet. Please note that customer may submit the Interconnection Application forms with original electronic signature but no copies will be accepted. ONE W-9 Form accurately filled out and signed by the customer applying for interconnection; 3 P age

6 ONE Interconnection Application Fee as Applicable please refer to page one of the Interconnection Application for details. Additional and optional documents include: ONE original TX Renewable Energy Facility Ownership Status form, completely and accurately filled out; _Energy_Facility_Ownership_Status.TX.pdf ONE Renewable Energy Credit Microgenerator Listing Form Credit_Microgenerator_Listing_Form.pdf REC Management Agreement Required by PUCT Subst Rule q (2) Agreement_Required_by_PUCT_Subst_Rule_25_173_q_2.pdf For more information on the Purchase Power Service Rate, please refer to Rate 48 on EPE s website or follow the link below: Firm_Purchased_Power pdf The Interconnection Packet and/or related documentation must be mailed to: Renewables Development El Paso Electric (loc. 131) P.O Box 982 El Paso, Texas P age

7 4. Application Process 4.1 New Mexico Renewable Energy Interconnection Process Flow 5 P age

8 4.2 New Mexico Application Process: Step 1: Step 2: Step 3: Step 4: Step 5: Step 6: Step 7: Customer completes Interconnection Packet and mails it to EPE Renewables Development Department. EPE Renewables Development reviews Interconnection Packet for completion and accuracy of forms. EPE Renewables Development initiates the process of the Interconnection application by reviewing the information provided for interconnection (e.g. name, address, account number, technical information, etc.) One-line diagram is submitted for review and technical approval by EPE Meter Test and EPE Engineering Departments. Please refer to Section 5. Technical Requirements for more information. If one-line diagram is not approved, EPE Renewables Development notifies the customer and informs customer of necessary changes. The customer must submit a revised oneline diagram for new review and technical approval. EPE Renewables Development informs the customer of technical review approval. The customer initiates the construction of the renewable energy system. Note: Communication is via by submitting an inquiry through smallrenewables@epelectric.com or by contacting EPE Renewables Development at , ext or ext Upon completion of system construction, the customer obtains the electrical release from the corresponding City/County and requests an EPE field inspection by contacting EPE Renewables Development at smallrenewables@epelectric.com. Please refer to Section 6.3 EPE Field Inspection to review the field inspection request checklist. An EPE Meter Test inspector visits the system site and performs the field inspection. If field inspection is not approved, EPE Renewables Development notifies the customer and 6 P age

9 informs necessary changes to be performed. The customer requests a new field inspection upon integration of changes. Step 8: Step 9: EPE Renewables Development informs the customer of field inspection approval and informs EPE internal groups for rate assignment and meter order to be issued. EPE internal groups perform their tasks and the EPE Meter Test inspector installs the new meters. NET and REC meters are installed. Step 10: The renewable energy system goes on-line. Step 11: One executed contract is mailed back to the customer and the other one is filed for EPE records. 7 P age

10 4.3 Texas Renewable Energy Interconnection Process Flow 8 P age

11 4.4 Texas Application Process: Step 1: Step 2: Step 3: Step 4: Step 5: Step 6: Step 7: Customer completes Interconnection Packet and mails it to EPE Renewables Development Department. EPE Renewables Development reviews Interconnection Packet for completion and accuracy of forms. EPE Renewables Development initiates the process of the Interconnection application by reviewing the information provided for interconnection (e.g. name, address, account number, technical information, etc.) One-line diagram is submitted for review and technical approval by EPE Meter Test and EPE Engineering Departments. Please refer to Section 5. Technical Requirements for more information. If one-line diagram is not approved, EPE Renewables Development notifies the customer and informs of necessary changes. The customer must submit a revised one-line diagram for new review and technical approval. EPE Renewables Development informs the customer of technical review approval. The customer initiates the construction of the renewable energy system. Note: Communication is via by submitting an inquiry to smallrenewables@epelectric.com or by the customer contacting Renewables Development at ext.4465 or ext Upon completion of construction of the system, the customer obtains the electrical release from the corresponding City/County and requests an EPE field inspection by contacting Renewables Development at smallrenewables@epelectric.com. Please refer to Section 6.3 EPE Field Inspection to review the field inspection request checklist. An EPE Meter Test inspector visits the system site and performs the field inspection. If field inspection is not approved, EPE Renewables Development notifies the customer and informs necessary changes to be performed. The customer requests a new field inspection upon integration of changes. 9 P age

12 Step 8: Step 9: EPE Renewables Development informs the customer of field inspection approval and informs EPE internal groups for rate assignment and meter order to be issued. EPE internal groups perform their tasks and the EPE Meter Test inspector installs the new meters. NET and REC meters are installed. Step 10: One executed contract is mailed back to the customer and the other one is filed for EPE s records. 10 P age

13 5. Technical Requirements The one-line diagram must include the following: Site Plan: The Customer must provide details on equipment capacity, type and location. Information must be clearly identified and marked to avoid confusions and delay in the technical review step. All specifications provided in the sample one-line diagram are reviewed and must be satisfied prior to technical review approval. For more information on the specifications, please follow the sample one-line diagram link provided previously in Section 3.1/3.2/3.3 or visit Appendix A. The one-line diagram must comply with the DSO 1875 standard. Please see Section 5.1 Sample One-Line Diagram. Note: Prior standards will not be accepted by EPE. Inverter information: All inverters must comply with UL1741 and must be equipped with protective devices to prevent connection or parallel operation of the generating equipment unless EPE s service voltage and frequency are within standard operating ranges. The delivery service phase must be clearly specified in the one-line diagram and in the Interconnection Application. Inverter s manufacturer and model, specific power and voltage ratings must be identified. A/C Disconnect information: A visible A/C Disconnect must be installed to allow manual interruption of electrical service from the main service panel. It must be accessible to EPE s Meter Test employees, and must be equipped with protective devices to prevent connection to a de-energized circuit. The location of the A/C Disconnect must be between the REC meter and the main service panel according to the one-line diagram requirements. Breaker information: The one-line diagram must depict the breaker rating. The breaker rating specified on the one line must match the breaker size installed at the premise. Wire Size Wire sizing must be provided for the wires used from the disconnect to the REC Meter and from the REC to the main service. Storage System information (if applicable): If installing a storage system, the one-line must also depict the following: The energy storage type: (e.g. battery) If Battery: Battery Chemistry (e.g. Lead Acid, Li-Ion, NiCa) Max Storage Capacity (kw) Energy Capacity (kwh) Energy Storage System Voltage: (V) 11 P age

14 Energy Storage Maximum Discharge Capacity: Rated maximum current at rated voltage (A) Energy Storage Nominal Discharge Capacity: Rated current at rated voltage (A) Specify intended use for mode of operation (Backup power, power quality, other) If installing a separate inverter for the storage system, please provide the following information on the one-line diagram: o Inverter Manufacturer o Inverter Model o Inverter certification o Rated output power (Watts) o Maximum apparent AC output power (VA) o Rated Output Voltage (V) o Inverter Short Circuit Capacity (Amps or per unit), if available o Provide Manufacturer specifications sheet o Provide transfer switch specs 12 P age

15 5.1 Sample One-Line Diagram 13 P age

16 14 P age

17 Examples of existing one-line diagrams/systems: Contractor to attach tag stating Net Metering Site Label for REC Meter Label for Disconnect One-Line Diagram located beside REC Meter 15 P age

18 One-Line Diagram located on REC Meter Address Contractor to attach tag stating Net Metering Site NOTE 1: Main Service Disconnect located inside Main Service Panel Voltage Rating 16 P age

19 17 P age

20 6. Checklists The customer may use these checklists as a tool to verify that the interconnection packet is complete. Note: The checklist does not have to be included in the interconnection packet. Its purpose is for customer reference only. 6.1 New Mexico Checklist Required Forms (New Mexico) Check Two (2) Simplified Interconnection Application Forms (Original Signature Required) One-Line Diagram, Side and Top View Diagrams One (1)- $50 check for Interconnection Application One (1)-NM Renewable Energy Facility Ownership Status form Form 35 Notice of Self Certification W-9 Form Technical Specifications or Technical Data Sheets Authorization Agreement for Direct Deposit Form (optional) 18 P age

21 6.2 Texas Checklist Required Forms (Texas) Check Two (2) Interconnection Applications Forms (Original Signature Required) One-Line Diagram, Side and Top View Diagrams Technical Specifications or Technical Data Sheets W-9 Form One (1)-TX (Optional) Renewable Energy Facility Ownership Status form Renewable Energy Credit Microgenerator Listing Form (Optional) REC Management Agreement Required by PUCT Subst Rule q 2 (Optional) Additional Information: Customer must sign in the customer section on each page of the interconnection applications that requires it. Please note that electronic signatures are now being accepted. If the system facility is different than the mailing address, the customer must include and indicate the mailing address where EPE should mail the executed application. The customer applying for the interconnection must be the EPE s service account owner or must be included in the application. 19 P age

22 The EPE account number must pertain to the location where the system is installed. For the system address, the customer must ensure that all paperwork with the City/County matches the address provided for the interconnection point. The customer must clearly specify the system s source type (e.g. solar, wind, etc.) The customer must include information relating to the power, voltage rating, and number of phases in the application spaces where they are required and in the one-line diagram. It is preferable if the kw capacity output of the system to be installed is provided in terms of AC. All information provided must be consistent in all applications. The customer must provide a valid address where applications status notifications will be received. If the application does not have a designated area for this information to be included, please make a note next to the customer s name/contractor. In order to avoid delays in the interconnection application process, the customer should verify that all the requirements described herein have been satisfied. Usage of the checklist provided as a tool in Section 6 is recommended. 20 P age

23 6.3 EPE Field Inspection The customer may use these checklists as a tool to verify that the system is ready for an EPE field inspection Residential System Checklist Yes Completed Requirements Notes No Utility Revenue Meter must be within 5 feet from the Main Service Disconnect. Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No No No No No No No No No No REC Meter must also be within 5 feet from the Main Service Disconnect. The Qualifying Facility AC energy source must have a visible, lockable disconnect within 5 feet of Main Service Disconnect. The Qualifying Facility AC Energy Source Disconnect must be placed between the Renewable Energy Meter and Utility Meter. A One-Line Electrical Diagram of the facility must be permanently posted on site next to the REC Meter. The One-Line Diagram must be weather proof (i.e. a placard, or inside a PVC pipe that is no less than 1.5 inch in diameter). Placards must be permanently placed on service indicating this is an Interconnection Site, REC Meter, A/C Disconnect. (3 placards) The system that is built must match the One-Line Diagram that is sent in with the Interconnection Application Package. The voltage that is listed on the One-Line Diagram must match the voltage of the system. Any revisions or additions must be pre-approved before implementation. If existing service is upgraded, changed or modified it must be brought up to current EPE standards and current local and state codes. 21 P age

24 6.3.2 Commercial System Checklist Yes Completed Requirements Notes No Utility Revenue Meter must be within 5 feet from the Main Service Disconnect. Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No No No No No No No No No No The Qualifying Facility AC energy source must have a visible, lockable disconnect within 5 feet of Main Service Disconnect. The Qualifying Facility AC Energy Source Disconnect must be placed between the Renewable Energy Meter and Utility Meter. A One-Line Electrical Diagram of the facility must be permanently posted on site next to the REC Meter. The One-Line Diagram must be weather proof (i.e. a placard, or inside a PVC pipe that is no less than 1.5 inches in diameter). Placards must be permanently placed on service indicating this is an Interconnection Site, REC Meter, A/C Disconnect. (3 placards) The system that is built must match the One-Line Diagram that is sent in with the Interconnection Application Package. The voltage that is listed on the One-Line Diagram must match the voltage of the system. Any revisions or additions must be pre-approved before implementation. If existing service is upgraded, change or modified it must be brought up to current EPE standards and current local and state codes. Utility Revenue Meter must be within 5 feet from the Main Service Disconnect. 22 P age

25 7. System Expansion A customer with an existing interconnected renewable energy system that would like to include additional panels and therefore increase the system capacity must follow the system expansion process. Note: When considering expanding an existing system please note that the documentation specified below is only applicable to systems that expand within the limits of small size systems ( 10kW); if the existing system is expanded beyond the 10kW limit, it becomes a medium size system and different guidelines apply (the customer will have to submit a medium size application package to EPE). To increase size of renewable energy system for a total system capacity of less than 10kW, customers must provide the following documentation to EPE prior to the expansion of the system: TWO original Simplified Expansion Applications accurately and completely filled out. The one-line diagram with all the specifications mentioned in this manual and specifying how many panels will be added to the system and the total capacity of the new system. For New Mexico Customers only: a $50 check application processing fee must be attached to the Interconnection Application (Please make check payable to El Paso Electric Co). 7.1 Expansion Application Process Step 1: Step 2: The customer completes the Expansion Interconnection Packet that includes two original Simplified Expansion Applications, the one-line diagram, and a $50 check(nm customers only). The customer mails the Expansion Interconnection Packet to EPE: Step 3: Renewables Development El Paso Electric (loc.131) P.O Box 982 El Paso, Texas Attention: Paul Garcia Renewables Development reviews the applications for completeness and accuracy and submits the one-line diagram for technical review to Engineering and Meter Test Departments. If the one-line diagram is rejected, Renewables Development informs the customer of disapproval and informs needed changes for the one-line diagram. The customer submits a revised one-line diagram for new technical revision. Note: Please review Section 5. Technical Requirements for more information on the oneline diagram. 23 P age

26 Step 4: Step 5: Renewables Development informs the customer of technical review approval. Renewables Development informs internal EPE groups of system expansion. Step 6: Customer completes construction of expansion and notifies Renewables Development. Step 7: Upon completion of system expansion, the customer requests an EPE field inspection by sending an to Step 8: EPE meter test performs field inspection. Step 9: The system goes on-line. Step 10: EPE mails to the customer the executed interconnection contract. Note: In order to avoid delays in the expansion application process, please take the time to verify all the requirements described herein have been satisfied. 8. Renewable Energy System Ownership Change A customer with an existing interconnected renewable energy system that will like to transfer the system ownership must follow the Renewable Energy system ownership change process. To change the ownership of an existing interconnected renewable energy system, the New Mexico customers must provide the following documentation to EPE: One Renewable Energy Credit (REC) Application accurately and completely filled out; and Note: Please write OWNERSHIP CHANGE on top of the Interconnection Application. One $50 check processing fee must be attached to the Renewable Energy System Ownership Change Application (Please make check payable to EPE). One W9 form accurately filled out and signed by the customer is required. Note: Before submitting the ownership change application, the customer must verify the EPE account for the system location is under the customer s name. To change the ownership of an existing interconnected renewable energy system, the Texas customers must send an notification to smallrenewables@epelectric.com for EPE to update its solar system interconnection records and call our customer service center in Texas at to update name on the electric account. 24 P age

27 8.1 Ownership Change Application Process Step1: Step 2: The customer prepares the Ownership Change Interconnection packet that includes one original Renewable Energy Credit Application, W9 form and a $50 check. The customer mails the Ownership Change Interconnection packet to EPE: Renewables Development El Paso Electric P.O Box 982 El Paso, Texas Attention: Paul Garcia (loc.131) Step 3: Step 4: Renewables Development reviews the accuracy and completeness of the forms and forwards it to EPE s internal groups. Renewables Development informs EPE internal groups of ownership change. Note: In order to avoid delays in the ownership change application process, please take the time to verify all the requirements described herein have been satisfied. 25 P age

28 9. Downloading Required Documentation from EPE Website Customers may find all application forms referred to in this manual by visiting EPE s website. The instructions on how to download all the forms are presented below: 1. Go to the EPE website: 2. Click on the Residential Services tab on the top of the page. 3. Select the appropriate State of service: 4. Click on the Renewable Energy blue tab: 5. Click on the Renewable Energy Interconnection orange tab located on the left column. 26 P age

29 6. Select the appropriate link: a. Interconnection of facilities less than 10kW for NM; or, b. Interconnection of facilities less than 20kW for TX. 7. Print and complete the appropriate forms and submit the Interconnection Packet to EPE. 27 P age

30 28 P age

31 10. Appendix A: Sample Forms for New Mexico Sample Simplified Interconnection Application for New Mexico 29 P age

32 Sample Simplified Interconnection Application for New Mexico 30 P age

33 Sample New Mexico Renewable Energy Facility Ownership Status 31 P age

34 Sample W-9 for New Mexico 32 P age

35 Direct Deposit Sample Form for New Mexico 33 P age

36 Sample Forms for Texas Sample Interconnection Agreement for Texas 34 P age

37 Sample Interconnection Agrement for Texas 35 P age

38 Sample Interconnection Agrement for Texas 36 P age

39 Sample Interconnection Agrement for Texas 37 P age

40 Sample Interconnection Agreement for Texas 38 P age

41 Sample Interconnection Agreement for Texas 39 P age

42 Sample Interconnection Agreement for Texas 40 P age

43 Sample Interconnection Agreement for Texas 41 P age

44 Sample Interconnection Agreement for Texas 42 P age

45 Sample Interconnection Agreement for Texas 43 P age

46 Sample Interconnection Application for Texas 44 P age

47 Sample Interconnection Application for Texas 45 P age

48 Sample Texas Renewable Energy Facility Owhership Status 46 P age

49 11. Appendix B: Simplified Interconnections Terms and Conditions Appendix B 47 P age

50 Appendix B 48 P age

51 12. Appendix C : Safety Recommendations Appendix C 49 P age

52 Appendix C 50 P age

53 Appendix C 51 P age

54 Appendix C 52 P age

55 Appendix C 53 P age

56 Appendix C 54 P age

57 13. Appendix D: Type of Service Voltages Appendix D 55 P age

58 Appendix D 56 P age

59 Appendix D 57 P age

60 Appendix D 58 P age

61 14. Appendix E: Technical Requirements for Interconnections and Parallel Operation of Qualifying Facilities 10 kw or Less Appendix E 59 P age

62 Appendix E 60 P age

CenterPoint Energy P O Box 1700 Houston, TX

CenterPoint Energy P O Box 1700 Houston, TX CenterPoint Energy P O Box 1700 Houston, TX 77251-1700 IF YOU ARE APPLYING FOR DISTRIBUTED GENERATION, PLEASE FOLLOW THE INSTRUCTIONS IN THE PARAGRAPHS BELOW. YOU WILL NEED TO COMPLETE AND SIGN AND THEN

More information

Oncor Residential/Small Commercial Project Requirements

Oncor Residential/Small Commercial Project Requirements Oncor Residential/Small Commercial Project Requirements Revised: March 26, 2018 In Effect: May 1, 2018 Equipment (Including all associated equipment) o Batteries o Utility Meter o Generators o Visible

More information

Checklist for Submission to Utility

Checklist for Submission to Utility Simplified Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource (DER) to the Utility s distribution system through the Simplified Process

More information

Green Power Connection Net Energy Metering Online Application Training

Green Power Connection Net Energy Metering Online Application Training Green Power Connection Net Energy Metering Online Application Training Presented by: Marianne Mannschreck and Joshua Cadoret Date: Welcome Historical Net Energy Metering Application Volume Benefits of

More information

Document C0. Use for:

Document C0. Use for: Date: July 27, 2015 Document C0 Use for: Connection of Electric Generation that will operate with an Open Transition (Category 1) between the Ameren System and the Generator or operate with a Synchronized

More information

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &

More information

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY Inverter Based Generators 25 kw and This document contains the interconnection requirements for inverter based generators, 25 kw and smaller, that operate

More information

MA SREC-II Extension Application Instructions

MA SREC-II Extension Application Instructions MA SREC-II Extension Application Instructions Qualification in SREC-II Less than or equal to 25 kw Systems interconnected on or before January 8, 2017 Original SREC-II factors Systems interconnected after

More information

DISTRIBUTED ENERGY RESOURCES NEM PLUS APPLICATION MANUAL

DISTRIBUTED ENERGY RESOURCES NEM PLUS APPLICATION MANUAL DISTRIBUTED ENERGY RESOURCES NEM PLUS APPLICATION MANUAL Reference Guide for the NEM Plus Application This guide is intended to help customers and contractors complete and submit an application for the

More information

Bulletin Installation of solar photovoltaic systems Rules , , , , and

Bulletin Installation of solar photovoltaic systems Rules , , , , and Bulletin 64-5-0 Installation of solar photovoltaic systems Rules 64-060, 64-200, 64-214, 84-020, 84-024 and 84-030 Scope (1) Introduction (2) Disconnecting means (a) Disconnecting means for solar photovoltaic

More information

Operations ISO Version: 1.6. Effective Date: 8/02/2018. Fieldwork Guide. Fieldwork Guide

Operations ISO Version: 1.6. Effective Date: 8/02/2018. Fieldwork Guide. Fieldwork Guide REVISION HISTORY VERSION NO. (Must match header) DATE REVISED BY DESCRIPTION 1.0 6/6/2016 EDAS Created Document 1.1 6/29/2016 EDAS Updates to include all Meter Work and instruction 1.2 8/29/2016 EDAS Included

More information

Solar*Rewards Community MN Application Manual

Solar*Rewards Community MN Application Manual Solar*Rewards Community MN Application Manual Version 2.0 February 2018 Contents 1. Introduction... 4 2. Application Form: Submission and Validation - Submitting Application Form... 5 2.1. Overview...

More information

ILLINOIS DISTRIBUTED GENERATION PROCUREMENT PROGRAM APPLICATION INSTRUCTIONS

ILLINOIS DISTRIBUTED GENERATION PROCUREMENT PROGRAM APPLICATION INSTRUCTIONS ILLINOIS DISTRIBUTED GENERATION PROCUREMENT PROGRAM APPLICATION INSTRUCTIONS AGENDA Company Overview Program Overview SRECTrade Registration and Bidding Process Summary and Q&A This document is protected

More information

WN U-60 Original Sheet No. 152

WN U-60 Original Sheet No. 152 WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H

More information

Bulletin Installation of Solar Photovoltaic Systems Section 50; Rules: , , ; Tables 11 and 19 Issued July 2010

Bulletin Installation of Solar Photovoltaic Systems Section 50; Rules: , , ; Tables 11 and 19 Issued July 2010 Ontario Electrical Safety Code - Bulletins 50-1-0 Bulletin 50-1-0 Installation of Solar Photovoltaic Systems Section 50; Rules: 84-020, 84-024, 84-030; Tables 11 and 19 Issued July 2010 Scope (1) Introduction

More information

LORAIN-MEDINA RURAL ELECTRIC COOPERATIVE, INC. NORTH CENTRAL ELECTRIC COOPERATIVE, INC.

LORAIN-MEDINA RURAL ELECTRIC COOPERATIVE, INC. NORTH CENTRAL ELECTRIC COOPERATIVE, INC. Page 1 LORAIN-MEDINA RURAL ELECTRIC COOPERATIVE, INC. NORTH CENTRAL ELECTRIC COOPERATIVE, INC. RULES AND REGULATIONS FOR DISTRIBUTED RESOURCES (DR) OBJECTIVES To provide for the safety of consumers, Cooperative

More information

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011 Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 2. Initial Technical Review a. The following flowchart provides, for illustrative purposes, the major steps in the Initial Technical Review process:

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

Small Hydro Regulatory and Permitting Requirements California

Small Hydro Regulatory and Permitting Requirements California Small Hydro Regulatory and Permitting Requirements California Lon W. House, Ph.D. 530.409.9702 Water & Energy Small Hydro Regulatory and Compliance FERC QF, Small Hydro License or Exemption EIA Generator

More information

Interconnection Application

Interconnection Application Interconnection Application Member interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

A Regulatory Perspective on Distributed Generation

A Regulatory Perspective on Distributed Generation A Regulatory Perspective on Distributed Generation Southwest Electrical Metering Association Spring Meeting Galveston June 10, 2015 Darryl Nelson Rates and Regulatory Agenda Why Rules are Needed Texas

More information

Oncor Application for Interconnection of Distributed Generation

Oncor Application for Interconnection of Distributed Generation Oncor Application for Interconnection of Distributed Generation Operating Mode: Parallel Operation Longer than 100 milliseconds (07/11/2018) This application is for generator systems that synchronously

More information

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011 Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 INTERCONNECTION APPLICATION FOR ALL BUT UL1741 CERTIFIED INVERTER BASED SYSTEMS LESS THAN 10 KW In addition to the information provided below, a complete

More information

New Jersey s Clean Energy Program SREC Registration Program (SRP) Program Guidebook

New Jersey s Clean Energy Program SREC Registration Program (SRP) Program Guidebook New Jersey s Clean Energy Program SREC Registration Program (SRP) Program Guidebook Prepared by TRC Energy Services November 2018 Table of Contents Acronyms... 4 SRP Program Definitions... 5 Purpose...

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

U.S. Virgin Islands Water and Power Authority

U.S. Virgin Islands Water and Power Authority U.S. Virgin Islands Water and Power Authority REQUIREMENTS AND PROCEDURES FOR INTERCONNECTION OF SOLAR PHOTOVOLTAIC GENERATION TO THE ELECTRICAL DISTRIBUTION SYSTEM Request for Proposals from Independent

More information

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS STATE OF MINNESOTA DISTRIBUTED GENERATION INTERCONNECTION TABLE OF CONTENTS Foreword 2 1. Introduction 3 2. References 6 3. Types of Interconnections 7 4. Interconnection Issues and Technical Requirements

More information

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5 Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System

More information

F-1 OPTIONAL PRACTICAL TRAINING STEM EXTENSION

F-1 OPTIONAL PRACTICAL TRAINING STEM EXTENSION Global Education Office (GEO) 2120 Mesa Vista Hall MSC06 3850 1 University of New Mexico Albuquerque, NM 87131-1056 Phone (505) 277-4032 Fax (505) 277-1867 Email geo@unm.edu Web: www.geo.unm.edu/ F-1 OPTIONAL

More information

Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory

Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Authority: This Interconnection Standard is filed in compliance with the Delaware Public Utility Commission in

More information

BLUE 3 INSTALLATION GUIDE

BLUE 3 INSTALLATION GUIDE BLUE 3 INSTALLATION GUIDE CATCH Power BLUE 3 Installation manual - Page 1 IMPORTANT This product must be installed by a licensed electrician. This product must be installed according to the AS3000 Australian

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Summary. Registration RULE 21 ONLINE PORTAL PILOT PG&E CONTACT DETAILS

Summary. Registration RULE 21 ONLINE PORTAL PILOT PG&E CONTACT DETAILS PG&E Interconnection Portal Contents List Summary... 1 Registration... 1 Account Details... 2 Starting a New Application... 3 Select Program... 3 Enter Generators... 4 Form Builder... 5 Tab Options...

More information

Elmhurst Mutual Power & Light nd Street South Tacoma, WA

Elmhurst Mutual Power & Light nd Street South Tacoma, WA Elmhurst Mutual Power & Light 120 132 nd Street South Tacoma, WA 98444-4808 Interconnection Requirements of Member Owned Renewable Electric Generating Facilities of 100 Kilowatts or Less Table of Contents

More information

City of Azusa Light & Water Department. Interconnection and Net Metering Agreement For Generating Facility 10kW or Less

City of Azusa Light & Water Department. Interconnection and Net Metering Agreement For Generating Facility 10kW or Less City of Azusa Light & Water Department Interconnection and Net Metering Agreement For Generating Facility 10kW or Less This Interconnection and Metering Agreement for Solar or Wind Turbine Electric Facilities

More information

SECTION ( ) LIGHTING CONTROL PANELBOARD

SECTION ( ) LIGHTING CONTROL PANELBOARD (26 24 16.02) LIGHTING CONTROL PANELBOARD PART 1 GENERAL 1.01 SCOPE A. The Contractor shall furnish and install Lighting Control Panelboards as specified and as shown on the contract drawings. B. The Lighting

More information

Feed-in Tariff application form

Feed-in Tariff application form For Office Use Only Date received: from Eligibility date: Start read: Version number: V3 Feed-in Tariff application form Please complete and sign this form and send it to us at: Freepost ECOTRICITY (no

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network Tasmanian Networks Pty Ltd ABN 24 167 357 299 Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network (AS4777 Compliant) NG R PD 09 Version 2.0 July 2014 TABLE

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Electric Sample Form No Agreement for Unmetered Low Wattage Equipment Connected to Customer-Owned Street Light Facilities

Electric Sample Form No Agreement for Unmetered Low Wattage Equipment Connected to Customer-Owned Street Light Facilities Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32135-E Cancelling Revised Cal. P.U.C. Sheet No. 27053-E Electric Sample Form No. 79-1048 Agreement for Unmetered

More information

PUBLIC UTILITY COMMISSION OF OREGON 550 CAPITOL STREET NE, STE. 215 PO BOX 2148 SALEM, OREGON (503) APPLICATION FOR CERTIFICATE OF

PUBLIC UTILITY COMMISSION OF OREGON 550 CAPITOL STREET NE, STE. 215 PO BOX 2148 SALEM, OREGON (503) APPLICATION FOR CERTIFICATE OF PUBLIC UTILITY COMMISSION OF OREGON 550 CAPITOL STREET NE, STE. 215 PO BOX 2148 SALEM, OREGON 97308-2148 (503) 378-8959 APPLICATION FOR CERTIFICATE OF AUTHORITY TO PROVIDE TELECOMMUNICATIONS SERVICE IN

More information

Stalking the Elusive and Somewhat Strange PV System

Stalking the Elusive and Somewhat Strange PV System A series of articles on photovoltaic (PV) power systems and the National Electrical Code by John Wiles PERSPECTIVES ON PV Stalking the Elusive and Somewhat Strange PV System Photo 1. Framed PV modules

More information

PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICE (CCS)) FRAME RELAY ATTACHMENT

PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICE (CCS)) FRAME RELAY ATTACHMENT PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICE (CCS)) FRAME RELAY ATTACHMENT Last Revised 2/1/2017 1. Private Mobile Connection Frame Relay. Pursuant to the terms and conditions of

More information

PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICE (CCS)) FRAME RELAY ATTACHMENT

PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICE (CCS)) FRAME RELAY ATTACHMENT PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICE (CCS)) FRAME RELAY ATTACHMENT 1. Private Mobile Connection Frame Relay. Pursuant to the terms and conditions of the Agreement and this

More information

FEED IN TARIFF APPLICATION FORM

FEED IN TARIFF APPLICATION FORM FEED IN TARIFF APPLICATION FORM You may not be eligible to register with us for the FIT scheme if you are not an SSE electricity customer. Please check your eligibility to join the Feed in Tariff (FIT)

More information

Back-UPS RS APC Back-UPS RS 800VA 120V Black

Back-UPS RS APC Back-UPS RS 800VA 120V Black Back-UPS RS APC Back-UPS RS 800VA 120V Black APC Back-UPS RS, 540 Watts / 800 VA,Input 120V / Output 120V Includes: CD with software, Cord management straps, Free trial of anti-virus : firewall : email

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

HT2000 Transverter Installation & Operation Manual

HT2000 Transverter Installation & Operation Manual HT2000 Transverter Installation & Operation Manual 1 A message from the team at Heart Transverter S.A. Thanks for your recent purchase of the HT2000 Power inverter in combination with the HTREM Remote

More information

More Questions from Inspectors Numerous PV Systems Pose Issues

More Questions from Inspectors Numerous PV Systems Pose Issues Perspectives on PV More Questions from Inspectors Numerous PV Systems Pose Issues by John Wiles 76 IAEI NEWS March. April 2012 www.iaei.org Photovoltaic (PV) systems prices continue to drop and inspectors

More information

Distributed Generation Requirements Update

Distributed Generation Requirements Update Distributed Generation Requirements Update Toronto Hydro has updated its real time monitoring and control requirements for Distributed Generation facilities. The latest version of the Distributed Generation

More information

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System PUBLIC SERVICE OF NEW HAMPSHIRE Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System September 2013 1.0 Purpose of this document Public Service of New Hampshire

More information

Feed-in Tariff Application Form

Feed-in Tariff Application Form Feed-in Tariff Application Form Once you ve completed all the details print off this form, sign it and return to us at Green Energy (UK) plc, Black Swan House, 23 Baldock Street, Ware, SG12 9DH. Scanned

More information

Online Permitting Directions

Online Permitting Directions 1 Online Permitting Directions Please be sure to read the Electronic Plan Submittal Instructions before beginning your online submittal. A paper permit application is NOT required for upload, a permit

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

Application For APTD and CPLP Recertification Points Preapproval Status

Application For APTD and CPLP Recertification Points Preapproval Status Application For APTD and CPLP Recertification Points Preapproval Status APPLICATION FOR APTD AND CPLP RECERTIFICATION POINTS PREAPPROVAL STATUS Applications for each program seeking preapproval should

More information

Customer Interconnection Tool (CIT)

Customer Interconnection Tool (CIT) Customer Interconnection Tool (CIT) Contractor Training September 2017 Slide 1 Agenda Welcome (Team Introductions) Overview of the Customer Interconnection Tool (CIT) Navigation Live Demo Contractor Account

More information

Installation and Operations Manual INVOLAR MAC250 Microinverter

Installation and Operations Manual INVOLAR MAC250 Microinverter Installation and Operations Manual INVOLAR MAC250 Microinverter Contact Information INVOLAR Corporation, Ltd. 887 Zuchongzhi Road, Build 84, Room 408, Shanghai, China 201203 Tel: 86-21-50272208 Fax: 86-21-50277705

More information

Application and Instructions for Firms

Application and Instructions for Firms United States Environmental Protection Agency Office of Prevention Pesticides, and Toxic Substances EPA 747-B-99-001 March 2010 https://www.epa.gov/lead Application and Instructions for Firms Applying

More information

SECTION ELECTRIC METERING

SECTION ELECTRIC METERING SECTION 26 27 13 ELECTRIC METERING SPEC WRITER NOTES: Use this section only for NCA projects Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable

More information

Legal Name of the Customer (or, if an individual, individual's name):

Legal Name of the Customer (or, if an individual, individual's name): Instructions An Interconnection Customer who requests a Utah Public Service Commission jurisdictional interconnection must submit this Interconnection Request by hand delivery, mail, or delivery service

More information

Powerware Plus 18. Operator's Manual

Powerware Plus 18. Operator's Manual Powerware Plus 18 Operator's Manual 1 Introduction Powerware Plus 18 Special Features Powerware Plus 18 Two year Best Power limited System Overview Powerware Plus 18 LTM-1336B System Requirements 3 COMPUTERS

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Go SOLAR Online Permitting System A Guide for Applicants November 2012

Go SOLAR Online Permitting System A Guide for Applicants November 2012 Go SOLAR Online Permitting System A Guide for Applicants November 2012 www.broward.org/gogreen/gosolar Disclaimer This guide was prepared as an account of work sponsored by the United States Department

More information

B60 Domestic Voltage Optimisation Unit

B60 Domestic Voltage Optimisation Unit B60 Domestic Voltage Optimisation Unit Installation Manual V1.2 Nov 2013 1 P a g e PRODUCT ADVISORY NOTICE This product must be installed by a competent person in accordance with the IEE Wiring Regulations,

More information

Building Tune-Up Program Application

Building Tune-Up Program Application Thank you for applying for Vectren s Building Tune-Up Program ( Program )! The Program provides a study focused on optimizing the energy performance of a facility by identifying no-and low-cost energy-saving

More information

Registrar Accreditation Application Form

Registrar Accreditation Application Form Registrar Accreditation Application Form BE OUR REGISTRAR TWNIC welcomes all interested parties to be our accredited registrar. To be a TWNIC accredited registrar, you must meet the requirements listed

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

STEEL FABRICATOR REGISTRATION PROGRAM

STEEL FABRICATOR REGISTRATION PROGRAM STEEL FABRICATOR REGISTRATION PROGRAM The Washington Association of Building Officials (WABO) maintains a roster of registered fabricators engaged in the manufacture of Structural Steel systems and assemblies.

More information

PowerClerk Online Application External User Guide For Expedited Installers

PowerClerk Online Application External User Guide For Expedited Installers Commonwealth Solar II Rebate Program PowerClerk Online Application External User Guide For Expedited Installers Please note that Expedited Installers are required to upload back-up documentation electronically

More information

Technical data sheet. PowerLogic power-monitoring units EM3500 series DIN Rail meter

Technical data sheet. PowerLogic power-monitoring units EM3500 series DIN Rail meter Technical data sheet PowerLogic power-monitoring units series DIN Rail meter The Series DIN Rail Meter combines exceptional performance and easy installation to deliver a cost-effective solution for power

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016

SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016 SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016 BY H S W Karunaratne Assistant Director - Engineering Sri Lanka Standards Institution. 1 DEFINITIONS Ac module:

More information

ECM-1240 Energy Consumption Monitor

ECM-1240 Energy Consumption Monitor ECM-1240 Energy Consumption Monitor The ECM-1240 packages are available with or without wireless communication option. NET Metering Capable for Measuring: Energy Consumed Energy Generated NET Energy (purchased

More information

Candidate Manual Certified Commissioning Firm (CCF) Program

Candidate Manual Certified Commissioning Firm (CCF) Program Candidate Manual Certified Commissioning Firm (CCF) Program Building Commissioning Certification Board 1600 NW Compton Drive, Suite 200 Beaverton, OR 97006 Phone: 1-877-666-BCXA (2292) E-mail: certification@bcxa.org

More information

Mount Pleasant Waterworks. Cross-Connection Control Program Guidelines October 2010

Mount Pleasant Waterworks. Cross-Connection Control Program Guidelines October 2010 Mount Pleasant Waterworks Cross-Connection Control Program Guidelines October 2010 1 PREFACE The purpose of this policy is to protect the public water supply from the possibility of contamination. The

More information

LINCOLN AUTHORIZED SERVICE FACILITY (LASF) SERVICE CODE TERMS & CONDITIONS

LINCOLN AUTHORIZED SERVICE FACILITY (LASF) SERVICE CODE TERMS & CONDITIONS The Lincoln Electric Company 22801 St. Clair Avenue Cleveland, Ohio 44117-1199 LASF Contract Attachment Last revision: February, 2016 LINCOLN AUTHORIZED SERVICE FACILITY (LASF) SERVICE POLICY: CODE TERMS

More information

Online Permitting Manual

Online Permitting Manual Online Permitting Manual CONTRACTOR REGISTRATION AND PERMIT APPLICATION PROCESS UPDAT ED 05/17/2018 1 TABLE OF CONTENTS PAGE Steps to Begin Register to use Online Services Online Permitting Types Available

More information

HOW TO OBTAIN A NEW MEXICO JOURNEYMAN CERTIFICATE

HOW TO OBTAIN A NEW MEXICO JOURNEYMAN CERTIFICATE HOW TO OBTAIN A NEW MEXICO JOURNEYMAN CERTIFICATE In New Mexico, electrical, mechanical and plumbing work must be performed by, or under the supervision of, someone who has a journeyman certificate for

More information

RESIDENTIAL FIXED WIRELESS BROADBAND. Service Description

RESIDENTIAL FIXED WIRELESS BROADBAND. Service Description RESIDENTIAL FIXED WIRELESS BROADBAND Service Description Residential Fixed Wireless Broadband Service Description Terms and interpretation used in this Wireless Service Description are further defined

More information

Authorized ICPM Instructional Partner FACT SHEET

Authorized ICPM Instructional Partner FACT SHEET Authorized ICPM Instructional Partner FACT SHEET ICPM is the largest management certifying body in the United States Thank you for your interest in becoming an ICPM Authorized Instructional Partner to

More information

STARHUB'S SERVICE SPECIFIC TERMS & CONDITIONS ONLINE STORE

STARHUB'S SERVICE SPECIFIC TERMS & CONDITIONS ONLINE STORE STARHUB'S SERVICE SPECIFIC TERMS & CONDITIONS ONLINE STORE STARHUB'S SERVICE SPECIFIC TERMS & CONDITIONS ONLINE STORE These are StarHub's Service Specific Terms & Conditions for customers who access the

More information

Oncor Installer Portal Training Guide

Oncor Installer Portal Training Guide Oncor Installer Portal Training Guide 1 Index 1 Introduction to Portal 2 3 Project Workflow 4 5 Introduction to Tabs in Portals 6 All Web Pages Navigation, Buttons, Features & Functionalities New Installer

More information

NOTICE OF EXAMINATION. Examination for Certificate of Fitness for Construction Site Fire Safety Manager (CSFSM) (S-56)

NOTICE OF EXAMINATION. Examination for Certificate of Fitness for Construction Site Fire Safety Manager (CSFSM) (S-56) NOTICE OF EXAMINATION Title: Examination for Certificate of Fitness for Construction Site Fire Safety Manager (CSFSM) (S-56) Date of Exam: Written tests are administered Monday through Friday (except legal

More information

Billion SG3015. Compact ZigBee Power Meter Series. Fully complied with IEEE

Billion SG3015. Compact ZigBee Power Meter Series.     Fully complied with IEEE T1 T2 T3 Single phase- 2 wire Billion SG3015 T4 Compact ZigBee Power Meter Series The Billion SG3015 series is a cost-effective energy monitoring and management solution deployed in Home Area Networks,

More information

1.4. Electronic Products. Contents Description E33 esm Keypad Multiplexed Switch Module Product Selection...

1.4. Electronic Products. Contents Description E33 esm Keypad Multiplexed Switch Module Product Selection... .4 Electronic Products Product Description Sealed Multiplexed Master Module using a LIN sub bus to communicate with up to seven expansion modules. Eaton is pleased to introduce the newest line of multiplexed

More information

FileMaker Business Alliance. Program Guide

FileMaker Business Alliance. Program Guide FileMaker Business Alliance Program Guide FileMaker Business Alliance Program Guide Get Started... 3 FBA Business Types and Requirements... 4 Partner Levels... 7 FBA Six Pillars of Excellence... 10 Contact

More information

SENSIBLE Project Technical innovations

SENSIBLE Project Technical innovations Energising Communities: Nottingham s Energy Revolution SENSIBLE Project Technical innovations Filipe Guerra EDP Labelec October 18th, 2018 SENSIBLE Overview and highlights Scope Demonstration of energy

More information

Green Power Connection TM. Solar Stakeholder Collaborative for Maryland

Green Power Connection TM. Solar Stakeholder Collaborative for Maryland Green Power Connection TM Solar Stakeholder Collaborative for Maryland September 6, 2016 1 Welcome Dave Velazquez President and CEO, Pepco Holdings 2 Welcome Donna Cooper President for the Pepco Region

More information

2018 PO BOX 604, BANNING, CA STAGECOACHDAYS.ORG SEPTEMBER 6-9 VENDOR APPLICATION

2018 PO BOX 604, BANNING, CA STAGECOACHDAYS.ORG SEPTEMBER 6-9 VENDOR APPLICATION Vendor Name: Contact Person: Address: City: 2018 PO BOX 604, BANNING, CA 92220 STAGECOACHDAYS.ORG SEPTEMBER 6-9 VENDOR APPLICATION State: Zip Code: Phone: ( ) - Cell: ( ) - CDL#: Email: VENDOR TYPE: Check

More information

DRIVER EDUCATION SCHOOL FEE SHEET

DRIVER EDUCATION SCHOOL FEE SHEET P.O. Box 12157 - Austin, Texas 78711-2157 800-803-9202 - (512) 463-6599 - FAX (512) 463-1512 www.tdlr.texas.gov des@tdlr.texas.gov DRIVER EDUCATION SCHOOL FEE SHEET ALL FEES ARE NONREFUNDABLE (C ) School

More information

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES 1. Introduction Real time monitoring and control is necessary to ensure public and employee safety and to protect the integrity

More information

PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICES (CCS)) PERMANENT VIRTUAL CIRCUIT ATTACHMENT

PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICES (CCS)) PERMANENT VIRTUAL CIRCUIT ATTACHMENT PRIVATE MOBILE CONNECTION (formerly COMMERCIAL CONNECTIVITY SERVICES (CCS)) PERMANENT VIRTUAL CIRCUIT ATTACHMENT Last Revised 12/20/17 1. Private Mobile Connection Permanent Virtual Circuit. Pursuant to

More information

Certified Trainer Program Guide

Certified Trainer Program Guide Certified Trainer Program Guide You can maximize your training opportunities by becoming a Sage certified trainer (CT). This unique program is designed for employees of Sage Software business partners

More information

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4

More information