Data Center Facility Analysis Project. Final Presentation Wednesday, July 22, :30 3:30 PM

Size: px
Start display at page:

Download "Data Center Facility Analysis Project. Final Presentation Wednesday, July 22, :30 3:30 PM"

Transcription

1 Data Center Facility Analysis Project Final Presentation Wednesday, July 22, :30 3:30 PM 1 Commonwealth Technology Center Conference Rooms 1 & 2

2 Enterprise Server Farm (ESF) Facility Data: 1 Technology Park, Harrisburg Built in 1991 Data Center = 12,369 sf Current Server Count = 862 servers Current Uptime Institute Rating: Tier II (redundant capacity components) Growth Capacity: At current build: +131 servers At full build out: +612 servers 2

3 ESF General Observations General Notes and Areas for Improvement: Facility is presently operating above the recommended operating limit of the UPS system Power infrastructure expansion project does not provide for comparable increase of HVAC capacity Power infrastructure expansion project does not provide for additional secondary power distribution capacity (PDU) Facility is Tier II Resilient (All HVAC is powered from a single ATS) Resilient HVAC capacity is less than resilient capacity of power expansion project Several HVAC elements are beyond their expected service life and should be evaluated for replacement Facility Recommendations: A primary hosting site for mission critical and other Commonwealth applications Current and future growth capacity suited for consolidation of systems from other sites 3

4 ESF Capacity Summary Enterprise Server Farm Data Center Operation at UPS limit with Power Expansion 2N Utility 2N 81% 89% 131% N+1 Space (RUs) 150% 0% 82% 79% 80% 80% 2N 134% N+1 UPS 2N 123% Notes: 1. Space limit presumes sw ing space reserved for 5 year refresh cycle + 5% contingency 2. Space consumption presumes historical policy deployment w ithout compaction or virtualization. % Consumed Operating Limit % of Rating System Enterprise Server Farm Resiliency Resilient Capacity Current Consumption UPS 1 N 450kW 406kW UPS 1 PDUs 2N 650kVA 392kVA UPS 2 N 117kW 70kW UPS 2 PDUs 2N 300kVA 71kVA CRAC N+1 170T 138T Air-cooled Condensers N+1 192T 152T Utility Transformer N 1500kVA 1233kVA Generator N 1000kW 838kW Temporary Generator N 500kW 79.kW Limiting Infrastructure Resiliency Resilient Capacity Assumed Operating Limit (%) Enterprise Server Farm Assumed Operating Limit Current Consumption Growth Potential (expressed as kw of IT Compute load) Growth Potential (expressed as % of current consumption) CRAC N T 90% 153 T 138 T 53 11% Condensers N T 90% T 152 T 66 14% Expansion PDU config 2N 800 kva 80% 640 kva 463 kva % Expansion UPS 2N 900 kw 80% 720 kw 476 kw % Approximate Growth - Number of Discrete Servers (+ supporting storage & network) 131 Comments Presumes power expansion project complete 4

5 ESF Tier III Conformance Electrical HVAC Site Subsystem Utility Service Lightning Protection & TVSS Primary Power Disrtibution UPS Systems UPS Batteries Engine Generators Load Bank Secondary (Critical) Power Distribution Grounding Description Comments & Related Subsystems Remediation Dual Utility Feed Data center building equipped with passive lightning protection Multi-tier TVSS deployed UPS powered at 2N; All HVAC powered from single ATS 2N UPS 2N Batteries sized to support rated load for 15 minutes 2N Generators but "Tie" can not be maintained in service No load bank 2N to IT load with some static switch PDUs deployed Counterpoise, pedistal grounding & perimeter ground in power room; no counterpoise around expansion generator housings CRAC N+1 at current load; Less than N at resilient Raised Floor Equipment rating of UPS Cooling Conveyance Not Applicable- Units contain compressors Present UPS room cooling is non-redundant; Power Equipment UPS Room Cooling Expansion electrical room e/w ~ N CRAC capacity Conveyance Not Applicable- Units contain compressors Eqpt- Data Cnter Condenser capacity < N for power expansion Dist'n. & Condensers paired 1:1 with CRAC units- design concept is Conv- Data concurrently maintainable but capacity is non-resilient Heat Rejection Eqpt- Pwr Power Expansion e/w < N condenser capacity Exp Bldg Dist'n. & Condensers paired 1:1 with CRAC units- design concept is Conv- Pwr concurrently maintainable but capacity is non-resilient Curret Uptime Tier Classification Notes: 1 Evaluation presumes power expansion project completion 2 Tier 3 considers generators to be the primary electrical source Tier II Concurrent Maintainability Scorecard Enterprise Server Farm Feeds are aerial to site & non-diverse on-site UL listing status unknown Main-Tie-Main configuration does not permit out-of-service maintenance of "Tie"; Utility & generator share bus Main-Tie-Main configuration does not permit out-of-service See Primary distribution remediation maintenance of "Tie" as utility & generator share bus Single starting batteries on existing generator Repaired equipment is testable only into production load Requires rigorous circuit management to ensure single corded IT kit is connected to static switched PDU; risk level elevated due to use of bulk STS Presently no EPO- to be implemented as p/o power expansiondetails unknown 1. Convert Main-Tie-Main configuration to Main-Tie-Tie-Main 2. On a phased basis, replace vintage CRAC units with units equipped with manually selectable, dual source capability 3. Furnish & install new 1200A HVAC distribution board 4. Furnish & install ten (10) manual transfer switches (MTS) 5. Disconnect circuits to all server room condenser units 6. Disconnect circuits to one (1) 30T condenser unit, one (1) UPS condenser unit, and two (2) 30T UPS CRAC units 7. Add circuits between one (1) 30T condenser unit, one (1) UPS condenser unit, and two (2) 30T server room condensers and the new HVAC distribution board 8. Add circuits between dual source CRAC units to New HVAC distribution board 9. Connect nine (9) MTS to both HVAC distribution boards 10. Connect one (1) MTS to both HVAC distribution boards and the 30T enterprise server room CRAC 11. Connect nine (9) MTS to condenser units Required to provide resiliency to support growth only; furnish & install 1, 10T CRAC in Enterprise Systems room and 2, 20T CRAC units in main server room Additionally, non-redundant exhaust fans to be deployed in wet Required to provide resiliency to support growth only; furnish & install 1, 30T CRAC in new cell battery rooms electrical room All HVAC powered from single ATS, et al Required to provide resiliency to support growth only; furnish & install 1, 10T Condenser unit and 2, 20T Condenser units Required to provide resiliency to support growth only; part of CRAC/Condenser installation Required to provide resiliency to support growth only; furnish & install 1, 30T Condenser unit Required to provide resiliency to support growth only; part of CRAC/Condenser installation Total estimated resiliency remediation cost = $1,566,000 + HVAC resiliency to support growth = $845,000 Rating Legend Concurrently Maintainable Increased Risk Shutdown Required Not Applicable 5

6 Facility Data: 43 North Circle Drive, Harrisburg Built in 1983 Data Center = 22,000 sf Current Server Count = 330 servers Current Uptime Institute Rating: Tier I (basic site infrastructure)* Growth Capacity: At current build: +210 servers At full build out: +668 servers Data PowerHouse (DPH) 6

7 DPH General Observations General Notes and Areas for Improvement: DPH is currently Tier I rated due to non-redundant cooling of the UPS and battery rooms; otherwise, it is Tier II resilient most notably owing to HVAC powering Input power restrictions prevent utilization of full UPS capacity The building is not equipped with a lightning protection system Facility grounding is not documented nor evident Data center fire suppression is via wet pipe system Primary electrical backbone equipment is within 5 years of its expected service life The terminals of the wet cell batteries are exposed and subject to accidental contact (although they are in a restricted access area) Staff expects the data center to be at capacity limits by mid 2010 Facility Recommendations: A primary hosting site for mission critical and other Commonwealth systems requiring high availability and 24x7 monitoring Current and future growth capacity suited for consolidation of systems from other sites 7

8 DPH Capacity Summary N+1 Utility N+1 Data Power House Data Center Full UPS Rating 59% 75% Space (RUs) 100% 58% 0% 47% 43% 65% 2N 81% 2N Notes: 1.Space consumption presumes historical policy deployment w ithout compaction or virtualization. 2. Pow er consumption adjusted for summer peak 3. UPS output limited by input pow er available via 1200A distribution System Data Power House Resiliency Resilient Capacity Current Consumption UPS 2N 1000kW 545kW PDU 2N 900kVA 608kVA CRAC N+1 440T 157T Drycoolers N+1 440T 173T Utility Transformers N kVA 1299kVA Generator N kW 1199kW N+1 N+1 (22/28) % Consumed Operating Limit Limiting Infrastructure Resiliency Resilient Capacity Assumed Operating Limit (%) Data PowerHouse Assumed Operating Limit Current Consumption Growth Potential (expressed as kw of IT Compute load) Growth Potential (expressed as % of current consumption) UPS 2N 1000 kw 65% 650 kw 545 kw % PDU 2N 900 kva 90% 810 kva 608 kva % Generator N kw 90% 1800 kw 1199 kw % Utility Transformer N kva 90% 2250 kva 1299 kva % Approximate Growth - Number of Discrete Servers (+ supporting storage & network) 210 Comments UPS supply circuit restricts UPS output to 65% of full resilient rating 8

9 DPH Tier III Conformance Electrical HVAC 9 Site Subsystem Utility Service Lightning Protection & TVSS Primary Power Disrtibution UPS Systems UPS Batteries Engine Generators Load Bank Secondary (Critical) Power Distribution Grounding Raised Floor Cooling UPS Room Cooling Equipment Conveyance Equipment Conveyance Equipment- Data Ctr. Dist'n. & Conv- Data Ctr. Heat Rejection Equipment- UPS Room Dist'n. & Conveyance- UPS Room Curret Uptime Tier Classification Description Comments & Related Subsystems Remediation Dual Utility Feed from two substations Data center building not equipped with lightning protection; Multi-tier TVSS deployed UPS powered at 2N; All HVAC powered from two ATS; HVAC is < 2N resilient 2N UPS 2N Batteries sized to support rated load for 15 minutes N+1 Generators but common paralleling bus; Generators share single radiator for heat rejection; Redundant starting batteries No load bank 2N to IT load via static switch PDUs Overall facility grounding is indeterminate- documentation specifies data center grid referenced to utility transformer neutral CRAC N+1 (22/28) at full UPS rating Not Applicable- Units contain compressors UPS room cooling is non-redundant- single 40T air handler/chiller Not Applicable- Units contain compressors Dry N+1 (22/28) redundancy Glycol conveyance comprised of 5 independent risers matching the 22/28 equipment resiliency deployment UPS room cooling is non-redundant- single 40T air handler/chiller Notes: 1 Tier 3 considers generators to be the primary electrical source Not Applicable- Packaged Unit with air distribution only Tier I Concurrent Maintainability Scorecard Data PowerHouse Feeds are aerial to site & non-diverse on-site Out-of-service maintenance of "Tie" in Main-Tie-Main configuration possible with emergency power system configuration Input source restrictions limit UPS to ~650kW output Must use utility as unprotected power source during bus & radiator maintenance Repaired equipment is testable only into production load Risk level elevated due to use of bulk rather than local STS for single cord devices Wet cell battery racks bonded to building steel Additionally, non-redundant exhaust fans in battery rooms Non-redundant cooling of UPS room Rating Legend Concurrently Maintainable Increased Risk Shutdown Required Not Applicable 1. Furnish & install one (1) automatic transfer switch (ATS) 2. Furnish & install three (3) manual transfer switches (MTS) 3. Furnish & install one (1) distribution panel for CRAC & drycooler system A 4. Install circuits from new ATS to distribution panel and generator distribution bus 5. Install circuits from new ATS to both main distribution panels 6. Install circuits between new ATS and three (3) new MTS 7. Disconnect circuit distribution panel CR2 Furnish & install 40-ton air conditioning unit + redundant fans for UPS room (current project) See UPS room equipment remediation Total estimated resiliency remediation cost = $1,590,000

10 Dept. of Env. Protection (DEP) Facility Data: 400 Market Street, Harrisburg Built in 1992 Data Center = 2,200 sf Current Server Count = 100 servers Current Uptime Institute Rating: Tier II (redundant capacity components) Growth Capacity: At current build: +68 servers At full build out: +160 servers 10

11 DEP General Observations General Notes and Areas for Improvement: Facility is Tier II resilient (non-redundant primary power backbone and non-redundant glycol conveyance) Data center fire suppression is via wet pipe system The center is protected by a single, non-redundant generator Facility grounding is not documented nor evident (although data center pedestals and cabinets are grounded The data center floor slab is rated for 100 pounds per square foot live loading TVSS is not deployed in the electrical distribution system Facility is located near an active railroad Per FEMA map # A dated May 2, 1977, the building is located on the boundary of the 100 and 500 year flood plains Facility Recommendations: Continue its role supporting critical agency systems Should be considered as a potential consolidation site for systems from other agencies that do not require high uptime or 24x7 monitoring 11

12 DEP Capacity Summary Dept. of Environmental Protection Data Center Operation at UPS Rating N Building Utility 2N Air Cooled Condensers 58% 35% Space (RUs) 100% 79% 55% 80% 2N 80% 0% 37% 59% 57% 80% Panel UP 2N Notes: 1. Space limit presumes sw ing space reserved for 5 year refresh cycle + 5% contingency 2. Operating limits presumed to be 90% of nameplate rating except as noted 3. Pow er consumption adjusted for summer peak 4. DCNR load on Panel UP presumed to be 152 A (100kVA rating) System Department of Environmental Protection Resiliency Resilient Capacity Current Consumption UPS 2N 104kW 39kW RPP 2N 900kVA 608kVA Panel UP N 600A 241A CRAC N+1 40T 11T Air-cooled Condensers N+1 94T 12T Building Utility Transformers 2N 2000kW 893kW Generator N 1100kW 384 N+1 % Consumed Operating Limit Limiting Infrastructure Resiliency Resilient Capacity Department of Environmental Protection Assumed Operating Limit (%) Assumed Operating Limit Current Consumption Growth Potential (expressed as kw of IT Compute load) Growth Potential (expressed as % of current consumption) RPP 2N 225 A 90% 203 A 108 A 34 88% UPS 2N 104 kw 80% 83 kw 39 kw % CRAC N+1 40 T 90% 36 T 11 T % Approximate Growth - Number of Discrete Servers (+ supporting storage & network) 68 Comments 12

13 DEP Tier III Conformance Electrical Site Subsystem Utility Service Lightning Protection & TVSS Primary Power Disrtibution UPS Systems UPS Batteries Engine Generators Load Bank Concurrent Maintainability Scorecard Department of Environmental Protection Description Comments & Related Subsystems Remediation Dual Utility Feed from two PP&L substations Data center building equipped with passive lightning protection; TVSS not noted nor indicated on drawings Single circuit powers UPS through panel UP1; All HVAC powered from single panel Feeds are underground to facility UL listing status unknown 1. Reconfigure power sources to Main-Tie-Tie-Main configuration by adding a 4000A breaker 2. Furnish & install one (1) 600A automatic transfer switch (ATS) 3. Furnish & install one (1) 400A HVAC distribution panel 4. Furnish & install one (1) distribution panel (UPB) 5. Furnish & install one (1) 100A manual transfer switch (MTS) 6. Install circuits from new 600A ATS to switchboard, new generator, new HVAC distribution panel, & new panel UPB 7. Install circuits one (1) new 2.5-ton CRAC unit and one (1) new condenser unit to each HVAC distribution panel 8. Install circuits from the new 50A MTS to each distribution panel, one (1) new CRAC unit, & one (1) new condenser 9. Install circuits from the new 100A MTS to each distribution panel 10. Remove circuits between one existing 20-ton CRAC unit and condenser and the existing HVAC distribution panel 11. Install circuits between one (1) 20-ton CRAC and condenser and the new HVAC distribution panel 2N UPS 2N Batteries sized to support rated load for 15 minutes Single Generator, non-redundant starting battery Not dedicated to technology operations 1. Furnish & install one (1) 500kW emergency generator No load bank Repaired equipment is testable only into production load Secondary (Critical) Power Distribution 2N to IT load; static switches not deployed Circuits powering single cord IT devices can not be maintained; UPS outputs via common panel with tie 1. Install circuits from one (1) existing UPS to panel UPB and to new UPS output panel; remove circuits to existing UP panel 2. Remove circuits from one (1) UPS to the UPS output panel 3. Install circuit between the new UPS output panel and the existing 225A distribution panel HVAC 13 Grounding Raised Floor Cooling UPS Room Cooling Dist'n. & Conv.- Data Ctr Heat Rejection Equipment- UPS Overall facility grounding is indeterminate- data center ground grid formed via pedistal bonding Equipment CRAC N+1 (2/3) at full UPS rating Conveyance Not Applicable- Units contain compressors Equipment UPS room cooling is N+1 redundant- 3 x 2.5T glycol units Conveyance Not Applicable- Units contain compressors Glycol pumps are redundant Equipment- Data Ctr Condensers paired 1:1 with 2 CRAC; Drycoolers are N+1 Dist'n. & Conv- UPS Two of 3 units are dual source units- refrigerant + glycol; third unit is glycol only Drycoolers are N+1 Linear glycol system with single riser to rooftop drycoolers Curret Uptime Tier Classification Tier II Notes: 1 Tier 3 considers generators to be the primary electrical source Glycol pumps are redundant Non-redundant primary power backbone, et al Rating Legend Concurrently Maintainable Increased Risk Shutdown Required Not Applicable 1. Remove one (1) vintage 20-ton CRAC unit & associated conveyance from server room 2. Furnish & install one (1) 20-ton CRAC unit in server room paired with condenser on 4th floor roof 3. Install circuits from the new 100A MTS to the new 20-ton CRAC & new 20-ton condenser 1. Remove three (3) 2.5-ton vintage (glycol) CRAC units & associated conveyance from the UPS room 2. Furnish & install three (3) 2.5-ton CRAC units in UPS room paired with condenser on 4th floor roof Total estimated resiliency remediation cost = $1,555,000

14 Facility Data: 651 Boas Street, Harrisburg Built in 1954 Data Center Renovation in 1997 Data Center = 7,000 sf Current Server Count = 593 servers Labor & Industry (L&I) Current Uptime Institute Rating: Tier II (redundant capacity components) Growth Capacity: At current build: +65 servers At full build out: +65 servers 14

15 L&I General Observations General Notes and Areas for Improvement: The L&I building is a multi-purpose, multi-tenant facility hosting over 30 L&I lines of business Data center is located adjacent to building lobby; access to building is not controlled by security Facility is Tier II resilient (non-redundant primary power backbone and non-redundant glycol conveyance) 11 raised floor height is not conducive to high density computing The center is protected by a single, non-redundant generator The UPS are located in the data center, contributing to the heat load TVSS is not deployed in the electrical distribution system Although located outside of the flood plain, flooding in surrounding areas could render the site unapproachable by critical staff Facility Recommendations: Continue its role supporting critical L&I systems Although expansion is limited, it should be considered as a potential consolidation site for systems from other agencies that do not require high uptime or 24x7 monitoring 15

16 L&I Capacity Summary N ATS N Substation N 85% Labor & Industry Data Center Operation at UPS Limit 49% 38% ATS N Space (RUs) 100% 78% 79% 0% 55% 45% 45% 48% 52% 57% 2N Substation N N+1 N+1 Notes: 1. UPS depicted as % of full rating with 45% policy deployment limit. 2. Space consumption presumes historical policy deployment without compaction or virtualization. 3. Power consumption adjusted for summer HVAC peak. % Consumed System Resiliency Resilient Capacity Current Consumption UPS 2N 440kW 172kW CRAC N+1 120T 54T Dry Coolers N+1 120T 59T Substation 8 Department of Labor & Industry N 500kVA 207kVA ATS 8 N 1200A 575A Substation 9 N 750kVA 243kVA ATS 9 N 1200A 675A Generator N 1500kW 421kW Operating Limit (90% unless otherwise noted) Department of Labor & Industry Limiting Infrastructure Resiliency Resilient Capacity Assumed Operating Limit (%) Assumed Operating Limit Current Consumption Growth Potential (expressed as kw of IT Compute load) Growth Potential (expressed as % of current consumption) Approximate Growth - Number of Discrete Servers (+ supporting storage & network) Comments UPS 2N 440 kw 45% 198 kw 172 kw 26 15% ATS 9 (HVAC) N 1200 A 90% 1080 A 675 A 53 46% Substation 9 N 750 kva 90% 675 kva 243 kva % 65 UPS operating limit expressed as % of total capacity 16

17 L&I Tier III Conformance Electrical HVAC 17 Site Subsystem Utility Service Lightning Protection & TVSS Primary Power Disrtibution UPS Systems UPS Batteries Engine Generators Load Bank Secondary (Critical) Power Distribution Grounding Raised Floor Cooling UPS Room Cooling Description Comments & Related Subsystems Remediation Dual Utility Feed from Capitol Campus Substation Roof containing critical drycoolers e/w passive lightning protection Single circuit via Power Center 8 powers UPS; Single circuit via Power Center 9 powers all critical HVAC Feeds are underground to facility; Substation double-ended form 4 PP&L circuits UL listing status unknown; TVSS not noted 2N UPS UPS system comprised of 8 independent in-row UPS Dedicated batteries for each UPS sized to support rated load for >15 minutes Single Generator e/w non-redundant starting batteries Single Load Bank dedicated to generator only 2N to IT load; static switches not deployed Overall facility grounding is indeterminate Equipment CRAC N+1 (6/8) at full UPS rating Conveyance Not Applicable- Units contain compressors Equipment Not Applicable- UPS located in Data Ctr Conveyance Not Applicable- UPS located in Data Ctr Eqpt- Data Ctr N+1 (6/8) at full UPS rating Dist'n. & Conv.- Data Linear glycol conveyance with single riser to roof Ctr Heat Rejection Cooling for Critical Power Centers 8 & 9 is non-redundant on Eqpt- Pwr Ctr base building system Dist'n. & Conv.- Pwr Linear chilled water conveyance to critical power center room Ctr Curret Uptime Tier Classification Notes: 1 Tier 3 considers generators to be the primary electrical source Concurrent Maintainability Scorecard Department of Labor & Industry Dedicated to technology operations Can not test UPS post maintenance Circuits powering single cord IT devices can not be maintained Per documentation, data center ground bar connected to telephone main ground via daisy chain; telco ground connected to main electrical ground in main electrical room- This ground was not evident Rating Legend Concurrently Maintainable Increased Risk Shutdown Required Not Applicable 1. Furnish & install one (1) 2000A power center 9b (including 750kVA transformer) 2. Furnish & install one (1) 800A power center 8b (including 250kVA transformer) 3. Furnish & install one (1) distribution board 4. Furnish & install six (6) manual transfer switches (MTS) 5. Furnish & install one (1) ATS 6. Disconnect circuits from seven (7) CRACs and their associated drycoolers 7. Install circuits from the new 800A ATS and the new 800A power center and UPS 5 and UPS 6 8. Add circuits from six (6) new MTS to both distribution boards and to six (6) CRACs and their associated drycoolers 9. Add circuit from one (1) CRAC and associated drycooler to the new distribution board 10. Disconnect circuits between the 1600A power center and UPS 1, UPS 2, UPS 5, UPS 6, and UPS Install circuits between the new 800A power center and UPS 1, UPS 2, and UPS 7 1. Furnish & install one (1) 1000kW generator 2. Furnish & install one (1) 2000A automatic transfer switch (ATS) 3. Furnish & install one (1) 800A ATS 4. Add circuits from the new generator to the new 800A and the new 2000A ATS 5. Add circuits from the new 2000A and the new 2000A ATS to the switchgear and the new power centers Not addressed due to operational disruption required to loop & add isolation to glycol conveyance; utilization of refrigerant system requires detailed engineering analysis Not addressed due to disruptive affect on building operations Not addressed due to disruptive affect on building operations Tier II Non-redundant primary power backbone, et al Total estimated resiliency remediation cost = $3,383,000

3300 kw, Tier 3, Chilled Water, 70,000 ft 2

3300 kw, Tier 3, Chilled Water, 70,000 ft 2 [Reference Design 22] 3300 kw, Tier 3, Chilled Water, 70,000 ft 2 DESIGN OVERVIEW Data Center IT Capacity 1100 kw per Data Hall 3 Independent Data Halls Design Application Range This design can be applied

More information

IXcellerate Moscow One Datacentre - Phase 1 & 2 Overview

IXcellerate Moscow One Datacentre - Phase 1 & 2 Overview Contents 1. Document Purpose... 2 2. Facility Overview... 2 2.1 Technical Space... 2 2.2 Load Density... 2 2.3 Resilience... 2 2.4 Engineering Plant Maintenance & Service Restoration... 3 3. Engineering

More information

Delaware s Premier Suburban Office Park

Delaware s Premier Suburban Office Park IRON IRON HILL HILL CORPORATE CORPORATE CENTER CENTER Delaware s Premier Suburban Office Park WHITE WING 700 RED WING 750 www.cbre.us/ironhill PROJECT SUMMARY White Wing Red Wing Blue Wing Parking Garage

More information

Delaware s Premier Suburban Office Park

Delaware s Premier Suburban Office Park IRON IRON HILL HILL CORPORATE CORPORATE CENTER CENTER Delaware s Premier Suburban Office Park WHITE WING 700 RED WING 750 BLUE WING 800 www.cbre.us/ironhill PROJECT SUMMARY White Wing Red Wing Blue Wing

More information

84 kw, Tier 3, Direct Expansion, 937 ft 2

84 kw, Tier 3, Direct Expansion, 937 ft 2 [Reference Design 42] 84 kw, Tier 3, Direct Expansion, 937 ft 2 DESIGN OVERVIEW Data Center IT Capacity 84 kw Target Availability Tier 3 Annualized PUE at 100% Load 1.712 Total Racks and Average Density

More information

7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America

7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America 7 Best Practices for Increasing Efficiency, Availability and Capacity XXXX XXXXXXXX Liebert North America Emerson Network Power: The global leader in enabling Business-Critical Continuity Automatic Transfer

More information

CenturyLink Data Center Services Omaha, Nebraska

CenturyLink Data Center Services Omaha, Nebraska CenturyLink Data Center Services Omaha, Nebraska HIGH AVAILABILITY ENTERPRISE COMPUTING Designed and equipped to meet the demands of enterprises, wholesale businesses and government agencies, CenturyLink

More information

Course Description. Audience. Prerequisites. : Course CTDC : Certified TIA-942 Design Consultant. Course Outline :: CTDC ::

Course Description. Audience. Prerequisites. : Course CTDC : Certified TIA-942 Design Consultant. Course Outline :: CTDC :: Module Title Duration : Course CTDC : Certified TIA-942 Design Consultant : 3 days Course Description Data centres are at the core of many organisations. Downtime of the data centre could lead to major

More information

White Paper: Data Center Capacity Management Provides New Business Opportunities & Efficiency at State-of-the-Art One Wilshire June 8, 2017

White Paper: Data Center Capacity Management Provides New Business Opportunities & Efficiency at State-of-the-Art One Wilshire June 8, 2017 White Paper: Data Center Capacity Management Provides New Business Opportunities & Efficiency at State-of-the-Art One Wilshire June 8, 2017 As operators have demanded increasing levels of power density

More information

MSYS 4480 AC Systems Winter 2015

MSYS 4480 AC Systems Winter 2015 MSYS 4480 AC Systems Winter 2015 Module 12: DATA CENTERS By Satwinder Singh 14/05/2015 1 Data Centers Data Centers are specialized environments that safeguard your company's most valuable equipment and

More information

Colocation Checklist Not all data centers are created equal.

Colocation Checklist Not all data centers are created equal. Colocation Checklist Not all data centers are created equal. They vary in performance, reliability, control and security standards. Know what to look for in a colocation provider with this comprehensive

More information

Cooling. Highly efficient cooling products for any IT application. For More Information: (866) DATA CENTER SOLUTIONS

Cooling. Highly efficient cooling products for any IT application. For More Information: (866) DATA CENTER SOLUTIONS Cooling > Highly efficient cooling products for any IT application. DATA CENTER SOLUTIONS For More Information: (866) 787-3271 Sales@PTSdcs.com End-to-End Cooling Solutions from the Closet to the Data

More information

STATE DATA CENTER DRAFT PROPOSAL. STATE OF OREGON DATA CENTER 28 October 2016

STATE DATA CENTER DRAFT PROPOSAL. STATE OF OREGON DATA CENTER 28 October 2016 STATE DATA CENTER DRAFT PROPOSAL 1 PROJECT TEAM 2 SERA Architects, Inc George Hager Patrick Sullivan PAE Engineers Dave Williams Doug Nachtrieb Michael Yee JMB Consulting Group Jon Bayles MEETING GOALS

More information

Kifer Industrial Park

Kifer Industrial Park FEATURES ±56,358 SF Data Center / Lab / Manufacturing Building The entire facility is built-out with raised floor data center and data center support space Heavy Power Multiple telecom providers Pre-action

More information

Passive RDHx as a Cost Effective Alternative to CRAH Air Cooling. Jeremiah Stikeleather Applications Engineer

Passive RDHx as a Cost Effective Alternative to CRAH Air Cooling. Jeremiah Stikeleather Applications Engineer Passive RDHx as a Cost Effective Alternative to CRAH Air Cooling Jeremiah Stikeleather Applications Engineer Passive RDHx as a Cost Effective Alternative to CRAH Air Cooling While CRAH cooling has been

More information

Data Center NJ1. Piscataway, NJ

Data Center NJ1. Piscataway, NJ Data Center NJ1 Piscataway, NJ powerful/ efficient /reliable solutions > Data Center NJ1 ABOUT DUPONT FABROS TECHOLOGY (DFT) DFT is a leading owner, developer, operator and manager of wholesale data centers.

More information

Mission Critical Facilities & Technology Conference November 3, 2011 Cooling 101. Nick Gangemi Regional Sales Manager Data Aire

Mission Critical Facilities & Technology Conference November 3, 2011 Cooling 101. Nick Gangemi Regional Sales Manager Data Aire Mission Critical Facilities & Technology Conference November 3, 2011 Cooling 101 Nick Gangemi Regional Sales Manager Data Aire Agenda Exactly what are we talking about ASHRAE TC 9.9 Design best practices

More information

5.2 MW, Pod-based build, Chilled Water, ft 2

5.2 MW, Pod-based build, Chilled Water, ft 2 [Reference Design 65] 5.2 MW, Pod-based build, hilled Water, 85000 ft 2 DESIGN OVERVIEW Data enter apacity 5.2 MW Target Availability Tier III with 2N power distribution and less-redundant generator configuration

More information

CenturyLink Data Center Services Herndon, Virginia

CenturyLink Data Center Services Herndon, Virginia CenturyLink Data Center Services Herndon, Virginia DATA CENTER SOLUTIONS TO SUPPORT GLOBAL ENTERPRISE IT The IT environment is rapidly changing. Organizations are expanding their IT infrastructure to accommodate

More information

DATA CENTER COLOCATION BUILD VS. BUY

DATA CENTER COLOCATION BUILD VS. BUY DATA CENTER COLOCATION BUILD VS. BUY Comparing the total cost of ownership of building your own data center vs. buying third-party colocation services Executive Summary As businesses grow, the need for

More information

1301 FANNIN HOUSTON, TEXAS 77002

1301 FANNIN HOUSTON, TEXAS 77002 1301 FANNIN HOUSTON, TEXAS 77002 10 TH FLOOR OVERVIEW Available SF: Lease Rate: OpEx: HIGHLIGHTS ± 41,255 SF $25.00 SF/Yr. (NNN) $15.63 SF/Yr. Rare large footprint available in the city s most robust datacenter

More information

INT 492 : Selected Topic in IT II (Data Center System Design) 3(3-0-6)

INT 492 : Selected Topic in IT II (Data Center System Design) 3(3-0-6) INT 492 : Selected Topic in IT II (Data Center Design) 3(3-0-6) การออกแบบระบบศ นย สารสนเทศ Overview The American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE) Technical Committee

More information

ENCLOSURE HEAT DISSIPATION

ENCLOSURE HEAT DISSIPATION ENCLOSURE HEAT DISSIPATION DATA CENTER SOLUTIONS A White Paper by Great Lakes Case & Cabinet Company www.werackyourworld.com 814.734.7303 Page 2 Introduction Dangerous heat levels inside an enclosure threaten

More information

Tier IV Standards as Specified in the TIA 942 Document

Tier IV Standards as Specified in the TIA 942 Document S No Architectural Proximity of visitor parking to data 18.3 m / 60 ft minimum separation with physical barriers to prevent vehicles from 1 center perimeter building walls driving closer 2 Building Construction

More information

ANSI/BICSI Data Center Design and Implementation Best Practices

ANSI/BICSI Data Center Design and Implementation Best Practices ANSI/BICSI 002-2014 Data Center Design and Implementation Best Practices Risk, Reliability & Availability Selecting a Data Center Design Class Bob Camerino RCDD DCDC CT Vice Chair BICSI Mainland Europe

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

EXPERIS DATA CENTER Valley Pike, Middletown, VA. Location Map & Aerials. Building Profile & Facts. Floor Plans

EXPERIS DATA CENTER Valley Pike, Middletown, VA. Location Map & Aerials. Building Profile & Facts. Floor Plans Building Profile & Facts 1 Location Map & Aerials 4 Floor Plans 5 BUILDING PROFILE & FACTS SHEET 1 Property Name Address Tax Map & Parcel Number Land Area Building Size Experis Data Centers, LLC 8209 Valley

More information

PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST

PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST THE CENTER THAT NEVER SLEEPS The greater New York metro area is a pulsing capital of industry and finance alive 24 x 7 x 365 with critical transactions

More information

2000 kw, Tier 3, Chilled Water, Prefabricated, sq. ft.

2000 kw, Tier 3, Chilled Water, Prefabricated, sq. ft. [Reference Design 64] 2000 kw, Tier 3, Chilled Water, refabricated, 23700 sq. ft. DESIGN OVERVIEW Data Center IT Capacity 2000 kw Target Availability Tier 3 Annualized E at 100% Load 1.64 in Miami, FL

More information

1.0 Executive Summary

1.0 Executive Summary Statement of Work - 1 - Power and Cooling Assessment for Data Center Professional Services Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service

More information

Total Modular Data Centre Solutions

Total Modular Data Centre Solutions Sector Data Centre Total Modular Data Centre Solutions www.airedale.com BRITISH MANUFACTURER ENERGY EFFICIENCY CONTROLS SERVICE TRAINING 01 Standardised Modular Designs to fit your needs Our modular system

More information

How Liquid Cooling Helped Two University Data Centers Achieve Cooling Efficiency Goals. Michael Gagnon Coolcentric October

How Liquid Cooling Helped Two University Data Centers Achieve Cooling Efficiency Goals. Michael Gagnon Coolcentric October How Liquid Cooling Helped Two University Data Centers Achieve Cooling Efficiency Goals Michael Gagnon Coolcentric October 13 2011 Data Center Trends Energy consumption in the Data Center (DC) 2006-61 billion

More information

SmartRow Solution Intelligent, Integrated Infrastructure for the Data Center

SmartRow Solution Intelligent, Integrated Infrastructure for the Data Center SmartRow Solution Intelligent, Integrated Infrastructure for the Data Center Deploy a Fully Configured Data Center in Just Weeks Availability, Capacity, Efficiency. You need them and now you can have them

More information

Powering Change in the Data Center. A White Paper from the Experts in Business-Critical Continuity TM

Powering Change in the Data Center. A White Paper from the Experts in Business-Critical Continuity TM Powering Change in the Data Center A White Paper from the Experts in Business-Critical Continuity TM Executive Summary Increases in data center density and diversity are driving change in the power and

More information

Syska Criticality Levels

Syska Criticality Levels Appendix C Syska Criticality Levels SYSKA CRITICALITY LEVEL TM DEFINITIONS Syska Hennessy Group Critical Facilities are designed and constructed on a scale of 1 10, 10 being the ultimate in criticality.

More information

a) Provision of a chilled water supply b) Provision of electric power supply and other fuels

a) Provision of a chilled water supply b) Provision of electric power supply and other fuels 10.0 UTILITIES ELEMENT The purpose of this element is to ensure coordinated provision of utility services required to meet the future needs of the University, consistent with current efforts to address

More information

Phil Tuma, Application Development Engineer John Gross, Mechanical Engineering Director Kar-Wing Lau, CEO Charles Benge, Director Mission Critical

Phil Tuma, Application Development Engineer John Gross, Mechanical Engineering Director Kar-Wing Lau, CEO Charles Benge, Director Mission Critical E n g i n e e r i n g W o r k s h o p : A d v a n c e d C o o l i n g S o l v i n g t h e E n e r g y C h a l l e n g e t h r o u g h I n n o v a t i o n s i n D a t a C e n t e r C o o l i n g 3m.com/immersion

More information

Cooling Solutions & Considerations for High Performance Computers

Cooling Solutions & Considerations for High Performance Computers Cooling Solutions & Considerations for High Performance Computers White Paper 6 Revision 1 By Rich Whitmore Executive summary The recent advances in high performance computing have driven innovations not

More information

CPS VS UPS FOR POWERING DATA CENTERS

CPS VS UPS FOR POWERING DATA CENTERS CPS VS UPS FOR POWERING DATA CENTERS HOW THE ADVANTAGES OF A NO BREAK CONVERGED POWER SYSTEM (CPS) PROVIDED BETTER POWER RELIABILITY, SYSTEM AVAILABILITY AND REDUCED COSTS OVER A UNINTERRUPTABLE POWER

More information

Measuring and Managing a Data Center Cooling Shutdown

Measuring and Managing a Data Center Cooling Shutdown Measuring and Managing a Data Center Cooling Shutdown Columbia University Information Technology - August 24, 2012 Table of Contents Overview Timeline Cricket Graphs What s being graphed Mechanical Electrical

More information

ANSI/BICSI Data Center Design and Implementation Best Practices

ANSI/BICSI Data Center Design and Implementation Best Practices ANSI/BICSI 002-2014 Data Center Design and Implementation Best Practices Risk, Reliability & Availability Selecting a Data Center Design Class Bob Camerino RCDD DCDC CT Secretary BICSI Mainland Europe

More information

KEEPING YOU OUT IN FRONT

KEEPING YOU OUT IN FRONT URBACON DATA CENTRE SOLUTIONS KEEPING YOU OUT IN FRONT A next generation data centre in the core of downtown Toronto DOWNTOWN DATA CENTRE 281 FRONT STREET TORONTO, ON 1 2 X URBACON BUILDING GROUP 70 Lake

More information

Future of Cooling High Density Equipment. Steve Madara Vice President and General Manager Liebert Precision Cooling Business Emerson Network Power

Future of Cooling High Density Equipment. Steve Madara Vice President and General Manager Liebert Precision Cooling Business Emerson Network Power Future of Cooling High Density Equipment Steve Madara Vice President and General Manager Liebert Precision Cooling Business Emerson Network Power Agenda Issues facing the Data Center Managing the explosive

More information

200 kw, Tier 3, Chilled Water, 5250 ft 2

200 kw, Tier 3, Chilled Water, 5250 ft 2 [eference Design 4] 200 kw, Tier 3, Chilled Water, 5250 ft 2 DESIGN OVEVIEW Data Center IT Capacity 200 kw Adaptable from 50 kw to 600 kw Target Availability Tier 3 Annualized UE at 100% Load 1.67 in Miami,

More information

A Data Center Heat Removal System That Saves... 80% Discover Inertech s Award-winning Data Center Heat Removal System

A Data Center Heat Removal System That Saves... 80% Discover Inertech s Award-winning Data Center Heat Removal System A Data Center Heat Removal System That Saves... Infrastructure Power Water up to 40% up to 80% up to 85% Discover Inertech s Award-winning Data Center Heat Removal System A Cool Solution; A Breakthrough

More information

REPORT. Energy Efficiency of the San Diego Supercomputer Center and Distributed Data Centers at UCSD. Prepared for:

REPORT. Energy Efficiency of the San Diego Supercomputer Center and Distributed Data Centers at UCSD. Prepared for: REPORT Energy Efficiency of the San Diego Supercomputer Center and Distributed Data Centers at UCSD Prepared for: San Diego Supercomputer Center 10100 John J Hopkins Drive San Diego, CA 92037 May 11, 2009

More information

Utility System Infrastructure

Utility System Infrastructure Utility System Infrastructure THE COLLEGE OF 2015 Campus Master Plan WILLIAM & MARY SUPPORTING DOCUMENTATION TABLE OF CONTENTS 3 4 4 4 4 5 Electrical Utility Infrastructure Emergency Power Generators

More information

ASCENT DATA CENTER. 30 MW Data Center Enterprise Grade Facility LEED Gold ATLANTA, GA ABOUT ASCENT CO LO CAT I O N SUI T E S AVAI LAB LE NO W!

ASCENT DATA CENTER. 30 MW Data Center Enterprise Grade Facility LEED Gold ATLANTA, GA ABOUT ASCENT CO LO CAT I O N SUI T E S AVAI LAB LE NO W! ASCENT DATA CENTER CO LO CAT I O N SUI T E S AVAI LAB LE NO W! ATLANTA, GA 30 MW Data Center Enterprise Grade Facility LEED Gold ABOUT ASCENT Ascent Data Center is located in the greater Atlanta, Georgia

More information

Datacentre Milton Keynes Hall C Data sheet

Datacentre Milton Keynes Hall C Data sheet Datacentre Milton Keynes Hall C Data sheet Data sheet Datacentre Milton Keynes Hall C Find us With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations, Pulsant

More information

Data Center SC1. Santa Clara, CA

Data Center SC1. Santa Clara, CA Data Center SC1 Santa Clara, CA powerful/ efficient /reliable solutions > Data Center SC1 ABOUT DUPONT FABROS TECHOLOGY (DFT) DFT is a leading owner, developer, operator and manager of wholesale data centers.

More information

Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design.

Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. TelecityGroup Kvastvägen 25-29 128 62 Sköndal Stockholm Sweden Tel: +46 (0) 8 799 3800 se.info@telecity.com www.telecitygroup.se

More information

1008 kw, Tier 2, Chilled Water, ft 2

1008 kw, Tier 2, Chilled Water, ft 2 [eference Design 81] 1008 kw, Tier 2, hilled Water, 18115 ft 2 DESIGN OVEVIEW Data enter IT apacity 1008 kw Adaptable from 200 kw to 3024 kw Target Availability Tier 2 Annualized PUE at 100% Load 1.65

More information

High Performance Computing (HPC) Data Center Proposal

High Performance Computing (HPC) Data Center Proposal High Performance Computing (HPC) Data Center Proposal Imran Latif, Facility Project Manager Scientific & Enterprise Computing Data Centers at BNL 10/14/2015 Quick Facts!! Located on 1 st floor in Building

More information

AT&T Enterprise Hosting Services

AT&T Enterprise Hosting Services AT&T Enterprise Hosting Services Irvine, CA Internet Data Center Last Update: 09.25.2008 2008 AT&T Intellectual Property. All rights reserved. AT&T and the AT&T logo are trademarks of AT&T Intellectual

More information

FREEING HPC FROM THE DATACENTRE

FREEING HPC FROM THE DATACENTRE FREEING HPC FROM THE DATACENTRE ku:l sistem TM COOLING REDEFINED www.iceotope.com ku:l sistem removes the need for inefficient air cooling technologies FREEING HPC FROM THE DATACENTRE Iceotope s patented

More information

Dude Solutions Business Continuity Overview

Dude Solutions Business Continuity Overview Dude Solutions Business Continuity Overview Table of Contents Overview.... 2 Primary and Disaster Recovery Data Centers.... 2 Network Infrastructure.... 3 Emergency Processes.... 3 Power and Cooling Systems....

More information

Thermal management. Thermal management

Thermal management. Thermal management Thermal management Thermal management Managing thermal loads is a major challenge for all Data Centre operators. Effecting proper control of the thermal environment drives energy consumption and ultimately

More information

POWERING A CONNECTED ASIA. Pacnet Hong Kong DataSpace1 Technical Specifications. Advanced Data Center Facility for Multi-Site Enterprises

POWERING A CONNECTED ASIA. Pacnet Hong Kong DataSpace1 Technical Specifications. Advanced Data Center Facility for Multi-Site Enterprises POWERING A CONNECTED ASIA Pacnet Hong Kong DataSpace1 Technical Specifications Advanced Data Center Facility for Multi-Site Enterprises Pacnet Hong Kong DataSpce1 (HKDS1) provides an ideal environment

More information

Liebert DCW CATALOGUE

Liebert DCW CATALOGUE Liebert DCW CATALOGUE Chilled Water-Based High Density Cooling For The Data Center LIEBERT DCW Flexible Approaches For Energy Efficient Cooling Save up to 70% in cooling energy usage Data center managers

More information

A) Differences between Precision and Comfort Cooling Here are the major differences exist between precision air conditioning and comfort systems.

A) Differences between Precision and Comfort Cooling Here are the major differences exist between precision air conditioning and comfort systems. DATA CENTRE COOLING SYSTEM A) Differences between Precision and Comfort Cooling Here are the major differences exist between precision air conditioning and comfort systems. 1. Cooling Optimized to Electronic

More information

Data Center Assessment Helps Keep Critical Equipment Operational. A White Paper from the Experts in Business-Critical Continuity TM

Data Center Assessment Helps Keep Critical Equipment Operational. A White Paper from the Experts in Business-Critical Continuity TM Data Center Assessment Helps Keep Critical Equipment Operational A White Paper from the Experts in Business-Critical Continuity TM Executive Summary The IT infrastructure within many companies has evolved

More information

Data Center Energy Savings By the numbers

Data Center Energy Savings By the numbers Data Center Energy Savings By the numbers Chris Kurkjian, PE HP Critical Facility Services provided by EYP Mission Critical Facilities 2008 Hewlett-Packard Development Company, L.P. The information contained

More information

Technology Incubation Center. High Tech Cleanroom Laboratory & Production Facility.

Technology Incubation Center. High Tech Cleanroom Laboratory & Production Facility. High Tech Cleanroom Laboratory & Production Facility www.technologyincubationcenter.com Jay Chmieleski 612 275 3775 mobile Dan Friedner FOR SALE OR LEASE Technology Incubation Center VADNAIS HEIGHTS, MINNESOTA

More information

Efficiency of Data Center cooling

Efficiency of Data Center cooling Efficiency of Data Center cooling Comparison of data room layouts and cooling systems Bohumil Cimbal Product manager for Cooling Systems in CONTEG Company Objective Basic questions between investor and

More information

G5 PDU Installation Guide

G5 PDU Installation Guide G5 PDU Installation Guide 1 Contents Before You Begin... 3 Overview... 3 Important Safety Information... 3 Required Tools... 5 Section 1 Introduction... 6 Classification Overview... 6 Features... 7 Form

More information

SmartMod Intelligent, Integrated Infrastructure for the Data Center

SmartMod Intelligent, Integrated Infrastructure for the Data Center SmartMod Intelligent, Integrated Infrastructure for the Data Center Deploy a High-Capacity, Efficient and Secure Infrastructure in Just Months Building a new data center in a short timeframe is nearly

More information

Impact of Air Containment Systems

Impact of Air Containment Systems White Paper June 2012 WP-20 Impact of Air Containment Systems Reducing Energy Consumption Introduction: The Importance of Maintaining Data Center Cooling Energy Efficiency Data centers are mission-critical

More information

9.6 MW, Traditional IT and OCP-compatible, Indirect Air Economizer, m 2

9.6 MW, Traditional IT and OCP-compatible, Indirect Air Economizer, m 2 [Reference esign 62] 9.6 MW, Traditional IT and OC-compatible, Indirect Air Economizer, 16970 m 2 ESIGN OVERVIEW ata Center IT Capacity 9.6 MW Target Availability Tier III with 2N power distribution and

More information

Datacentre Milton Keynes Data sheet

Datacentre Milton Keynes Data sheet Datacentre Milton Keynes Data sheet Data sheet Datacentre Milton Keynes Find us With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations, Pulsant has the

More information

Cable Facility Classification Definitions and Requirements

Cable Facility Classification Definitions and Requirements ENGINEERING COMMITTEE Energy Management Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 226 2015 Cable Facility Classification Definitions and Requirements NOTICE The Society of Cable Telecommunications

More information

Two-Stage Power Distribution: An Essential Strategy to Future Proof the Data Center

Two-Stage Power Distribution: An Essential Strategy to Future Proof the Data Center Two-Stage Power Distribution: An Essential Strategy to Future Proof the Data Center Adapting to Change Concern over the pace of technology change is increasing among data center managers. This was reflected

More information

APC InfraStruXure Solution Overview

APC InfraStruXure Solution Overview APC InfraStruXure Solution Overview We re waiting for your call or email. 800--0 uptime@uptimeu.com Wiring Closets ( Racks) Small Server Rooms ( Racks) Small Data Centers ( 0 Racks) Medium Data Centers

More information

RFP Questions Guideline For Data Center Buyers

RFP Questions Guideline For Data Center Buyers RFP Questions Guideline For Data Center Buyers Rev: 00W0052015 1 P a g e This guideline document is a supporting download for our webinar titled 5 RFP Questions Data Center Buyers Must Ask a Provider and

More information

FPX. Forest Park Ten 8333 Forest Point Boulevard Charlotte, NC Cardinal Real Estate Partners LLC

FPX. Forest Park Ten 8333 Forest Point Boulevard Charlotte, NC Cardinal Real Estate Partners LLC Forest Park Ten 8333 Forest Point Boulevard Charlotte, NC 28273 For More Information, Contact the Leasing Team at: Cardinal Real Estate Partners LLC John Culbertson, CRE, CCIM, SIOR jculbertson@cardinal-partners.com

More information

Variable Density, Closed-Loop, Water-Cooled Data Center Solution

Variable Density, Closed-Loop, Water-Cooled Data Center Solution Variable Density, Closed-Loop, Water-Cooled Data Center Solution Overview Great Lakes Case & Cabinet Co., Inc. has worked with Naissus Thermal Management Solutions, of Toronto, Ontario to develop one of

More information

Boise Data Center Guarantees 100 Percent Uptime

Boise Data Center Guarantees 100 Percent Uptime Boise Data Center Guarantees 100 Percent Uptime All-Copper Grounding Systems Ensure Reliability, Lower Maintenance Costs Among Involta s newest-generation data centers is this 31,400 square feet facility

More information

GROW YOUR BRAND AND MAKE AN IMPRESSION. Unique 2-storey office building with Highway 401 exposure

GROW YOUR BRAND AND MAKE AN IMPRESSION. Unique 2-storey office building with Highway 401 exposure GROW YOUR BRAND AND MAKE AN IMPRESSION Unique 2-storey office building with Highway 401 exposure Grand entrance and great room with high ceilings Low gross up factor - 4.3%, large floor plates 2 internal

More information

Datacentre Newbridge Data sheet

Datacentre Newbridge Data sheet Datacentre Newbridge Data sheet Data sheet Datacentre Newbridge Find us 7 Claylands Road Edinburgh EH28 8LF Scotland With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our

More information

IBM Site Enablement Services

IBM Site Enablement Services IBM Site Enablement Services Resilience for Your Data Centre 13/05/2005 Why Site Enablement Services? Hardware and Software are becoming increasingly dependable, but the environment in which they operate

More information

Critical IT Facilities at the Edge

Critical IT Facilities at the Edge Critical IT Facilities at the Edge Mark Howell Global IT Facilities Planning & Engineering Ford Motor Company Critical IT Facilities at the Edge What are critical IT facilities at the Edge? Why are critical

More information

Seven Best Practices for Increasing Efficiency, Availability and Capacity: The Enterprise Data Center Design Guide

Seven Best Practices for Increasing Efficiency, Availability and Capacity: The Enterprise Data Center Design Guide Seven Best Practices for Increasing Efficiency, Availability and Capacity: The Enterprise Data Center Design Guide A White Paper from the Experts in Business-Critical Continuity TM Table of Contents Introduction...

More information

Datacentre Reading East 2 Data sheet

Datacentre Reading East 2 Data sheet Datacentre Reading East 2 Data sheet Data sheet Datacentre Reading East 2 Find us With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations, Pulsant has the

More information

Data Centre In A Box

Data Centre In A Box Data Centre In A Box Data Centre In A Box Rittal s Data Centre In A Box replicates all of the key data centre capabilities but on a smaller scale. The Data Centre In A Box mitigates risk and provides compelling

More information

Viable Options for Data Center Solutions. By Ning Liu Offering Group Panduit APJ

Viable Options for Data Center Solutions. By Ning Liu Offering Group Panduit APJ Viable Options for Data Center Solutions By Ning Liu Offering Group Panduit APJ Agenda Market Overview Data Center Challengers Business Drivers Data Center Standards Data Center Technologies Panduit Solutions

More information

Engineering Pre-Design Study

Engineering Pre-Design Study Engineering Pre-Design Study report for: University of Minnesota Project Name: University Project Number: 01-184-17-1520 KFI Project Number: 17-038.00 March 2, 2017 Title Page Building Information University

More information

LANL High Performance Computing Facilities Operations. Rick Rivera and Farhad Banisadr. Facility Data Center Management

LANL High Performance Computing Facilities Operations. Rick Rivera and Farhad Banisadr. Facility Data Center Management Slide-1 LANL High Performance Computing Facilities Operations Rick Rivera and Farhad Banisadr Facility Data Center Management Division Slide-2 Outline Overview - LANL Computer Data Centers Power and Cooling

More information

Dazelidis Thanos - Product Manager Rittal Greece 1

Dazelidis Thanos - Product Manager Rittal Greece 1 Dazelidis Thanos - Product Manager Rittal Greece 1 Facility Location Lefdal Mine is located in the region Sogn og Fjordane between Måløy and Nordfjordeid. It is situated next to a deep, cold fjord with

More information

Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect

Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect of Record: SPARCH Project Overview The project is located

More information

Newark, Delaware Architectural Engineering Senior Thesis Portfolio

Newark, Delaware Architectural Engineering Senior Thesis Portfolio Telecommunications System Design The represents the advancement of solar design in our world today. The building itself is an example of this. A Headquarters this dedicated to moving into the future should

More information

Types of Prefabricated Modular Data Centers

Types of Prefabricated Modular Data Centers Types of Prefabricated Modular Data Centers White Paper 165 Revision 0 by Wendy Torell Executive summary Data center systems or subsystems that are preassembled in a factory are often described with terms

More information

Energy Logic: Emerson Network Power. A Roadmap for Reducing Energy Consumption in the Data Center. Ross Hammond Managing Director

Energy Logic: Emerson Network Power. A Roadmap for Reducing Energy Consumption in the Data Center. Ross Hammond Managing Director Energy Logic: A Roadmap for Reducing Energy Consumption in the Data Center Emerson Network Power Ross Hammond Managing Director Agenda Energy efficiency Where We Are Today What Data Center Managers Are

More information

brightsolid Data Hall 1 Keysource Technical Specifications

brightsolid Data Hall 1 Keysource Technical Specifications brightsolid Data Hall 1 Keysource Technical Specifications Page 1 Introduction A Data Centre is a highly controlled environment that provides IT to external organisations seeking to outsource their requirements

More information

FACT SHEET: IBM NEW ZEALAND DATA CENTRE

FACT SHEET: IBM NEW ZEALAND DATA CENTRE FACT SHEET: IBM NEW ZEALAND DATA CENTRE IBM and the Data Centre IBM is the largest occupier of data centre space in the world and currently owns or occupies approximately one million square metres globally.

More information

Data Center Design and the ANSI/TIA-942 Standard

Data Center Design and the ANSI/TIA-942 Standard Data Center Design and the BICSI Regional Meeting Ellicott, MD Rick Foster RCDD,TLT Communications Infrastructure Group July 27, 2006 What is ANSI/TIA-942? Published by TIA in April 2005 Telecommunications

More information

Evaporative free air cooling technology Providing evaporative free air cooling solutions.

Evaporative free air cooling technology Providing evaporative free air cooling solutions. Evaporative free air cooling technology Providing evaporative free air cooling solutions. Creating an effective workspace environment data centre free air cooling technology FreeCool - Evaporative Free

More information

Maximise Data Center Value

Maximise Data Center Value Maximise Data Center Value with Higher Density Infrastructure Dramatic cost savings enabled; Requires solving unique electrical + cooling challenges; 08 December 2015 Speaker gokhan.gulal@4g.net.tr Genel

More information

Cisco CRS 16-Slot Chassis Power Systems

Cisco CRS 16-Slot Chassis Power Systems This chapter includes the following sections: Power specifications are provided in Technical Specifications Power Systems Overview, on page 1 Power Component Information Common to the Two Types of Power

More information

T66 Central Utility Building (CUB) Control System Reliability, Optimization & Demand Management

T66 Central Utility Building (CUB) Control System Reliability, Optimization & Demand Management T66 Central Utility Building (CUB) Control System Reliability, Optimization & Demand Management Name Doug Demian Title Application Engineer Date November 7 & 8, 2012 Rev 5058-CO900C Copyright 2012 Rockwell

More information

Data Center Site Infrastructure Tier Standard: Topology

Data Center Site Infrastructure Tier Standard: Topology U P T I M E I N S T I T U T E Data Center Site Infrastructure Tier Standard: Topology Prepared by Uptime Institute Professional Services Copyright 2009 by the Uptime Institute Building 100 2904 Rodeo Park

More information

Increasing Data Center Efficiency by Using Improved High Density Power Distribution

Increasing Data Center Efficiency by Using Improved High Density Power Distribution Increasing Data Center Efficiency by Using Improved High Density Power Distribution By Neil Rasmussen White Paper #128 Revision 1 Executive Summary A new approach to power distribution for high density

More information