Updates and Modifications to Report

Size: px
Start display at page:

Download "Updates and Modifications to Report"

Transcription

1 QUARTERLY COMPLIANCE REPORT (APRIL 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision ( D. ) , SCE hereby provides this quarterly report on the status of transmission and generation interconnection projects. Relevant information on the construction status, approval status and the purpose of the project (in the form requested by Energy Division) is provided in the attached tables. Modifications from the previous report are highlighted in gray. Cancelled projects are highlighted in green and new projects are highlighted in yellow. Project cost information has already been provided to the Energy Division under Public Utilities Code Section 583 and is therefore not included in the table. Updates and Modifications to Report SCE has made the following updates and modifications from the January 2017 Quarterly Report: OVERALL CHANGES New projects submitted into the 2 nd Quarter 2017 filing: No new projects submitted this quarter. Projects removed from 2 nd Quarter 2017 filing (projects are removed from the AB970 Report four quarters after they are operational, incorporated into another project, or cancelled): Project No. 88 Jasper 220kV Substation PROJECT UPDATES Project No. 24 Path 42 Upgrade Project Status: SCE scope of work is complete Project No. 51 Wildlife (formally Jurupa) 230kV Sub Transmission Miles: 10 Planned In-Service Date: 7/1/2023 Cost Range ($M): 350M-400M

2 Project No. 53 West of Devers (WOD) Upgrade Project Project Description: This project also includes partial upgrade to San Bernardino - Etiwanda and San Bernardino - Vista 220kV lines. Project No. 58 Tehachapi Renewable Transmission Project Project No. 59 North of Magunden Redundant BCT Upgrade Project No. 64 Lugo Sub Install new 500kV CBs for AA Banks Cost Range ($M): 1.1M-10M Project No. 82 Mesa 500 kv Substation Approval Status o CPUC: PTC Approved February 2017 Project Status: Pre-Construction Project No. 105 New SCE-Owned Eldorado 220 kv Switchyard and 500/220 kv AA Transformer Bank PIN No.: 7248/7241 Project No. 112 Victor-Aqueduct 115kV Line Project Status: Cancelled Project No. 113 Victor Loop-in Project Project No. 114 Eldorado-Lugo-Mohave Upgrade Planned In-Service Date: 6/1/2020 Project No. 115 Lugo-Mohave Series Capacitor Upgrade Planned In-Service Date: Transferred as part of work associated with PIN Project No. 117 Lugo -Victorville RAS Project No. 118 Whirlwind 3 rd AA Bank and SPS Project No. 119 Santiago Synchronous Condenser 2

3 Planned In-Service Date: 12/31/2017 Project No. 120 Eldorado-Mohave & Eldorado-Moenkopi 500 kv Line Position Swap Location: Clark County, Nevada Approval Status: o CPUC: This work takes place in Nevada. PUCN ruled the project exempt. Project No. 122 Kramer High Voltage Mitigation Tertiary and Bus Shunt Reactors Project No. 123 Eagle Mountain Reactor Project Project No. 124 Calcite 220kV Substation PIN No.: 7885/6092 Generation Interconnection Projects Updated Item to reflect that all SCE facilities are now complete, including TRTP, and the initial 189 MW phase of generation is operational (no incremental SCE facilities required to accommodate the remaining generation). Accordingly, this project will be removed from the report during the Third Quarter update. Updated Item Planned In Service Date to reflect that TRTP is complete; the 3rd AA Bank at Whirlwind is expected to be in service in May 2017; and the Northern Area SPS in service date is TBD and continues to be under review. Removed Items and as these projects are now operational and all SCE upgrades are complete as indicated in the First Quarter 2017 update. Updated Item to reflect that the Project Capacity has been downsized to 140 MW and that all SCE facilities are now complete, including TRTP. Accordingly, this project will be removed from the report during the Third Quarter update. Updated Item Project Name and Planned In Service Date to reflect that all SCE facilities are now complete, including TRTP, and the initial 394 MW phase of generation is operational (no incremental SCE facilities required to accommodate the remaining generation). Accordingly, this project will be removed from the report during the Third Quarter update. Updated Items 18.31, 18.32, and to reflect that TRTP is complete; the 3rd AA Bank at Whirlwind is expected to be in service in May 2017; and the Northern Area SPS in service date is TBD and continues to be under review. 3

4 Removed Item as this projects is now operational and all upgrades are complete as indicated in the 1st Quarter 2017 update. Updated Item to reflect that TRTP is complete; the 3rd AA Bank at Whirlwind is expected to be in service in May 2017; and the Northern Area SPS in service date is TBD and continues to be under review. Removed Item as this project is now operational and all upgrades are complete as indicated in the 1st Quarter 2017 update. Removed Item as the LGIA for this project has been terminated as indicated in the 1st Quarter 2017 update. Added new Item for the Golden Oasis Project. Respectfully submitted, GARY CHEN /s/ Gary Chen By: Gary Chen Attorney for SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California Telephone: (626) April 3,

5 CERTIFICATE OF SERVICE I hereby certify that, pursuant to the Commission s Rules of Practice and Procedure, I have this day served a true copy of QUARTERLY COMPLIANCE REPORT (April 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION AND GENERATION INTERCONNECTION PROJECTS on all parties identified on the attached service list(s). Service was effected by one or more means indicated below: Transmitting the copies via to all parties who have provided an address. First class mail will be used if electronic service cannot be effectuated. Executed this 3rd day of April, 2017, at Rosemead, California. /s/ Norman L. Goss Norman L. Goss Legal Administrative Assistant SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Eldorado-Lugo-Mohave

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E For a Permit to Construct Electrical Facilities With Voltages

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (APRIL 2011) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS Pursuant to Commission Decision ( D. ) 06-09-003, SCE hereby provides

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Leatherneck

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for Authority to Lease Available Land at Walnut Substation

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Cerritos

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ERRATA TO SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) REPLY TO PROTESTS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ERRATA TO SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) REPLY TO PROTESTS BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Certificate of Public Convenience and Necessity

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER07-1034-002 REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities

More information

February 25, Subject: Southern California Edison 2015 Annual Progress Report

February 25, Subject: Southern California Edison 2015 Annual Progress Report February 25, 2015 Mr. Tracy Rolstad, Chair WECC Technical Studies Subcommittee Avista Corp. 1411 East Mission Avenue Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff Salt Lake City, UT 84103-1114

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY'S (U 338-E) NOTICE OF COMMUNICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY'S (U 338-E) NOTICE OF COMMUNICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into the November 2018 Submission of Southern California Edison Risk Assessment and Mitigation Phase. I.18-11-006

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PREHEARING CONFERENCE STATEMENT OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PREHEARING CONFERENCE STATEMENT OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into the November 2018 Submission of Southern California Edison Risk Assessment and Mitigation Phase I.18-11-006

More information

2012 General Rate Case

2012 General Rate Case Application No.: Exhibit No.: SCE-0, Vol. 0 Part 0 & 0, Ch. I-II Witnesses: P. Arons K. Varnell (U -E) 01 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Part - Transmission

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: M. Flores B. Tolentino A (U -E) 01 General Rate Case ERRATA Transmission & Distribution (T&D) Volume 0 Substation Construction & Maintenance

More information

Decision on the 2012/2013 ISO Transmission Plan

Decision on the 2012/2013 ISO Transmission Plan Decision on the 2012/2013 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 20-21, 2013 Approving the plan means approving

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In The Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for Authority to Lease Certain Fiber Optic Cables to CELLCO

More information

December 10, 2012 Advice Letter 2797-E

December 10, 2012 Advice Letter 2797-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 10, 2012 Advice Letter 2797-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA NOTICE OF EX PARTE COMMUNICATION OF SOUTHERN CALIFORNIA EDISON COMPANY (U338-E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA NOTICE OF EX PARTE COMMUNICATION OF SOUTHERN CALIFORNIA EDISON COMPANY (U338-E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E) for Approval of Green Energy Programs. Application No. 18-09-015 NOTICE OF

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Full Network Model Scope for FNM DB2017Q4

Full Network Model Scope for FNM DB2017Q4 Transmission Projects PG&E SCE 1. Cooley Landing BK2, 115/60 kv Transformer Replacement (Formerly Resource ID P.07237), phase # 1 2. Cortina #3 60kV Line Reconductoring, phase # 1 3. Dyer Summit Wind Repower

More information

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006 Business Update Al Fohrer Chief Executive Officer Southern California Edison Company Merrill Lynch Power & Gas Conference September 2006 Forward-Looking Statement This presentation contains forward-looking

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

November 14, 2008 Advice Letter 2265-E

November 14, 2008 Advice Letter 2265-E STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 November 14, 2008 Advice Letter 2265-E Akbar Jazayeri Vice President, Regulatory Operations

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: A.1--00 SCE-0, Vol. 0 R. Woods E. Takayesu (U -E) 01 General Rate Case ERRATA Transmission and Distribution (T&D) Volume System Planning Capital Projects Before

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Promote Policy and Program Coordination and Integration in Electric Utility Resource Planning. Order Instituting

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (NOT CONSOLIDATED) And Related Matters. Application Application

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (NOT CONSOLIDATED) And Related Matters. Application Application BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for Development of Distribution Resources Plans Pursuant to Public

More information

December 5, 2012 Advice Letter 2441-E

December 5, 2012 Advice Letter 2441-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 5, 2012 Advice Letter 2441-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

SOUTHERN CALIFORNIA EDISON COMPANY

SOUTHERN CALIFORNIA EDISON COMPANY SOUTHERN CALIFORNIA EDISON COMPANY COMPLIANCE PROCEDURES IMPLEMENTING FERC ORDER 717C STANDARDS OF CONDUCT Version 1.2 Updated June 14, 2017 Purpose: To provide Southern California Edison s (SCE) overall

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

December 9, 2011 Advice Letter 2613-E

December 9, 2011 Advice Letter 2613-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 9, 2011 Advice Letter 2613-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Hetch Hetchy Water and Power of the City and County of San Francisco Joint Transmission Planning Base Case Preparation Process This is a living document. Please

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

March 1, 2013 Advice Letter 2840-E

March 1, 2013 Advice Letter 2840-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor March 1, 2013 Advice Letter 2840-E Akbar Jazayeri Vice President, Regulatory Operations P O Box

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011 Western DSW Planning Stakeholder Meeting (Western OATT Attachment P) June 9, 2011 Agenda: 1. Welcome and Introductions of Attendees 2. Planning Process 3. Interconnection Requests 4. Comments/questions

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

Warrenton Wheeler Gainesville 230kV Reliability Project

Warrenton Wheeler Gainesville 230kV Reliability Project Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Opening 2013/2014 Transmission Planning Process Stakeholder Meeting Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Yesterday s Agenda November 20 th Topic Opening Introduction

More information

Joint Transmission Planning Base Case Preparation Process

Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Southern California Edison Joint Transmission Planning Base Case Preparation Process NERC Reliability Standard MOD-032-1 Version 1.2 August 31, 2017 INTENTIONALLY

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop a Successor to Existing Net Energy Metering Tariffs Pursuant to Public Utilities Code Section 2827.1,

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

National Load Despatch Centre Power System Operation Corporation

National Load Despatch Centre Power System Operation Corporation Module on Procedure for Data Collection National Load Despatch Centre Power System Operation Corporation Background Algorithms/ Processes AC Load flow and transmission losses Slack bus determination- Average

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.-0- Exhibit No.: SCE-0, Vol. Witnesses: T. Reeves (U -E) 0 General Rate Case Transmission & Distribution (T&D) Volume - Other Costs, Other Operating Revenues Before the Public Utilities

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update January 7, 2019 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

SRP Ten Year Transmission Plan

SRP Ten Year Transmission Plan 2018 SRP Ten Year Transmission Plan 2018-2027 Prepared for the Arizona Corporation Commission January 2018 Docket No. E-00000D-17-0001 Page1 Page1 Table of Contents 1. Introduction... 1 2. Planning Organizations...

More information

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way California Independent System Operator October 30, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Wendy al-mukdad, PE Utilities Engineer Grid Planning & Reliability Section, Energy Division California Public Utilities

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E) for Approval of Its 2018-2020 Triennial Investment Plan for the Electric Program

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Evaluate Telecommunications Corporations Service Quality Performance and Consider Modification to Service

More information

THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS?

THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? Whitepaper authored by: Herbert Falk Senior Solutions Architect SISCO, Inc. herb@sisconet.com One of the major

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Proceeding to Consider Amendments to the Revised Right-Of-Way Rules Adopted by Decision 16-01-046. Rulemaking

More information

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D (.laps Lisa Malagon Leader Federal and State Compliance Mail Station 9704 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250- 5671 Elisa.Malagon@aps.com January 31, 2014 Docket Control Arizona Corporation

More information

CERTIFICATE OF COMPLIANCE

CERTIFICATE OF COMPLIANCE Issued to: SMA Solar Technology AG Sonnenallee 1 34266 Niestetal GERMANY This is to certify that representative samples of STATIC INVERTERS, CONVERTERS AND ACCESSORIES FOR USE IN INDEPENDENT POWER SYSTEMS

More information

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project ) Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Dominion Supplemental Projects

Dominion Supplemental Projects Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: SCE-1 J. P. Shotwell (U -E) 01 General Rate Case Testimony Regarding Accessibility Issues Developed Jointly By SCE and Center for Accessible Technology Before the

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 July 30, 2010 Re: Q2 Quarterly

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Transmission Register PTO Admin User Manual. Version 1.0

Transmission Register PTO Admin User Manual. Version 1.0 Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6

More information

The ESP Handbook. Chapter 2 Enrolling in Direct Access An Overview. Version 5.0 December 1, 2011

The ESP Handbook. Chapter 2 Enrolling in Direct Access An Overview. Version 5.0 December 1, 2011 The ESP Handbook Chapter 2 Enrolling in Direct Access An Overview Version 5.0 December 1, 2011 Chapter 2: Enrolling in Direct Access An Overview Providing Direct Access Services in the SCE Service Territory:

More information

SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES

SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES Per the SAAS Accreditation Agreement and SAAS Procedure 200, all accredited CBs are required to report a written list of all certifications granted every three

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

2009 General Rate Case

2009 General Rate Case Application No.: Exhibit No.: SCE-0, Vol., Pt. Ch. I-IV Witness: A. Salinas (U -E) 00 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Capital Expenditures Part, Chapter I IV

More information

CenterPoint Energy P O Box 1700 Houston, TX

CenterPoint Energy P O Box 1700 Houston, TX CenterPoint Energy P O Box 1700 Houston, TX 77251-1700 IF YOU ARE APPLYING FOR DISTRIBUTED GENERATION, PLEASE FOLLOW THE INSTRUCTIONS IN THE PARAGRAPHS BELOW. YOU WILL NEED TO COMPLETE AND SIGN AND THEN

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) NOTICE OF EX PARTE COMMUNICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) NOTICE OF EX PARTE COMMUNICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application Of Southern California Edison Company (U 338-E) For Authority To Increase Its Authorized Revenues For Electric Service In 2018,

More information

The NYISO shall assign a Queue Position based upon the date and time of receipt of the

The NYISO shall assign a Queue Position based upon the date and time of receipt of the 30.4 Queue Position 30.4.1 General The NYISO shall assign a Queue Position based upon the date and time of receipt of the valid Interconnection Request; provided that, if the sole reason an Interconnection

More information

STATE OF CALIFORNIA ) ) ) ) ) ) ) SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) PETITION FOR MODIFICATION OF DECISION NO.

STATE OF CALIFORNIA ) ) ) ) ) ) ) SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) PETITION FOR MODIFICATION OF DECISION NO. BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Certificate of Public Convenience and Necessity

More information

Outage Management System Pilot Roll-out: Division User Manual

Outage Management System Pilot Roll-out: Division User Manual Outage Management System Pilot Roll-out: Division User Manual February 2017 Table of Contents 1. Outage Management System... 2 1.1. Overall Objective... 2 1.2. Outage Categories... 2 1.3. Division User

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information

Final Benchmarking Policy and Procedures

Final Benchmarking Policy and Procedures Final Benchmarking Policy and Procedures Strategic Plan Task 3.1.1 Deliverable 2.2.3 Funded by Southern California Edison Company Local Government Strategic Plan Strategies Program 2013 2015 Program Period

More information