EDS MW AND MVAR TRANSDUCER CONNECTION
|
|
- Bryan Hall
- 5 years ago
- Views:
Transcription
1 Document Number: EDS Network(s): Summary: ENINEERIN DESIN STANDARD EDS MW AND MVAR TRANSDUCER CONNECTION EPN, LPN, SPN This standard details the convention to be used when wiring MW and MVAr transducers so that power flow direction can be ascertained. Owner: James Ford Approved By: Paul Williams Approved Date: 13/09/2016 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Applicable To UK Power Networks All UK Power Networks Asset Management Capital Programme Connections HSS&TT Network Operations UK Power Networks Services Other External 81 Website Contractors ICPs/IDNOs Meter Operators THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE
2 Revision Record Version 3.0 Review Date 31/08/2021 Date 31/08/2016 Author James Ford Why has the document been updated Periodic review What has changed - 11kV and LV network added and diagrams within appendices refreshed Version 2.0 Review Date 17/12/2015 Date 12/11/2012 Author Azzam Al-Riyami Document reviewed and minor modification to cater for the preference to have the transducer functions within the protection devices. Version 1.4 Review Date Date 16/07/2012 Author Lee Strachan Document reviewed for publishing on 81 Version 1.3 Review Date Date 25/08/2011 Author Chris Anderson Re-classified from EI to EDS Version 1.2 Review Date Date 16/03/2011 Author Don Fossett Document re-branded Version 1.1 Review Date Date 10/08/2010 Author Reviewed and review date extended James Ford / Steve Spencer Version 1.0 Review Date Date 06/12/2006 Author James Ford Original UK Power Networks 2016 All rights reserved 2 of 8
3 Contents 1 Introduction Scope Details Actions Required... 4 Appendix A Example Diagram Appendix B Example Diagram Appendix C Example Diagram Appendix D Example Diagram UK Power Networks 2016 All rights reserved 3 of 8
4 1 Introduction Throughout the EPN area of UK Power Networks, MW and MVAr transducers have been installed and connected to the SCADA system, however, there was no set convention agreed for the connection of the transducers. This has resulted in the transducers being connected in various different ways which means that it is not possible to accurately tell which direction the power is flowing. This is a particular problem where there is embedded generation connected to the network. In the SPN area of UK Power Networks the transducers have been installed to a standard (the same standard as used by National rid (N)). This standard shall be adopted for use with the EPN transducers. The LPN area also has a standard that differs from SPN and N; however, this will not be changed. 2 Scope The scope of this standard is to detail the site output polarity for the given MW and MVAr value based on the direction of flow of the power and to detail the scale range of the transducers to be used. The convention is to be applied at all voltage levels. This standard does not detail how the MW and MVAr values are to be displayed on ENMAC. 3 Details The MW and MVAr transducers should be set up to show a positive output on site when power is flowing away from busbars or specific reference point and a negative output on site when power is flowing towards the busbars or specific reference point. At circuit mid points such as West March rid, the side of the circuit breaker the transducers are connected to needs to be ascertained so the convention can be applied correctly. With reference to the position of the MW and MVAr transducers, a power flow towards the circuit breaker will show a negative output and a power flow away from the circuit breaker will show a positive output. The ENMAC (UK Power Networks Electrical Network Control System) network diagram will need to indicate which side of the circuit breaker the transducers are connected so the convention can be correctly applied. Alternatively, a symbol incorporating an arrow to display the direction of power flow could possibly be developed in the future. The method of displaying the MW and MVAr value on ENMAC is not covered by this standard. The preference is not to use discrete transducers but where available, to use built in functionality within the protection devices. Depending on local RTU capability, the transducer output shall be connected either via serial communication or via discreet hardwired analogue communication, the former being the preference where possible. The analogue output of these transducers shall have the following scale range: -10 / 0 / +10 ma. For reference, please refer to the example diagrams in Appendix A to Appendix D. 4 Actions Required The output of all new MW and MVAr transducers shall be installed as detailed within this document. Any modifications to the output wiring of existing transducers will be covered by a specific project. The locations of the CTs the transducers are connected to need to be recorded so that the analogue can be correctly placed on the ENMAC diagram. UK Power Networks 2016 All rights reserved 4 of 8
5 Appendix A Example Diagram 1 Reference point for direction convention Primary Substation Direction of power flow Transformer Current Transformer (CT) enerator enerator Substation rid Substation Switching Station UK Power Networks 2016 All rights reserved 5 of 8
6 Appendix B Example Diagram 2 Reference point for direction convention Primary Substation Direction of power flow Transformer Current Transformer (CT) enerator enerator Substation rid Substation Switching Station UK Power Networks 2016 All rights reserved 6 of 8
7 Appendix C Example Diagram 3 Primary Substation Reference point for direction convention Direction of power flow Transformer Current Transformer (CT) enerator rid Substation Switching Station UK Power Networks 2016 All rights reserved 7 of 8
8 Appendix D Example Diagram 4 Reference point for direction convention Direction of power flow Transformer Current Transformer (CT) enerator LV Bar HV Bar UK Power Networks 2016 All rights reserved 8 of 8
EDS SCADA NUMBERING SYSTEM
Document Number: EDS 05-9007 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 05-9007 SCADA NUMBERING SYSTEM This standard describes the system for numbering SCADA wiring within switchgear
More informationECP SECONDARY SUBSTATION COMMISSIONING PROCEDURE
Document Number: ECP 11-0501 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0501 SECONDARY SUBSTATION COMMISSIONING PROCEDURE EPN, LPN, SPN This procedure details the end-to-end process
More informationECS LUCY GEMINI 3 CONFIGURATION PROCEDURE
Document Number: ECS 05-9541 Network(s): Summary: ENGINEERING CONSTRUCTION STANDARD ECS 05-9541 LUCY GEMINI 3 CONFIGURATION PROCEDURE EPN, LPN, SPN This document details the configuration procedure for
More informationEBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES
Network(s): Summary: ENGINEERING BULLETIN EBB 08-0061 PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES EPN, SPN This bulletin provides a framework for the pilot scheme for unmetered
More informationECP NORTROLL CABLETROLL 2350 FPI INSTALLATION AND COMMISSIONING PROCEDURE
Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0521 NORTROLL CABLETROLL 2350 FPI INSTALLATION AND COMMISSIONING PROCEDURE EPN, LPN, SPN This document details the installation, testing
More informationECP GPRS/3G/4G COMMS DEVICE CONFIGURATION AND COMMISSIONING PROCEDURE
Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0601 GPRS/3G/4G COMMS DEVICE CONFIGURATION AND COMMISSIONING PROCEDURE EPN, LPN, SPN Configuration and commissioning procedure for the GPRS/3G/4G
More informationEOS LUCY GEMINI 3 TYPE E RTU
Document Number: EOS 05-9305 Network(s): Summary: ENGINEERING OPERATION STANDARD EPN, LPN, SPN EOS 05-9305 LUCY GEMINI 3 TYPE E RTU This standard details the application, installation and operation of
More informationEOS REMSDAQ CALLISTO NX TYPE E RTU
Document Number: EOS 05-9306 Network(s): Summary: ENGINEERING OPERATING STANDARD EOS 05-9306 REMSDAQ CALLISTO NX TYPE E RTU EPN, LPN, SPN This standard details the application, installation and operation
More informationEDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES
Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-0150 LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES LPN This standard provides guidelines for the development of the 33kV distribution
More informationEDS KV, GRID AND PRIMARY SYSTEM PROTECTION AND CONTROL SCHEMES
Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 05-0001 132KV, GRID AND PRIMARY SYSTEM PROTECTION AND CONTROL SCHEMES EPN, LPN, SPN This engineering design standard describes the requirements for
More informationEDS LV CUSTOMER UNMETERED SUPPLIES
Document Number: EDS 08-2102 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-2102 LV CUSTOMER UNMETERED SUPPLIES EPN, LPN, SPN This standard details the requirements for unmetered single-phase
More informationEOS LUCY SABRE 'A' RANGE SWITCHGEAR
Document Number: EOS 03-0027 Network(s): Summary: ENGINEERING OPERATION STANDARD EOS 03-0027 LUCY SABRE 'A' RANGE SWITCHGEAR EPN, LPN, SPN This standard details the installation, commissioning and operation
More informationEOS SCHNEIDER RINGMASTER 'C' RANGE SWITCHGEAR
Document Number: EOS 03-0018 Network(s): Summary: ENGINEERING OPERATION STANDARD EOS 03-0018 SCHNEIDER RINGMASTER 'C' RANGE SWITCHGEAR EPN, LPN, SPN This standard details the installation, commissioning
More informationMESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS
Engineering Specification Electrical Networks MESP 081000-01 TECHNICAL SPECIFICATION FOR SCADA CABLING IN Version: 1 Issued: March 2014 Owner: Electrical Networks Asset Manager Approved By: George Marulli
More informationTransmission or Distribution. Phil Collins March 18, 2005
Transmission or Distribution Phil Collins March 18, 2005 CUSC Principles of Ownership Power Station Busbar clamp on busbar side of busbar isolators on generators circuit Distribution System Busbar clamp
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationManual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements
Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Standard Number: HPC-5DA-07-0001-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document
More informationSTCP 04-3 Issue 005 Real Time Data Provision
STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationDESIGN PRACTICE NOTE NEGATIVE BUSBAR SHUNTS
Approval Amendment Record Approval Date Version Description 27/05/2013 1 Initial issue under MTM. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6 Table of Contents
More informationManual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide
Manual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide Standard Number: HPC-5DA-07-0004-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document
More informationEngineering Recommendation G87 Issue
PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation G87 Issue 2-2015 Guidelines for the Provision of Low Voltage Connections to Multiple Occupancy Buildings
More informationCompany Directive STANDARD TECHNIQUE: TP18A/1. Application of Connection Control Panels for Soft Intertrip and/or Voltage Constraint Schemes
Company Directive STANDARD TECHNIQUE: TP18A/1 Application of Connection Control Panels for Soft Intertrip and/or Voltage Constraint Schemes Summary This document provides guidance on the application of
More informationNetwork Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY
Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Original Issue: September 2007 Prepared by: Lee Chan & Rob Rogerson This Revision: 0 October 2007 Date For Next Review:
More informationANCILLARY SERVICES BUSINESS MONITORING
ANCILLARY SERVICES BUSINESS MONITORING This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for
More informationABB Digital medium-voltage switchgear
NAMIBIA AMEU/AEDU MARCH 2018 ABB Digital medium-voltage switchgear Barry Addinall UniGear Digital Contents 1. Digital switchgear 2. Complexity of Distribution networks 3. New technologies using digital
More informationDistribution Substation Manual (DSM) Section 6: Miscellaneous
Distribution Substation Manual (DSM) Section 6: Miscellaneous Standard Number: HPC-5DA-07-0006-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document Owner Name: Justin
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationIndependent Connections Provider (ICP) Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure
Independent Connections Provider () Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure Owner Name Title Neil Clarke Head of Highway Services Signature Date 16 August 2018 Authoriser Name
More informationMTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES
SURGE PROTECTION IN SIGNAL Approval Amendment Record Approval Date Version Description 11/05/2016 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION
More informationDesign Guidelines for SCADA & DSA
Design Guidelines for SCADA & 28 th February 2017 28 FEBRUARY 2017 ISSUE 4 PREPARED BY: PRINCIPAL ENGINEER SCADA & MANAGER AUTHORISED BY: MANAGER SECONDARY SYSTEMS DOCUMENT NUMBER: ISSUE 4 This plan is
More informationEDS GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET NETWORKS (IDNOS AND OTHER LICENSED DNOS)
THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE ENGINEERING DESIGN STANDARD EDS 08-0113 GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET
More informationManual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements
Manual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements Standard Number: HPC-5DA-07-0005- Document Control Author Name: Viswa Easwaran Position: Standards Engineer
More informationECS TYPE E RTU AND ANCILLARY ITEMS INSTALLATION PROCEDURE
Document Number: ECS 05-9540 Network(s): Summary: ENGINEERING CONSTRUCTION STANDARD ECS 05-9540 TYPE E AND ANCILLARY ITEMS INSTALLATION PROCEDURE EPN, LPN, SPN This procedure details the installation,
More informationCritical Asset Identification Methodology. William E. McEvoy Northeast Utilities
Critical Asset Identification Methodology William E. McEvoy Northeast Utilities Disclaimer This NPCC TFIST workshop provides a forum for the presentation and discussion of member experience in the implementation
More informationCONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]
Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected
More informationSTCP22-1 Issue 003 Production of Models for GB System Planning
STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationMESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM
Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V Version: 1 Issued: March 2014 Owner: Electrical Networks Asset
More informationCAISO RIG Acceptance Test Procedure
CAISO RIG Acceptance Test Procedure TABLE OF CONTENTS 1.0 PURPOSE... 3 2.0 INTRODUCTION... 3 3.0 TEST PROCEDURE... 8 Market Services/ EDAS CAISO Public Revision History 1.0 PURPOSE The procedure is intended
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationSECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE
SECTION 16262 - APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE PART 1 - GENERAL 1.01 RELATED SECTIONS A. Section 01300 Submittals B. Section 16262 Static Frequency Converter C. Section 16262A Appendix A SFC
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationTENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT
TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN >>> TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN Tengiz is one of the largest oil fields in the world, and is located in western
More informationNovaTech Orion I/O Overview
NovaTech Orion I/O 2 NOVATECH ORION I/O 3 NovaTech Orion I/O Overview NovaTech Orion I/O is an extension of the family of OrionLX Automation Platforms for substation automation and incorporates the same
More informationLecture 5 Substation Automation Systems. Course map
Lecture 5 Substation Automation Systems 1 Course map 2 1 Contents of the Lecture Part 1 Substation Automation Components Substation Automation Functions Communication within the Substation (Intro) Part
More informationAutomate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control
Welcome to NovaTech Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control Paul Grabowski About the Author Paul Grabowski
More informationSubstation Workshop. 7 th February 2018
Substation Workshop 7 th February 2018 1 Agenda Welcome and Introductions Antony White Substation Design Overview Andy Moore Question & Answer Session Break 1500kVA Transformers James Devriendt & Andy
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationOwner/Operator Forum 12 December
Owner/Operator Forum 12 December Steve Halsey DG Development Manager Today s Agenda Transition to DSO Breakout session What we do the role of the DNO Our vision Welcome and Introduction (DNO) Distribution
More informationSapphire Wind Farm 330/33kV Substation
Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire
More information2 NOVATECH. This page is intentionally left blank.
NovaTech Orion I/O 2 NOVATECH This page is intentionally left blank. ORION I/O 3 NovaTech Orion I/O Overview NovaTech Orion I/O is an extension of the family of OrionLX Automation Platforms for substation
More informationT49 - Integration of Power Protection Devices on IEC Protocol to the Automation Control System
T49 - Integration of Power Protection Devices on IEC 61850 Protocol to the Automation Control System Copyright 2016 Rockwell Automation, Inc. All Rights Reserved. 1 Agenda Electrical and Process Automation
More informationGeneration, Transmission, and End User Facilities
Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3
More informationJim McGhee, Utility Market Manager, RuggedCom Inc.
First Practical Experience with IEEE 1588 High Precision Time Synchronization in High Voltage Substation with IEC 61850 Process Bus Jim McGhee, Utility Market Manager, RuggedCom Inc. (JimMcGhee@RuggedCom.com)
More informationSmart Distribution Technology
Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications
More informationSmall Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662
Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately
More informationPower Xpert Meter 350 (PXM350) three-phased DIN-rail multifunction meter
Contents Description Page Product overview.... 2 Key features.... 2 Wide voltage range.... 2 Ordering information... 2 Additional features.... 2 functions comparison... 3 Metering.... 4 Specifications....
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationDistributed Generation Customer Perspectives. Focus on LV to 33kV Connections sector (PV)
Distributed Generation Customer Perspectives Focus on LV to 33kV Connections sector (PV) James Hoare CEng MIET MEI BRE National Solar Centre -Associate Consultant LHW Partnership LLP - Owner 24 th September
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationRecording and Reporting of High Voltage and Low Voltage Switching
1 SCOPE This document details the procedures to be adopted prior to, during, and on completion of Switching operations, and details the manner in which HV and LV Switching shall be recorded in order to
More informationState Estimation at All India Level
State Estimation at All India Level Akhil Singhal Harish Kumar Rathour P.K. Agarwal KVS Baba S.K. Soonee Deputy Manager Chief Manager General Manager Executive Director Chief Executive Officer POWER SYSTEM
More informationTitle System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)
Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards
More informationCity of London Stakeholder Consultation
City of London Stakeholder Consultation 15 May 2013 2011. UK Power Networks. All rights reserved Safety and Housekeeping No planned fire alarms Emergency exits Fire assembly points Toilets Mobile phones
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationLecture 6 Substation Automation Systems
Lecture 6 Substation Automation Systems 1 Course map 2 Contents of the Lecture Part 1 Substation Automation Components & Architectures Substation Automation Functions Communication within the Substation
More informationGAS. POWER. WATER. TELCO. POWER
GAS. POWER. WATER. TELCO. POWER Who is Zinfra? Zinfra is a leading power, gas, water and telco infrastructure service provider. We offer a comprehensive range of engineering, construction and maintenance
More informationEnergy Meter and. Current Transducer. Assembly Manual
Energy Meter and Current Transducer Assembly Manual 2017 1 The energy meter assembly is made of two separate boxes and associated accessories, as follows: Energy Meter (EM) Box, with two cables feeding
More informationProgress Report on the GCC Electricity Grid Interconnection in the Middle East
GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Progress Report on the GCC Electricity Grid Interconnection in the Middle East by: Adnan Al-Mohaisen, GM, GCCIA Luc Chausse, Project Director, SNC-Lavalin
More informationOffshore BMU Configuration
BMU Configuration Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Steve Curtis : System Operator
More informationIDM DATA ACQUISITION SYSTEM
DATA ACQUISITION SYSTEM The a compact and economical multifunction data acquisition system Rendering all Unrivalled product profile Advanced multifunctional distributed data acquisition system Fully multitasking
More informationDISCERN SGAM Visio Template User Guide
Distributed Intelligence for Cost-Effective and Reliable Distribution Network Operation DISCERN SGAM Visio Template User Guide Author: OFFIS Date: 22.04.2016 www.discern.eu The research leading to these
More informationI/A Series HARDWARE Product Specifications
I/A Series HARDWARE Product Specifications I/A Series Remote Terminal Unit (RTU) C50 3 Phase Digital Transducer Module FEATURES Simultaneous sampling eliminates skew error Replaces MW, MVAR, MVA, Volts,
More informationDesigning a new IEC substation architecture
Designing a new IEC 61850 substation architecture Gerrit Dogger Senior Product and Application Specialist Cooper Power Systems gerrit.dogger@cybectec.com Garry Tennese Station Integration Specialist Manitoba
More informationBranch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.
Branch Procedure Document No. Issue No. : : CEOP8012 5 Approved By : Specialist Engineering NETWORK : Manager Approval Date Review Date : : 29/06/2018 29/06/2021 (Supersedes CEOP8012, Generation Connection:
More informationEDS HV NETWORK DESIGN
Document Number: EDS 08-3000 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-3000 HV NETWORK DESIGN This standard details the guidelines for the design and development of the 11kV
More informationITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems
ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017
More informationRecommendation to Board. Final Action
MOTION NO. M2017-142 Ratification and contract for Tukwila traction power sub-station repairs MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee Board 12/7/2017 12/21//2017
More informationFlexible Urban Networks Low Voltage Successful and safe installation, commissioning and operation of LV switches and circuit breakers on LV networks
Flexible Urban Networks Low Voltage Successful and safe installation, commissioning and operation of LV switches and circuit breakers on LV networks (SDRC 9.2) Contents Executive Summary... 5 1. Introduction...
More informationChapter 2 State Estimation and Visualization
Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation
More informationFlexible Connections for DG Customers
Flexible Connections for DG s Session 1b: Connections Paul Pretlove UK Power Networks Ruth Kemsley Wind Prospect In partnership with: Deployment Key outputs REQUIREMENTS Interface specification guidance
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationSession Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers
Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power 1. Abstract Dinesh Mithanthaya Design Manager, Horizon Power Higher capacity substation power transformers ( 5MVA),are
More informationSpecification Voltage Limiting Device
Engineering Specification Electrical Networks L1-CHE-SPE-152 Specification Voltage Limiting Device Version: 1 Issued: 20 th April 2018 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering,
More informationRevision 6.0. Transmission Interconnection Guide
Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview
More informationShabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India
SCADA in Transmission Line Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India ABSTRACT: Transmission line equivalent circuit parameters are often 25%
More informationMESP MODULAR SUBSTATION USER REQUIREMENTS
Engineering Specification Electrical Networks MODULAR SUBSTATION USER Version: 2 Issued: November 2015 Owner: Head of Engineering/Electrical Approved By: Head of Engineering/Electrical PRINTOUT MAY NOT
More informationSupervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6
Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6 Version 3 Effective Date 10/17/2017 Approved by: Transmission Maintenance Coordination Committee
More informationRelevant Electrical Standards (RES) Grid Code Review Panel January 2014
Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same
More informationRemotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly
Specification Electrical Networks L1-CHE-SPE-128 Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly Version: 1 Issued: February 2016 Owner: Head of Engineering - Electrical Approved
More informationSDG&E EPIC Program Overview
SDG&E EPIC Program Overview Presented by: Frank Goodman, SDG&E i-pcgrid Workshop March 30, 2018. All copyright and trademark rights reserved. Presentation overview SDG&E overview Project lists for three
More informationJanuary 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.
California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California
More informationDistribution Code Review Panel Protection Engineer assessment Working Group. Draft Document for
Distribution Code Review Panel Protection Engineer assessment Working Group Draft Document for Procedure for Assessment of Protection Relay Testing Engineers INTRODUCTION Electrical Protection system testing
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution
More informationUnofficial Comment Form Project Disturbance Monitoring
Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request
More informationBenefits, offering and references
DOC ID: 9AKK107045A9180 DISTRIBUTION SOLUTIONS Digital medium-voltage switchgear Benefits, offering and references Contents Digital switchgear for medium-voltage applications Digital switchgear definition
More information1. Project Description
Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal
More informationOctober 05, ECE 421 Session 12. Utility SCADA and Automation. Presented by: Chris Dyer
ECE 421 Session 12 October 05, 2017 Utility SCADA and Automation Presented by: Chris Dyer Utility SCADA & Automation Chris Dyer, P.E. BSEE University of Idaho, 1997 SCADA & Automation Engineer POWER Engineers,
More informationDigital Substation Overview of Technology, Industry
Digital Substation Overview of Technology, Industry Trends and Standardization Efforts 4th International Scientific & Technical Conference Actual Trends in Development of Power System Protection and Automation
More information