MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007

Size: px
Start display at page:

Download "MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007"

Transcription

1 MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007 Report submitted to NERC on: July 12, This report is submitted in accordance with the NERC Transmission Loading Relief (TLR) Investigation Procedure for the TLR events that occurred on Flowgate June 11, The MISO systems detected high post-contingent flows on Wisdom-Triboji 161kV line for loss of (flo) the Sherco #3 unit. This event resulted in curtailment of firm transmission service and a reduction obligation (or requirement) due to Network/Native Load (NNL) impacts. 1. Description of purpose/cause of hold/curtailment: The definition of flowgate is listed below. Monitored Facility: Wisdom-Triboji 161kV Contingent Facility: Sherco #3 2. Facility/Flow gate limitations and flow at the time the TLR was initiated: Flowgate measures and captures the flow on the Wisdom-Triboji 161kV line for the loss of the Sherco #3 unit. The Wisdom-Triboji 161kV line is limited by 223 MVA thermal emergency rating. On June 11, 2007, heavy south to north power transfer through Iowa caused an increased flow in Wisdom-Triboji 161kV line for the loss of Sherco #3 unit. At 11:00 EST, the calculated post contingency flow on Wisdom-Triboji 161kV line for the loss of Sherco #3 unit reached 229 MVA. The MISO RC initiated internal MISO market redispatch as well as committed MISO market generation to reduce the post contingency flow in the flowgate. At 15:15 EST, the calculated post contingency flow on Wisdom-Triboji 161kV line for the loss of Sherco #3 unit reached 249 MVA. At this point, NERC IDC showed there was not sufficient non-firm scheduled on FG14266 and TLR 5B was issued at 15:20 EST for FG to be effective across 15:30 EST. At this time the MISO RC contacted MEC to assist them in finding a generation pairing to fulfill their NNL obligation as prescribed by the NERC IDC. MEC decided to curtail a transaction with WAPA that would result in the proper amount of relief for their NNL obligation. As the NERC IDC showed the insufficiency of non-firm schedule curtailment to relieve flow, TLR 5 was issued for a total of three continuous issuances. The TLR was reduced to level 3A x 18:00 EST and was terminated at 20:00 EST when flows decreased to acceptable levels. Page 1 of 5

2 3. TLR Level 5 issuance information, timing (EST), firm tag and NNL reduction information obtained for flowgate #14266 June 11, 2007: TLR LEVEL TIME (EST) 5B 15:30 5A 16:00 Firm Transaction / Curtailment Information 3 tags of (7-F) = 3 MW schedules curtailed to provide.2 MW relief MISO Market responsibility = 43.3 MW 4 tags of (7-F) = 19 MW schedules curtailed to provide 1.4 MW relief MISO Market responsibility = 46.4 MW 5A 17:00 MISO Market responsibility =.7 MW None 3A 18:00 All firm schedule and NNL were reloaded 0 20:00 NNL Reduction Requirement MEC 6.6 MEC 8.8 NNL Mitigation: MEC NNL obligation was met by curtailing a schedule with WAPA which increased Oahe and decreased the output of the Wisdom CT. MISO Market responsibility was met by internally committing and dispatching market generation via the AREVA UDS dispatch tool. 4. Transmission and generation outage or changes from prediction that may have contributed: Significant Transmission Outages: Raun-Lakefield 345kV line Planned outage Elk-Brewster 161 kv - Planned outage Pomeroy-NW Fort Dodge 161 kv - Planned outage Significant Generator Outages in the Region: King = 585 MW Boswell 4 = 580 MW Leland Olds 1 = 222 MW Square Butte 2 = 455 MW Coal Creek 1 = 550 MW Mankato 2 = 182 MW Faribault 1 = 160 MW Total Generation off = 2734 MW System Condition Summary: Heavy south-to-north power transfer across northwest Iowa occurred due to the outages as above and high load to the north. The heavy south-to-north power flows increased the post contingent loading in Wisdom-Triboji 161kV line. Page 2 of 5

3 It should be noted that MISO next day analysis did not show this violation originally, however the subsequent rerun following the Boswell 4 forced outage did show this constraint loaded to 106%. The Coal Creek emergency outage started at 14:05 EST, this was not included in either study. 5. Procedures implemented prior to hold/curtailment: MISO Market redispatch was implemented prior to the TLR event. 6. Compare Complete Transaction Curtailment List with the Whole Transaction List as generated by the IDC, before and after curtailments: Firm transactions impacting the flow gate by 5% or greater were curtailed. 7. Known Transactions not in the IDC and actions taken: There were no known transactions not in the IDC at the time this TLR was in effect that were impacting this flow gate. 8. RCIS or other system messages: Information was provided to NERC Reliability Coordinators via the NERC IDC. The IDC automatically sends TLR Level information to the RCIS. Curtailment information was communicated to the MISO control areas via the MISO MCN and ICCS messaging systems. 9. State estimator snapshots and security analysis including contingency analysis or stability analysis along with any other recorded data indicating the need for TLR: Real-time security analysis was monitored by the System Operator at the ATC control center and by the Reliability Coordinator at the MISO West Reliability Center. TLR relief requirements were calculated by using the real-time security analysis tool, and by monitoring the real-time loading on the monitored element. 10. ATC Limitations before, during, and after the event: There were no ATC limitations for this event. 11. Description of actions taken to avoid future hold/curtailments: The MISO RC followed the direction given in the special operating guide for the Raun- Lakefield 345kV planned outage which identified this constraint. 12. Re-dispatch actions taken: This was a thermal overload. Re-dispatch procedures were used in addition to mitigate NNL responsibility as prescribed by the NERC TLR procedure. 13. If Firm transaction curtailments took place, description of Transactional Contribution Factor calculation and results as well as how necessary relief was obtained through network service and native load contributions: MEC NNL obligation was met by curtailing a transaction from their Wisdom CT to Oahe in WAPA. Page 3 of 5

4 Non-Market Balancing Authority actions to mitigate the NNL requirements: EST CA IDC NNL INC (MW) DEC (MW) GSF % Actual NNL Response MEC 6.6 WAPA - Oahe Wisdom MW Non-Market Balancing Authority actions to mitigate the NNL requirements: EST CA IDC NNL INC (MW) DEC (MW) GSF % Actual NNL Response MEC 8.8 WAPA - Oahe Wisdom MW 14. Other options considered before/during to avoid hold/curtailment: The MISO Reliability Coordinator brought on line all available quick start units in the MISO market and re-dispatched market generation for this constraint. The following units were called on line to relieve loading: Lime Creek CT 1 Lime Creek CT 2 Pleasant Valley CT 1 Pleasant Valley CT 2 Pleasant Valley CT 3 Anson CT 2 Lakefield CT 2 Lakefield CT 3 Lakefield CT 4 Lakefield CT 5 Lakefield CT 6 Cambridge CT Inver Hills CT 1 Inver Hills CT 2 Inver Hills CT 3 Inver Hills CT 4 Inver Hills CT 5 Inver Hills CT 6 Page 4 of 5

5 15. The following chart identifies the flowgate loading for the TLR level 5 event: Wisdom-Triboji 161kV flo Sherco #3 on June 11, MW :32:23 10:20:06 11:19:46 12:31:05 13:17:07 14:02:23 14:50:20 15:40:15 16:34:04 17:33:20 Time (EST) RTCA Flow Emergency Limit 16. Lessons Learned In summary, the combination of planned outages, the forced outages of Boswell 4 and Coal Creek 1 caused significant stress to the Wisdom-Triboji 161kV line. The MISO RC did have an agreed upon plan with MEC and CBPC to take the Wisdom CT off line in the event of the Sherco #3 trip. This along with the curtailments and re-dispatch would relieve the loading on the Wisdom-Triboji 161kV line in the event of the contingency. This is shown on the graph with the post contingent flows dropping as the Wisdom CT started down between 15:00 EST and 16:00 EST, coming off line at 1800 EST. Page 5 of 5

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements. MISO Investigation Report on the NERC TLR Level 5 Event North Platte Stockville 115kV for the loss of the Gentleman Red Willow 345kV Flowgate 6023 August 22 nd / 23 rd, 2002 Report issued: September 3

More information

LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL. September 2001

LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL. September 2001 LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL September 2001 TABLE OF CONTENTS INTRODUCTION...3 SECTION A: GENERATION SHIFT FACTORS...4 SECTION B: COMMUNICATIONS PROTOCOLS...ERROR! BOOKMARK NOT DEFINED.

More information

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September 23, 2009 TABLE OF CONTENTS INTRODUCTION A. RESPONSIBILITIES

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Terry Williams Tennessee Valley Authority

Terry Williams Tennessee Valley Authority Knox - Douglas 161 (FLO) E Knox - Dumplin Valley 161 exceedance Presentation 1 Use of Proxy Flowgate for Exceedance to: Knox - Douglas 161kV (FLO) E Knox - Dumplin Valley 161kV line 9/29/2015 Terry Williams

More information

Getting Effective Transmission Built on the SPP-MISO Seam. MISO-SPP IPSAC Meeting March 2016

Getting Effective Transmission Built on the SPP-MISO Seam. MISO-SPP IPSAC Meeting March 2016 Getting Effective Transmission Built on the SPP-MISO Seam MISO-SPP IPSAC Meeting March 2016 1 General Information MISO and SPP have roughly over 60 interconnections most at lower voltage (less than 345kV).

More information

MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO

MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO 1 MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO 2 MISO Overview MISO is an independent, non-profit, memberbased organization committed to reliability. We serve as

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures.

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval. Introduction 1. Title: IROL and SOL Mitigation in the ERCOT Region 2. Number: IRO-006-TRE-1 3. Purpose: To provide and execute transmission loading relief procedures that can be used to mitigate SOL or

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Enhanced Curtailment Calculator Update

Enhanced Curtailment Calculator Update Enhanced Curtailment Calculator Update December 13, 2017 Member Advisory Committee Meeting Brett Wangen Chief Engineering and Technology Officer Jeremy West Manager, Interconnection Reliability Initiatives

More information

Wide Area Measurements & Control Systems

Wide Area Measurements & Control Systems The 8 th Electric Power Control Centers Workshop June 5-8, 2005, Les Diablerets, Switzerland Wide Area Measurements & Control Systems NERC Security Coordinators and Interregional Security Network Nodes

More information

2016 Fall ITO Stakeholder Meeting. Topics in Operations

2016 Fall ITO Stakeholder Meeting. Topics in Operations 2016 Fall ITO Stakeholder Meeting Topics in Operations 11/17/2016 TOP-003-3 Requirement R1. Each Transmission Operator shall maintain a documented specification for the data necessary for it to perform

More information

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor May 10, 2017 ISAS Salt Lake City, UT WECC Standard TOP 007 WECC 1a Title: System Operating Limits Purpose: To limit instances where

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support TOP/IRO Standards RC Users Group January 21, 2016 Vic Howell Manager, Operations Engineering Support Saad Malik Manager, Real-Time Operations Engineering New/Revised TOP & IRO Standards November 19, 2015,

More information

Bulk Electric System Definition Changes and Reporting

Bulk Electric System Definition Changes and Reporting Bulk Electric System Definition Changes and Reporting June 12, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Overview BES Definition Change BES Definition Reference

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL

N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL Michehl R. Gent President and CEO N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL Princeton Forrestal Village, 116-390 Village Boulevard, Princeton, New Jersey 08540-5731 The Honorable Patrick H. Wood III,

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Coordinate Interchange

Coordinate Interchange Coordinate Interchange Purpose: The purpose of this standard is to define procedures for market participants to request the implementation of Interchange Transactions. Applicability: This Standard applies

More information

Coordinate Interchange

Coordinate Interchange Coordinate Interchange Purpose: The purpose of this standard is to define procedures for market participants to request the implementation of Interchange Transactions. Applicability: This Standard applies

More information

WECC Path Concept White Paper

WECC Path Concept White Paper Document name Category WECC Path Concept White Paper ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Regional Business Practice ( ) Policy ( ) Guideline (X) Report or other ( ) Charter Document

More information

Unused Generation Capacity Study Scope. Informational Analysis

Unused Generation Capacity Study Scope. Informational Analysis Unused Generation Capacity Study Scope Informational Analysis MISO Jan 9, 2014 Table of Contents 1.0 Project Overview... 3 2.0 Scope of Work... 4 2.1 Phase 1 - Preliminary Analysis... 5 2.2 Phase 2 System

More information

WIND ENERGY, CONGESTION MANAGEMENT, AND TRANSMISSION RIGHTS ISSUE DESCRIPTION/PROBLEM STATEMENT. August Issue Brief

WIND ENERGY, CONGESTION MANAGEMENT, AND TRANSMISSION RIGHTS ISSUE DESCRIPTION/PROBLEM STATEMENT. August Issue Brief ND ENERGY, CONGESON MANAGEMEN, AND RANSMSSON RGHS ssue Brief SSUE DESCRPON/PROBLEM SAEMEN ransmission congestion occurs when more power is scheduled or flows across transmission lines than the physical

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Year Assessment Preliminary Needs

Year Assessment Preliminary Needs 2018 10-Year Assessment Preliminary Needs Stakeholder and Customer Presentation March 1, 2018 Jeremy Voigt Purpose Key Study Assumptions Reminder Summarize Preliminary Changes to Needs Solicit Input on

More information

Peak Reliability Coordination Services in the West March 30, 2018

Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability, 2018. 1 Peak Reliability Coordination Services in the West Peak s fundamental mission is to enhance and promote the reliability

More information

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 Mark Buchholz WAPA Upper Great Plains Region Compliance Manager What is Western? One of four Power Marketing Administration within

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

MOD Transmission Reliability Margin Implementation Document

MOD Transmission Reliability Margin Implementation Document Transmission Margin Implementation Document Transmission Margin Implementation Document For NERC Page 1 of 7 Transmission Margin Implementation Document 1.0 Purpose The California Independent System Operator

More information

Cherrywood Circuit Breaker Incident - December 12, 2005

Cherrywood Circuit Breaker Incident - December 12, 2005 Public IESO_REP_0316 Cherrywood Circuit Breaker Incident - December 12, 2005 Public IESO_REP_0316 Document ID IESO_REP_0316 Document Name Cherrywood Circuit Breaker Incident - December 12, 2005 Issue Issue

More information

Available Transfer Capability Definitions and Determination

Available Transfer Capability Definitions and Determination Available Transfer Capability Definitions and Determination A framework for determining available transfer capabilities of the interconnected transmission networks for a commercially viable electricity

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way California Independent System Operator October 30, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

Seams Management at the RTO level

Seams Management at the RTO level Seams Management at the RTO level IEEE Winter Meeting January 29, 2002 New York, NY Mike Gahagan V. P., CIO and Chief Strategic Officer The Midwest Independent Transmission System Operator, Inc. A Brief

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

November 9, Revisions to the Violation Risk Factors for Reliability Standards IRO and TOP

November 9, Revisions to the Violation Risk Factors for Reliability Standards IRO and TOP !! November 9, 2016 VIA ELECTRONIC FILING Jim Crone Director, Energy Division Manitoba Innovation, Energy and Mines 1200-155 Carlton Street Winnipeg MB R3C 3H8 RE: Revisions to the Violation Risk Factors

More information

Open Access Transmission Tariff of Southern Companies

Open Access Transmission Tariff of Southern Companies Open Access Transmission Tariff of Southern Companies Procedures for Reserving Transmission Capacity for Future Load Growth, Designating/Undesignating Network Resources, and Arranging for Other Related

More information

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision Table of Contents I. Purpose... 2 II. Introduction... 2 III. Peak Roles and Responsibilities... 2 IV. Applicability and Obligations... 3 V. Questions and Comments... 6 VI. Data Request Spreadsheet... 6

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

Operating Reliability Subcommittee Presentations. February 10-11, 2015

Operating Reliability Subcommittee Presentations. February 10-11, 2015 Operating Reliability Subcommittee Presentations February 10-11, 2015 Presentation 1 ORS February 10, 2015 EInet Transition Efforts All current RC nodes on NERCNet have placed orders for new network EIDSN

More information

COM Communications and Coordination

COM Communications and Coordination COM-002-2 Communications and Coordination February 27, 2014 Lonnie Lindekugel ~ SPP Jim Nail ~ City of Independence INTRODUCTION NERC Reliability Standard COM-002-2 (Communications and Coordination) serves

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

WECC Criterion INT-001-WECC-CRT-3

WECC Criterion INT-001-WECC-CRT-3 WECC Criterion INT-001-WECC-CRT-3 A. Introduction 1. Title: e-tag Requirements for WECC including Wrongful Denial of Request for Interchange (RFI) 2. Number: INT-001-WECC-CRT-3 3. Purpose: To manage Arranged

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

December 13, Sw. Power Pool, Inc., 144 FERC 61,224 (2013) ( September 2013 Order ).

December 13, Sw. Power Pool, Inc., 144 FERC 61,224 (2013) ( September 2013 Order ). The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 December 13, 2013 Re: Southwest Power Pool, Inc., Docket No. ER12-1179-00 SPP

More information

primary Control Center, for the exchange of Real-time data with its Balancing

primary Control Center, for the exchange of Real-time data with its Balancing A. Introduction 1. Title: Reliability Coordination Monitoring and Analysis 2. Number: IRO-002-5 3. Purpose: To provide System Operators with the capabilities necessary to monitor and analyze data needed

More information

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities Non-Tariff System Impact Study March 204 Prepared by: Utility System Efficiencies, Inc (USE) Under Contract with:

More information

Building a Topology Estimator for Large Inter-regional Networks

Building a Topology Estimator for Large Inter-regional Networks Building a Topology Estimator for Large Inter-regional Networks ETREP02.pdf Robin Podmore *, Margaret Goodrich**, David Becker***, Peter Hirsch***, Stephen Lee ***, Marck Robinson**** robin@incsys.com,

More information

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources.

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources. Business Practice 1. General 1.1 Primary Network Service is a long-term firm service and should only be used by Network Customers when reserving and scheduling delivery of energy from Designated Network

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

CROW Outage Scheduler Web GUI Tutorial

CROW Outage Scheduler Web GUI Tutorial CROW Outage Scheduler Web GUI Tutorial 9/14/2011 SPP Operations Engineering Revision History Date or Version Number Author Change Description Comments 06/22/2011 Derek Hawkins Initial Draft Draft for review

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Standards Authorization Request Justification

Standards Authorization Request Justification Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

NERC CIP Information Protection

NERC CIP Information Protection NERC CIP Information Protection Eric Ruskamp Manager, Regulatory Compliance September 13, 2017 1 Agenda NERC History NERC Compliance Overview of Reliability Standards Compliance with Reliability Standards

More information

System Studies for American Transmission Co. s Benson Lake SVC Project

System Studies for American Transmission Co. s Benson Lake SVC Project Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC Outline Introduction

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

_ Dear Secretary Bose: The attached. Folsom, CA

_ Dear Secretary Bose: The attached. Folsom, CA California Independent System Operator June 29, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach

Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach How should the CapX TO s approach the response to the MISO Request For Proposal for the MH TSR Facility Study?

More information

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.:

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.: City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM Closing Date: July 17, 2018 at 2:00 p.m. RFI No.: 19-127502 Description: The City of Farmington Electric

More information

AC-DC ERCOT. Bill Bojorquez Dejan J. Sobajic ERCOT Grid Engineering LLC. June 6, 2005 Les Diablerets, Switzerland

AC-DC ERCOT. Bill Bojorquez Dejan J. Sobajic ERCOT Grid Engineering LLC. June 6, 2005 Les Diablerets, Switzerland The 8 th Electric Power Control Centers Workshop June 5-8, 2005, Les Diablerets, Switzerland Panel Session "Monitoring and Control of Large Interconnections under Normal and Emergency Operating Conditions"

More information

Standard EOP Disturbance Reporting

Standard EOP Disturbance Reporting A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Standard Authorization Request Form

Standard Authorization Request Form Standard Authorization Request Form E-mail completed form to rsm@texasre.org Texas RE to Complete SAR No: Title of Proposed Standard IRO-006-TRE-1 IROL and SOL Mitigation in the ERCOT Region Request Date

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure 1 2 3 Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure MISO Functions Served by the Network Model by the

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

Transmission Reliability Margin Implementation Document (TRMID)

Transmission Reliability Margin Implementation Document (TRMID) Avista Corporation Transmission Services Transmission Reliability Margin Implementation Document (TRMID) Posted: March 16, 2011 Effective: April 1, 2011 Version No.: 1 Section 1 NERC defined terms: TRM

More information

ISO-NE Demand response season preparation webinar

ISO-NE Demand response season preparation webinar ISO-NE Demand response 2017 season preparation webinar agenda What you need to know Program information recap Market history and expectations Up-to-date information Curtailment plans Communications drill

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

MTEP16 South SPM #3 MISO Louisiana Project Information

MTEP16 South SPM #3 MISO Louisiana Project Information MTEP16 South SPM #3 MISO Louisiana Project Information 3 rd South Sub-regional Planning Meeting August 25, 2016 NERC TPL Contingency Categories TPL Category Old TPL Category Description BES Level Acceptable

More information

ERO Certification and Review Procedure

ERO Certification and Review Procedure ERO Certification and Review Procedure Reliability Assurance December 15, 2016 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 16 Table of Contents Table

More information

Planning for the Future

Planning for the Future Gas/Electric Partnership Conference Planning for the Future February 1, 2018 Entergy Texas, Inc. Entergy Texas, Inc. Staci Meyer Manager, Resource Planning Jeff Dicharry Manager, Transmission Planning

More information

Designation and Termination of Network Resources

Designation and Termination of Network Resources Transmission & Reliability Services Business Practice: Designation and Termination of Network Resources Posted: February 8, 2010 Effective: May 3, 2010 Revision No.: 5 1. Purpose The purpose of this business

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Electric Transmission Reliability

Electric Transmission Reliability 1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at

More information

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Self-Monitoring:

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

System Data Exchange (SDX) Users Manual. Table of Contents

System Data Exchange (SDX) Users Manual. Table of Contents System Data Exchange (SDX) User s Manual Revision 8 July 2008 System Data Exchange (SDX) Users Manual Table of Contents 1.0 Record of Revisions...3 2.0 General Information...4 2.1 Internet Locations...

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic October 27, 2010 2010 RTEP Baseline Analysis Update Potential loss of load exceeding 300 MW for the loss of the Smithburg Englishtown 230 kv and Raritan River Deep

More information

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Operating Personnel Communications Protocols Please DO NOT use this form. Please use the electronic comment form to submit comments

More information

Interchange Distribution Calculator Billing

Interchange Distribution Calculator Billing Interchange Distribution Calculator Billing Chris Russell Manager, Customer Settlements New York Independent System Operator Billing & Accounting Working Group November 26, 2012 KCC 2012 New York Independent

More information

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network

More information

WECC Criterion INT-001-WECC-CRT-2.13

WECC Criterion INT-001-WECC-CRT-2.13 WECC Criterion INT-001-WECC-CRT-2.13 A. Introduction 1. Title: e-tag Requirements for WECC including Wrongful Denial and Loss of Communication ProceduresRequest for Interchange (RFI) 2. Number: INT-001-WECC-CRT-2.13

More information

Transmission Service Reference Manual. May 08, 2017

Transmission Service Reference Manual. May 08, 2017 Transmission Service Reference Manual May 08, 2017 Revision History Revision History Date or Version Number April 29, 2015 Version 1.0 May 08, 2017 Version 2.0 Author Shari Brown Julie Gerush Change Description

More information

Network Integration Service

Network Integration Service Network Integration Service MPS PAG Meeting November 21, 2013 Network Service The Transmission Provider will provide firm transmission service over its Transmission System to the Network Customer for the

More information

City of Grand Island Tuesday, February 28, 2017 Council Session

City of Grand Island Tuesday, February 28, 2017 Council Session City of Grand Island Tuesday, February 28, 2017 Council Session Item G-6 #2017-50 - Approving Transmission Services Agreement with Nebraska Public Power District Staff Contact: Tim Luchsinger, Stacy Nonhof

More information

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities A. Introduction 1. Title: Real-time Reliability Monitoring and Analysis Capabilities 2. Number: TOP-010-1(i) 3. Purpose: Establish requirements for Real-time monitoring and analysis capabilities to support

More information

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Revision History Version Effective Date Summary of Revisions

More information