EDS MW AND MVAR TRANSDUCER CONNECTION

Size: px
Start display at page:

Download "EDS MW AND MVAR TRANSDUCER CONNECTION"

Transcription

1 Document Number: EDS Network(s): Summary: ENINEERIN DESIN STANDARD EDS MW AND MVAR TRANSDUCER CONNECTION EPN, LPN, SPN This standard details the convention to be used when wiring MW and MVAr transducers so that power flow direction can be ascertained. Owner: James Ford Approved By: Paul Williams Approved Date: 13/09/2016 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Applicable To UK Power Networks All UK Power Networks Asset Management Capital Programme Connections HSS&TT Network Operations UK Power Networks Services Other External 81 Website Contractors ICPs/IDNOs Meter Operators THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE

2 Revision Record Version 3.0 Review Date 31/08/2021 Date 31/08/2016 Author James Ford Why has the document been updated Periodic review What has changed - 11kV and LV network added and diagrams within appendices refreshed Version 2.0 Review Date 17/12/2015 Date 12/11/2012 Author Azzam Al-Riyami Document reviewed and minor modification to cater for the preference to have the transducer functions within the protection devices. Version 1.4 Review Date Date 16/07/2012 Author Lee Strachan Document reviewed for publishing on 81 Version 1.3 Review Date Date 25/08/2011 Author Chris Anderson Re-classified from EI to EDS Version 1.2 Review Date Date 16/03/2011 Author Don Fossett Document re-branded Version 1.1 Review Date Date 10/08/2010 Author Reviewed and review date extended James Ford / Steve Spencer Version 1.0 Review Date Date 06/12/2006 Author James Ford Original UK Power Networks 2016 All rights reserved 2 of 8

3 Contents 1 Introduction Scope Details Actions Required... 4 Appendix A Example Diagram Appendix B Example Diagram Appendix C Example Diagram Appendix D Example Diagram UK Power Networks 2016 All rights reserved 3 of 8

4 1 Introduction Throughout the EPN area of UK Power Networks, MW and MVAr transducers have been installed and connected to the SCADA system, however, there was no set convention agreed for the connection of the transducers. This has resulted in the transducers being connected in various different ways which means that it is not possible to accurately tell which direction the power is flowing. This is a particular problem where there is embedded generation connected to the network. In the SPN area of UK Power Networks the transducers have been installed to a standard (the same standard as used by National rid (N)). This standard shall be adopted for use with the EPN transducers. The LPN area also has a standard that differs from SPN and N; however, this will not be changed. 2 Scope The scope of this standard is to detail the site output polarity for the given MW and MVAr value based on the direction of flow of the power and to detail the scale range of the transducers to be used. The convention is to be applied at all voltage levels. This standard does not detail how the MW and MVAr values are to be displayed on ENMAC. 3 Details The MW and MVAr transducers should be set up to show a positive output on site when power is flowing away from busbars or specific reference point and a negative output on site when power is flowing towards the busbars or specific reference point. At circuit mid points such as West March rid, the side of the circuit breaker the transducers are connected to needs to be ascertained so the convention can be applied correctly. With reference to the position of the MW and MVAr transducers, a power flow towards the circuit breaker will show a negative output and a power flow away from the circuit breaker will show a positive output. The ENMAC (UK Power Networks Electrical Network Control System) network diagram will need to indicate which side of the circuit breaker the transducers are connected so the convention can be correctly applied. Alternatively, a symbol incorporating an arrow to display the direction of power flow could possibly be developed in the future. The method of displaying the MW and MVAr value on ENMAC is not covered by this standard. The preference is not to use discrete transducers but where available, to use built in functionality within the protection devices. Depending on local RTU capability, the transducer output shall be connected either via serial communication or via discreet hardwired analogue communication, the former being the preference where possible. The analogue output of these transducers shall have the following scale range: -10 / 0 / +10 ma. For reference, please refer to the example diagrams in Appendix A to Appendix D. 4 Actions Required The output of all new MW and MVAr transducers shall be installed as detailed within this document. Any modifications to the output wiring of existing transducers will be covered by a specific project. The locations of the CTs the transducers are connected to need to be recorded so that the analogue can be correctly placed on the ENMAC diagram. UK Power Networks 2016 All rights reserved 4 of 8

5 Appendix A Example Diagram 1 Reference point for direction convention Primary Substation Direction of power flow Transformer Current Transformer (CT) enerator enerator Substation rid Substation Switching Station UK Power Networks 2016 All rights reserved 5 of 8

6 Appendix B Example Diagram 2 Reference point for direction convention Primary Substation Direction of power flow Transformer Current Transformer (CT) enerator enerator Substation rid Substation Switching Station UK Power Networks 2016 All rights reserved 6 of 8

7 Appendix C Example Diagram 3 Primary Substation Reference point for direction convention Direction of power flow Transformer Current Transformer (CT) enerator rid Substation Switching Station UK Power Networks 2016 All rights reserved 7 of 8

8 Appendix D Example Diagram 4 Reference point for direction convention Direction of power flow Transformer Current Transformer (CT) enerator LV Bar HV Bar UK Power Networks 2016 All rights reserved 8 of 8

EDS SCADA NUMBERING SYSTEM

EDS SCADA NUMBERING SYSTEM Document Number: EDS 05-9007 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 05-9007 SCADA NUMBERING SYSTEM This standard describes the system for numbering SCADA wiring within switchgear

More information

ECP SECONDARY SUBSTATION COMMISSIONING PROCEDURE

ECP SECONDARY SUBSTATION COMMISSIONING PROCEDURE Document Number: ECP 11-0501 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0501 SECONDARY SUBSTATION COMMISSIONING PROCEDURE EPN, LPN, SPN This procedure details the end-to-end process

More information

ECS LUCY GEMINI 3 CONFIGURATION PROCEDURE

ECS LUCY GEMINI 3 CONFIGURATION PROCEDURE Document Number: ECS 05-9541 Network(s): Summary: ENGINEERING CONSTRUCTION STANDARD ECS 05-9541 LUCY GEMINI 3 CONFIGURATION PROCEDURE EPN, LPN, SPN This document details the configuration procedure for

More information

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES Network(s): Summary: ENGINEERING BULLETIN EBB 08-0061 PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES EPN, SPN This bulletin provides a framework for the pilot scheme for unmetered

More information

ECP NORTROLL CABLETROLL 2350 FPI INSTALLATION AND COMMISSIONING PROCEDURE

ECP NORTROLL CABLETROLL 2350 FPI INSTALLATION AND COMMISSIONING PROCEDURE Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0521 NORTROLL CABLETROLL 2350 FPI INSTALLATION AND COMMISSIONING PROCEDURE EPN, LPN, SPN This document details the installation, testing

More information

ECP GPRS/3G/4G COMMS DEVICE CONFIGURATION AND COMMISSIONING PROCEDURE

ECP GPRS/3G/4G COMMS DEVICE CONFIGURATION AND COMMISSIONING PROCEDURE Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0601 GPRS/3G/4G COMMS DEVICE CONFIGURATION AND COMMISSIONING PROCEDURE EPN, LPN, SPN Configuration and commissioning procedure for the GPRS/3G/4G

More information

EOS LUCY GEMINI 3 TYPE E RTU

EOS LUCY GEMINI 3 TYPE E RTU Document Number: EOS 05-9305 Network(s): Summary: ENGINEERING OPERATION STANDARD EPN, LPN, SPN EOS 05-9305 LUCY GEMINI 3 TYPE E RTU This standard details the application, installation and operation of

More information

EOS REMSDAQ CALLISTO NX TYPE E RTU

EOS REMSDAQ CALLISTO NX TYPE E RTU Document Number: EOS 05-9306 Network(s): Summary: ENGINEERING OPERATING STANDARD EOS 05-9306 REMSDAQ CALLISTO NX TYPE E RTU EPN, LPN, SPN This standard details the application, installation and operation

More information

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-0150 LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES LPN This standard provides guidelines for the development of the 33kV distribution

More information

EDS KV, GRID AND PRIMARY SYSTEM PROTECTION AND CONTROL SCHEMES

EDS KV, GRID AND PRIMARY SYSTEM PROTECTION AND CONTROL SCHEMES Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 05-0001 132KV, GRID AND PRIMARY SYSTEM PROTECTION AND CONTROL SCHEMES EPN, LPN, SPN This engineering design standard describes the requirements for

More information

EDS LV CUSTOMER UNMETERED SUPPLIES

EDS LV CUSTOMER UNMETERED SUPPLIES Document Number: EDS 08-2102 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-2102 LV CUSTOMER UNMETERED SUPPLIES EPN, LPN, SPN This standard details the requirements for unmetered single-phase

More information

EOS LUCY SABRE 'A' RANGE SWITCHGEAR

EOS LUCY SABRE 'A' RANGE SWITCHGEAR Document Number: EOS 03-0027 Network(s): Summary: ENGINEERING OPERATION STANDARD EOS 03-0027 LUCY SABRE 'A' RANGE SWITCHGEAR EPN, LPN, SPN This standard details the installation, commissioning and operation

More information

EOS SCHNEIDER RINGMASTER 'C' RANGE SWITCHGEAR

EOS SCHNEIDER RINGMASTER 'C' RANGE SWITCHGEAR Document Number: EOS 03-0018 Network(s): Summary: ENGINEERING OPERATION STANDARD EOS 03-0018 SCHNEIDER RINGMASTER 'C' RANGE SWITCHGEAR EPN, LPN, SPN This standard details the installation, commissioning

More information

MESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS

MESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS Engineering Specification Electrical Networks MESP 081000-01 TECHNICAL SPECIFICATION FOR SCADA CABLING IN Version: 1 Issued: March 2014 Owner: Electrical Networks Asset Manager Approved By: George Marulli

More information

Transmission or Distribution. Phil Collins March 18, 2005

Transmission or Distribution. Phil Collins March 18, 2005 Transmission or Distribution Phil Collins March 18, 2005 CUSC Principles of Ownership Power Station Busbar clamp on busbar side of busbar isolators on generators circuit Distribution System Busbar clamp

More information

REAL-TIME MONITORING DATA SPECIFICATION

REAL-TIME MONITORING DATA SPECIFICATION REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...

More information

Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements

Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Standard Number: HPC-5DA-07-0001-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document

More information

STCP 04-3 Issue 005 Real Time Data Provision

STCP 04-3 Issue 005 Real Time Data Provision STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish

More information

DESIGN PRACTICE NOTE NEGATIVE BUSBAR SHUNTS

DESIGN PRACTICE NOTE NEGATIVE BUSBAR SHUNTS Approval Amendment Record Approval Date Version Description 27/05/2013 1 Initial issue under MTM. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6 Table of Contents

More information

Manual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide

Manual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide Manual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide Standard Number: HPC-5DA-07-0004-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document

More information

Engineering Recommendation G87 Issue

Engineering Recommendation G87 Issue PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation G87 Issue 2-2015 Guidelines for the Provision of Low Voltage Connections to Multiple Occupancy Buildings

More information

Company Directive STANDARD TECHNIQUE: TP18A/1. Application of Connection Control Panels for Soft Intertrip and/or Voltage Constraint Schemes

Company Directive STANDARD TECHNIQUE: TP18A/1. Application of Connection Control Panels for Soft Intertrip and/or Voltage Constraint Schemes Company Directive STANDARD TECHNIQUE: TP18A/1 Application of Connection Control Panels for Soft Intertrip and/or Voltage Constraint Schemes Summary This document provides guidance on the application of

More information

Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY

Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Original Issue: September 2007 Prepared by: Lee Chan & Rob Rogerson This Revision: 0 October 2007 Date For Next Review:

More information

ANCILLARY SERVICES BUSINESS MONITORING

ANCILLARY SERVICES BUSINESS MONITORING ANCILLARY SERVICES BUSINESS MONITORING This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for

More information

ABB Digital medium-voltage switchgear

ABB Digital medium-voltage switchgear NAMIBIA AMEU/AEDU MARCH 2018 ABB Digital medium-voltage switchgear Barry Addinall UniGear Digital Contents 1. Digital switchgear 2. Complexity of Distribution networks 3. New technologies using digital

More information

Distribution Substation Manual (DSM) Section 6: Miscellaneous

Distribution Substation Manual (DSM) Section 6: Miscellaneous Distribution Substation Manual (DSM) Section 6: Miscellaneous Standard Number: HPC-5DA-07-0006-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document Owner Name: Justin

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

Independent Connections Provider (ICP) Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure

Independent Connections Provider (ICP) Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure Independent Connections Provider () Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure Owner Name Title Neil Clarke Head of Highway Services Signature Date 16 August 2018 Authoriser Name

More information

MTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES

MTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES SURGE PROTECTION IN SIGNAL Approval Amendment Record Approval Date Version Description 11/05/2016 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION

More information

Design Guidelines for SCADA & DSA

Design Guidelines for SCADA & DSA Design Guidelines for SCADA & 28 th February 2017 28 FEBRUARY 2017 ISSUE 4 PREPARED BY: PRINCIPAL ENGINEER SCADA & MANAGER AUTHORISED BY: MANAGER SECONDARY SYSTEMS DOCUMENT NUMBER: ISSUE 4 This plan is

More information

EDS GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET NETWORKS (IDNOS AND OTHER LICENSED DNOS)

EDS GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET NETWORKS (IDNOS AND OTHER LICENSED DNOS) THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE ENGINEERING DESIGN STANDARD EDS 08-0113 GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET

More information

Manual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements

Manual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements Manual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements Standard Number: HPC-5DA-07-0005- Document Control Author Name: Viswa Easwaran Position: Standards Engineer

More information

ECS TYPE E RTU AND ANCILLARY ITEMS INSTALLATION PROCEDURE

ECS TYPE E RTU AND ANCILLARY ITEMS INSTALLATION PROCEDURE Document Number: ECS 05-9540 Network(s): Summary: ENGINEERING CONSTRUCTION STANDARD ECS 05-9540 TYPE E AND ANCILLARY ITEMS INSTALLATION PROCEDURE EPN, LPN, SPN This procedure details the installation,

More information

Critical Asset Identification Methodology. William E. McEvoy Northeast Utilities

Critical Asset Identification Methodology. William E. McEvoy Northeast Utilities Critical Asset Identification Methodology William E. McEvoy Northeast Utilities Disclaimer This NPCC TFIST workshop provides a forum for the presentation and discussion of member experience in the implementation

More information

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)] Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected

More information

STCP22-1 Issue 003 Production of Models for GB System Planning

STCP22-1 Issue 003 Production of Models for GB System Planning STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V Version: 1 Issued: March 2014 Owner: Electrical Networks Asset

More information

CAISO RIG Acceptance Test Procedure

CAISO RIG Acceptance Test Procedure CAISO RIG Acceptance Test Procedure TABLE OF CONTENTS 1.0 PURPOSE... 3 2.0 INTRODUCTION... 3 3.0 TEST PROCEDURE... 8 Market Services/ EDAS CAISO Public Revision History 1.0 PURPOSE The procedure is intended

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

SECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE

SECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE SECTION 16262 - APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE PART 1 - GENERAL 1.01 RELATED SECTIONS A. Section 01300 Submittals B. Section 16262 Static Frequency Converter C. Section 16262A Appendix A SFC

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT

TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN >>> TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN Tengiz is one of the largest oil fields in the world, and is located in western

More information

NovaTech Orion I/O Overview

NovaTech Orion I/O Overview NovaTech Orion I/O 2 NOVATECH ORION I/O 3 NovaTech Orion I/O Overview NovaTech Orion I/O is an extension of the family of OrionLX Automation Platforms for substation automation and incorporates the same

More information

Lecture 5 Substation Automation Systems. Course map

Lecture 5 Substation Automation Systems. Course map Lecture 5 Substation Automation Systems 1 Course map 2 1 Contents of the Lecture Part 1 Substation Automation Components Substation Automation Functions Communication within the Substation (Intro) Part

More information

Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control

Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control Welcome to NovaTech Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control Paul Grabowski About the Author Paul Grabowski

More information

Substation Workshop. 7 th February 2018

Substation Workshop. 7 th February 2018 Substation Workshop 7 th February 2018 1 Agenda Welcome and Introductions Antony White Substation Design Overview Andy Moore Question & Answer Session Break 1500kVA Transformers James Devriendt & Andy

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Owner/Operator Forum 12 December

Owner/Operator Forum 12 December Owner/Operator Forum 12 December Steve Halsey DG Development Manager Today s Agenda Transition to DSO Breakout session What we do the role of the DNO Our vision Welcome and Introduction (DNO) Distribution

More information

Sapphire Wind Farm 330/33kV Substation

Sapphire Wind Farm 330/33kV Substation Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire

More information

2 NOVATECH. This page is intentionally left blank.

2 NOVATECH. This page is intentionally left blank. NovaTech Orion I/O 2 NOVATECH This page is intentionally left blank. ORION I/O 3 NovaTech Orion I/O Overview NovaTech Orion I/O is an extension of the family of OrionLX Automation Platforms for substation

More information

T49 - Integration of Power Protection Devices on IEC Protocol to the Automation Control System

T49 - Integration of Power Protection Devices on IEC Protocol to the Automation Control System T49 - Integration of Power Protection Devices on IEC 61850 Protocol to the Automation Control System Copyright 2016 Rockwell Automation, Inc. All Rights Reserved. 1 Agenda Electrical and Process Automation

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

Jim McGhee, Utility Market Manager, RuggedCom Inc.

Jim McGhee, Utility Market Manager, RuggedCom Inc. First Practical Experience with IEEE 1588 High Precision Time Synchronization in High Voltage Substation with IEC 61850 Process Bus Jim McGhee, Utility Market Manager, RuggedCom Inc. (JimMcGhee@RuggedCom.com)

More information

Smart Distribution Technology

Smart Distribution Technology Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications

More information

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662 Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately

More information

Power Xpert Meter 350 (PXM350) three-phased DIN-rail multifunction meter

Power Xpert Meter 350 (PXM350) three-phased DIN-rail multifunction meter Contents Description Page Product overview.... 2 Key features.... 2 Wide voltage range.... 2 Ordering information... 2 Additional features.... 2 functions comparison... 3 Metering.... 4 Specifications....

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Distributed Generation Customer Perspectives. Focus on LV to 33kV Connections sector (PV)

Distributed Generation Customer Perspectives. Focus on LV to 33kV Connections sector (PV) Distributed Generation Customer Perspectives Focus on LV to 33kV Connections sector (PV) James Hoare CEng MIET MEI BRE National Solar Centre -Associate Consultant LHW Partnership LLP - Owner 24 th September

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Recording and Reporting of High Voltage and Low Voltage Switching

Recording and Reporting of High Voltage and Low Voltage Switching 1 SCOPE This document details the procedures to be adopted prior to, during, and on completion of Switching operations, and details the manner in which HV and LV Switching shall be recorded in order to

More information

State Estimation at All India Level

State Estimation at All India Level State Estimation at All India Level Akhil Singhal Harish Kumar Rathour P.K. Agarwal KVS Baba S.K. Soonee Deputy Manager Chief Manager General Manager Executive Director Chief Executive Officer POWER SYSTEM

More information

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

City of London Stakeholder Consultation

City of London Stakeholder Consultation City of London Stakeholder Consultation 15 May 2013 2011. UK Power Networks. All rights reserved Safety and Housekeeping No planned fire alarms Emergency exits Fire assembly points Toilets Mobile phones

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Lecture 6 Substation Automation Systems

Lecture 6 Substation Automation Systems Lecture 6 Substation Automation Systems 1 Course map 2 Contents of the Lecture Part 1 Substation Automation Components & Architectures Substation Automation Functions Communication within the Substation

More information

GAS. POWER. WATER. TELCO. POWER

GAS. POWER. WATER. TELCO. POWER GAS. POWER. WATER. TELCO. POWER Who is Zinfra? Zinfra is a leading power, gas, water and telco infrastructure service provider. We offer a comprehensive range of engineering, construction and maintenance

More information

Energy Meter and. Current Transducer. Assembly Manual

Energy Meter and. Current Transducer. Assembly Manual Energy Meter and Current Transducer Assembly Manual 2017 1 The energy meter assembly is made of two separate boxes and associated accessories, as follows: Energy Meter (EM) Box, with two cables feeding

More information

Progress Report on the GCC Electricity Grid Interconnection in the Middle East

Progress Report on the GCC Electricity Grid Interconnection in the Middle East GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Progress Report on the GCC Electricity Grid Interconnection in the Middle East by: Adnan Al-Mohaisen, GM, GCCIA Luc Chausse, Project Director, SNC-Lavalin

More information

Offshore BMU Configuration

Offshore BMU Configuration BMU Configuration Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Steve Curtis : System Operator

More information

IDM DATA ACQUISITION SYSTEM

IDM DATA ACQUISITION SYSTEM DATA ACQUISITION SYSTEM The a compact and economical multifunction data acquisition system Rendering all Unrivalled product profile Advanced multifunctional distributed data acquisition system Fully multitasking

More information

DISCERN SGAM Visio Template User Guide

DISCERN SGAM Visio Template User Guide Distributed Intelligence for Cost-Effective and Reliable Distribution Network Operation DISCERN SGAM Visio Template User Guide Author: OFFIS Date: 22.04.2016 www.discern.eu The research leading to these

More information

I/A Series HARDWARE Product Specifications

I/A Series HARDWARE Product Specifications I/A Series HARDWARE Product Specifications I/A Series Remote Terminal Unit (RTU) C50 3 Phase Digital Transducer Module FEATURES Simultaneous sampling eliminates skew error Replaces MW, MVAR, MVA, Volts,

More information

Designing a new IEC substation architecture

Designing a new IEC substation architecture Designing a new IEC 61850 substation architecture Gerrit Dogger Senior Product and Application Specialist Cooper Power Systems gerrit.dogger@cybectec.com Garry Tennese Station Integration Specialist Manitoba

More information

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4. Branch Procedure Document No. Issue No. : : CEOP8012 5 Approved By : Specialist Engineering NETWORK : Manager Approval Date Review Date : : 29/06/2018 29/06/2021 (Supersedes CEOP8012, Generation Connection:

More information

EDS HV NETWORK DESIGN

EDS HV NETWORK DESIGN Document Number: EDS 08-3000 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-3000 HV NETWORK DESIGN This standard details the guidelines for the design and development of the 11kV

More information

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017

More information

Recommendation to Board. Final Action

Recommendation to Board. Final Action MOTION NO. M2017-142 Ratification and contract for Tukwila traction power sub-station repairs MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee Board 12/7/2017 12/21//2017

More information

Flexible Urban Networks Low Voltage Successful and safe installation, commissioning and operation of LV switches and circuit breakers on LV networks

Flexible Urban Networks Low Voltage Successful and safe installation, commissioning and operation of LV switches and circuit breakers on LV networks Flexible Urban Networks Low Voltage Successful and safe installation, commissioning and operation of LV switches and circuit breakers on LV networks (SDRC 9.2) Contents Executive Summary... 5 1. Introduction...

More information

Chapter 2 State Estimation and Visualization

Chapter 2 State Estimation and Visualization Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation

More information

Flexible Connections for DG Customers

Flexible Connections for DG Customers Flexible Connections for DG s Session 1b: Connections Paul Pretlove UK Power Networks Ruth Kemsley Wind Prospect In partnership with: Deployment Key outputs REQUIREMENTS Interface specification guidance

More information

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS

More information

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power 1. Abstract Dinesh Mithanthaya Design Manager, Horizon Power Higher capacity substation power transformers ( 5MVA),are

More information

Specification Voltage Limiting Device

Specification Voltage Limiting Device Engineering Specification Electrical Networks L1-CHE-SPE-152 Specification Voltage Limiting Device Version: 1 Issued: 20 th April 2018 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering,

More information

Revision 6.0. Transmission Interconnection Guide

Revision 6.0. Transmission Interconnection Guide Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview

More information

Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India

Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India SCADA in Transmission Line Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India ABSTRACT: Transmission line equivalent circuit parameters are often 25%

More information

MESP MODULAR SUBSTATION USER REQUIREMENTS

MESP MODULAR SUBSTATION USER REQUIREMENTS Engineering Specification Electrical Networks MODULAR SUBSTATION USER Version: 2 Issued: November 2015 Owner: Head of Engineering/Electrical Approved By: Head of Engineering/Electrical PRINTOUT MAY NOT

More information

Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6

Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6 Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6 Version 3 Effective Date 10/17/2017 Approved by: Transmission Maintenance Coordination Committee

More information

Relevant Electrical Standards (RES) Grid Code Review Panel January 2014

Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same

More information

Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly

Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly Specification Electrical Networks L1-CHE-SPE-128 Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly Version: 1 Issued: February 2016 Owner: Head of Engineering - Electrical Approved

More information

SDG&E EPIC Program Overview

SDG&E EPIC Program Overview SDG&E EPIC Program Overview Presented by: Frank Goodman, SDG&E i-pcgrid Workshop March 30, 2018. All copyright and trademark rights reserved. Presentation overview SDG&E overview Project lists for three

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

Distribution Code Review Panel Protection Engineer assessment Working Group. Draft Document for

Distribution Code Review Panel Protection Engineer assessment Working Group. Draft Document for Distribution Code Review Panel Protection Engineer assessment Working Group Draft Document for Procedure for Assessment of Protection Relay Testing Engineers INTRODUCTION Electrical Protection system testing

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

Benefits, offering and references

Benefits, offering and references DOC ID: 9AKK107045A9180 DISTRIBUTION SOLUTIONS Digital medium-voltage switchgear Benefits, offering and references Contents Digital switchgear for medium-voltage applications Digital switchgear definition

More information

1. Project Description

1. Project Description Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal

More information

October 05, ECE 421 Session 12. Utility SCADA and Automation. Presented by: Chris Dyer

October 05, ECE 421 Session 12. Utility SCADA and Automation. Presented by: Chris Dyer ECE 421 Session 12 October 05, 2017 Utility SCADA and Automation Presented by: Chris Dyer Utility SCADA & Automation Chris Dyer, P.E. BSEE University of Idaho, 1997 SCADA & Automation Engineer POWER Engineers,

More information

Digital Substation Overview of Technology, Industry

Digital Substation Overview of Technology, Industry Digital Substation Overview of Technology, Industry Trends and Standardization Efforts 4th International Scientific & Technical Conference Actual Trends in Development of Power System Protection and Automation

More information