Transmission or Distribution. Phil Collins March 18, 2005
|
|
- Henry Maxwell
- 5 years ago
- Views:
Transcription
1 Transmission or Distribution Phil Collins March 18, 2005
2 CUSC Principles of Ownership Power Station Busbar clamp on busbar side of busbar isolators on generators circuit Distribution System Busbar clamp on busbar side of busbar selector isolator on distribution circuit If no busbar exists, an equivalent isolator If no isolator exists, an agreed bolted connection at or adjacent to the tee point Non-Embedded Customer Clamp on circuit breaker side of cable disconnections at User s substation
3 Overview Transmission Connection Boundary Definition: Shareable or potentially shareable assets classed as Infrastructure s and associated site infrastructure and land classed as Transmission Infrastructure Generation only Spurs are Transmission Infrastructure Shared substations where National Grid or s own the busbars and transformer circuits connecting shared LV substations are Infrastructure Grid Supply Points DNO has no right of export Embedded Connections Non Contiguous Connections
4 Transmission Connection Examples
5 Single DNO T Connection Demand Distributor Owned Connection Boundary Owned 132kV, 275kV or 400kV Infrastructure
6 Single T Connection ~ LV Owned User Owned Owned 132kV, 275kV or 400kV Infrastructure
7 Shared T Connection Demand ~ Shared LV Owned User Owned Owned 132kV, 275kV or 400kV Infrastructure
8 Generation and Demand Connection Demand Distributor Owned Connection Boundary User Owned ~ Owned 132kV, 275kV or 400kV Infrastructure
9 Generation Only - Non Spur Connection Infrastructure ~ Owned 132kV, 275kV or 400kV ~ Generator Infrastructure
10 Generation Only Spur (Turn in) ~ Generator Owned 132kV, 275kV or 400kV Infrastructure
11 Generation Only Spur (Remote sub) ~ Generator Owned 132kV, 275kV or 400kV Infrastructure
12 Generation Only Spur (Tee) ~ Generator Owned 132kV, 275kV or 400kV Infrastructure
13 Distribution Connection Examples
14 DNO Connection with embedded generation and demand Demand ~ Distributor Owned DNO Connection Boundary National Grid 132kV, 275kV or 400kV Infrastructure
15 DNO Connection with embedded generation and demand Demand ~ Distributor Owned Distributor Owned DNO Connection Boundary National Grid 132kV, 275kV or 400kV
16 DNO Connection with embedded generation and demand Demand ~ Distributor Owned DNO Connection Boundary Distributor Owned National Grid 132kV, 275kV or 400kV
17 Connection Example
18 What am I? No Demand enerator ~ Distributor Owned Connection Boundary Owned 132kV, 275kV or 400kV Infrastructure
19 Application Process - Transmission
20 Transmission Application Process Applications Customer NGC (GBSO) Host Affected
21 Transmission Application Process Offers Host GBSO Customer Affected
22 Transmission Application Process Offer Acceptance Host Customer GBSO Affected s
23 Transmission Application Process Summary User makes application GBSO makes an NGC Construction Application if required make Construction Offer (CO) if works are required GBSO makes Offer to Customer Customer signs and returns Offer GBSO signs Offer and CO GBSO returns Construction Agreement
24 Application Process - Embedded
25 Embedded Application Process Summary Embedded Generator NGC (GBSO) Host DNO Affected
26 Embedded Application Process Key Attributes BEGA User Applies NGC Construction Application Construction Offer (null) BEGA Gets Construction Agreement and Bilateral Agreement NGC makes Mod Notice to DNO (possible CONSAG) BELLA User and DNO Applies NGC Construction Application Construction Offer (null) BELLA gets Bilateral Agreement and DNO gets Construction Agreement
STCP22-1 Issue 003 Production of Models for GB System Planning
STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission
More informationEDS MW AND MVAR TRANSDUCER CONNECTION
Document Number: EDS 05-5001 Network(s): Summary: ENINEERIN DESIN STANDARD EDS 05-5001 MW AND MVAR TRANSDUCER CONNECTION EPN, LPN, SPN This standard details the convention to be used when wiring MW and
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationTHE CONNECTION AND USE OF SYSTEM CODE TEMPORARY TEC EXCHANGE RATE REQUEST FORM
CUSC EXHIBIT W THE CONNECTION AND USE OF SYSTEM CODE TEMPORARY TEC EXCHANGE RATE REQUEST FORM DIRECTLY CONNECTED POWER STATION EMBEDDED POWER STATION INTERCONNECTOR OWNER DISTRIBUTION INTERCONNECTOR Please
More informationOTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER
Parsons Brinckerhoff Associates OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER A report prepared for 23 March 2007 Disclaimer Notice Report for
More informationNetwork Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY
Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Original Issue: September 2007 Prepared by: Lee Chan & Rob Rogerson This Revision: 0 October 2007 Date For Next Review:
More informationBalancing and Settlement Code BSC PROCEDURE
Balancing and Settlement Code BSC PROCEDURE Registration of Transmission System Boundary Points, Grid Supply Points, GSP Groups and Distribution Systems Connection Points BSCP25 Version 8.0 Date: 29 June
More informationSCHEDULE 22 COMMON CONNECTION CHARGING METHODOLOGY
SCHEDULE 22 COMMON CONNECTION CHARGING METHODOLOGY Introduction 1. This Schedule 22 sets out the Common Connection Charging Methodology (CCCM). The CCCM is the whole of this Schedule 22 excluding only
More informationSTCP19-3 Issue 006 Operational Notification & Compliance Testing
STCP19-3 Issue 006 Operational Notification & Compliance Testing STC Procedure Document Authorisation Company National Grid Electricity Transmission plc Name of Party Representative Signature Date SP Transmission
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationOffshore BMU Configuration
BMU Configuration Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Steve Curtis : System Operator
More informationMicrogrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids
Enrico Ragaini (ABB Low Voltage Products), Alexandre Oudalov (ABB Corporate Research), ISGT Europe 2012, Berlin Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids
More informationSTCP Amendment Proposal Form
STCP Amendment Proposal Form PA036 1. Title of Amendment Proposal STCP 09-2 Incorporation material currently within SPT SCS and making standard for both TOs. 2. Description of the Proposed Amendment (mandatory
More informationDisturbance Monitoring and
PRC-002-2 R1 Notification Disturbance Monitoring and Reporting Requirements Compliance Spring Workshop May 10, 2017 Objectives This presentation will discuss: Requirement R1 Part 1.2 notifications Definition
More informationRelevant Electrical Standards (RES) Grid Code Review Panel January 2014
Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same
More informationAir-insulated medium-voltage secondary distribution switchgear
DISTRIBUTION SOLUTIONS Air-insulated medium-voltage secondary distribution switchgear Compact size Complete solution Factory tested Air-insulated medium-voltage secondary distribution switchgear The ABB
More informationTransmission Register PTO Admin User Manual. Version 1.0
Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6
More informationBranch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.
Branch Procedure Document No. Issue No. : : CEOP8012 5 Approved By : Specialist Engineering NETWORK : Manager Approval Date Review Date : : 29/06/2018 29/06/2021 (Supersedes CEOP8012, Generation Connection:
More informationEngineering Recommendation G87 Issue
PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation G87 Issue 2-2015 Guidelines for the Provision of Low Voltage Connections to Multiple Occupancy Buildings
More informationData and Forecasting Summary
Data and Forecasting Summary This article highlights the need for more integrated and aligned data systems within WPD and improved interfaces within the industry. It also looks at the increased need for
More informationWhat You Should Know About Communication Systems: Business Strategies and Options
Doug Voda, PPMV Global Segment Leader for Smart Grid February 2015 NRECA TechAdvantage What You Should Know About Communication Systems: Business Strategies and Options The visionary Smart Grid Five Pillars
More informationGUIDELINES FOR SHARED TRANSMISSION CONNECTIONS IN VICTORIA
GUIDELINES FOR SHARED TRANSMISSION CONNECTIONS IN VICTORIA PREPARED BY: Transmission Services VERSION: 2.0 RELEASE DATE: 14 December 2011 FINAL Version Release History Version Date Approved 1.0 3 Jun 11
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationDecision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement
Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,
More informationIEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems
Alexandre Oudalov, ABB Switzerland Ltd., Corporate Research, 2014-04-30 Microgrid Protection IEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems Microgrid Protection
More informationEnergy Energy Networks. Networks Association. Association. Insert presentation title here. The Voice of the Networks
The Voice of the Networks Energy Energy Networks Networks Association Association Open Networks Project Workstream 1 Product 12 (Update Section 12.3) Insert presentation title here Name Position Date Context
More informationDistributed Generation Customer Perspectives. Focus on LV to 33kV Connections sector (PV)
Distributed Generation Customer Perspectives Focus on LV to 33kV Connections sector (PV) James Hoare CEng MIET MEI BRE National Solar Centre -Associate Consultant LHW Partnership LLP - Owner 24 th September
More informationFlexible Distributed Generation. FDG-A March Area (EPN) December 2016
Flexible Distributed Generation FDG-A March Area (EPN) December 2016 Principles of Flexible Distributed Generation A Flexible DG connection is a technical and commercial agreement where a generator is
More informationEDS GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET NETWORKS (IDNOS AND OTHER LICENSED DNOS)
THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE ENGINEERING DESIGN STANDARD EDS 08-0113 GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET
More informationAn Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections
An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections An Introduction to the Operational Notification and Compliance Process Including
More informationPower System Control And Smart Grid
Power System Control And Smart Grid The Technology Journey so far... 2005-07 2007-09 2009-11 2011-12 OMS Implementation ISO 27001- Security certification Basic DMS Application,SPM JGC DMS System & Distribution
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationDescription Activities Description. Co-ordination with GB System Operator. Co-ordination with other DSOs and Distribution Networks (including IDSOs)
Appendix A DSO Functions (Version 7) No. DSO Functions 1 System Coordination Description Activities Description Operate local and regional areas and co-ordinate energy and power transfers with other networks
More informationDISCERN SGAM Visio Template User Guide
Distributed Intelligence for Cost-Effective and Reliable Distribution Network Operation DISCERN SGAM Visio Template User Guide Author: OFFIS Date: 22.04.2016 www.discern.eu The research leading to these
More informationIntroduction to Generation Availability Data System (GADS) Wind Reporting
Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics
More informationOpen Networks Project
Open Networks Project s and efinitions 25 July 2018 ocument Ref: WS2P3JUL18 Restriction: Published ocument Name ocument Control Version Control Version Issue ate Author Comments 1.1 25 th July 2018 ENA
More informationSTCP 18-3 Issue 006 TEC Changes
STCP 18-3 Issue 006 TEC Changes STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc. Scottish Hydro-Electric
More informationFlexible Connections for DG Customers
Flexible Connections for DG s Session 1b: Connections Paul Pretlove UK Power Networks Ruth Kemsley Wind Prospect In partnership with: Deployment Key outputs REQUIREMENTS Interface specification guidance
More informationANCILLARY SERVICES BUSINESS MONITORING
ANCILLARY SERVICES BUSINESS MONITORING This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for
More informationManual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements
Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Standard Number: HPC-5DA-07-0001-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document
More informationStatement of Charges for Use of System for The Electricity Network Company Limited s Distribution Network
Statement of Charges for Use of System for The Electricity Network Company Limited s Distribution Network FINAL STATEMENT Effective from: 1 st April 2014 BK-CSR-IG-0108 Use of System Charging Statement
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December
More informationOur Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium
Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium Voltage Panels and Enclosures designed and built with
More informationCapital Contribution Policy for New Load and Network Extensions Marlborough Lines
Capital Contribution Policy for New Load and Network Extensions Marlborough Lines Table of Contents 1. Glossary of Terms... 3 2. Purpose... 3 3. Policy... 4 4. Network Development Levy... 6 5. Remote Area
More informationASSET RISK MANAGEMENT Criticality Framework
ASSET RISK MANAGEMENT Criticality Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to
More informationGE Energy Connections Grid Solutions MMLZ. Technical Data Sheet Auxiliary Modules. Publication reference: MMLZ/EN TDS/B
GE Energy Connections Grid Solutions MMLZ Technical Data Sheet Auxiliary Modules Publication reference: MMLZ/EN TDS/B MMLZ Technical Data Sheet FEATURES Wide choice of application specific models Fully
More informationMMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A
AUTOMATION MMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A GRID Note: The technical manual for this device gives instructions for its installation, commissioning,
More informationIMP/ 001 / 014 Policy for the Protection of Distribution Networks
Version:- 1.1 Date of Issue:- July 2016 Page 1 of 39 IMP/ 001 / 014 Policy for the Protection of Distribution Networks 1. Purpose The purpose of this document is to detail the network protection philosophy
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationIEEE Distribution Automation Working Group
IEEE Distribution Automation Working Group Tuesday 26 June Tampa, Florida EDF Distribution system of the future and DA roadmap 1 EDF Group at a glance United Kingdom EDF Energy 8 M customers 16 GW capacity
More informationUniSec, MV AIS for Secondary Distribution Smart Grid applications
Ing. Natalia Moizzes- Switchgear Product Specialist Chile Abril 14 th 2015 UniSec, MV AIS for Secondary Distribution Smart Grid applications Slide 1 Concept - Needs and Solutions Requests are: Manage faults
More informationImplementation of One and a Half Breaker Arrangement in Fierza 220 KV Substation with Prozanet Scada System
Implementation of One and a Half Breaker Arrangement in Fierza 220 KV Substation with Prozanet Scada System Doi:10.5901/ajis.2015.v4n2s2p167 Abstract Eni Saqe * Prof.Asoc.Dr. Marialis Celo* Phd. Marjela
More informationEFASOLAR PVStation Solutions
www.efacec.com EFASOLAR PVStation Solutions EFASOLAR PVStation EFASOLAR PVStation Solutions 0,5 MW 1 x EFASOLAR 50 0,50 MW 1 x EFASOLAR 500M 1 MW 1,46 MW Efacec is a century-long experienced company in
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationSTCP 04-3 Issue 005 Real Time Data Provision
STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationPowering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director
Powering the North West s Future: From DNO to DSO Paul Bircham Commercial Strategy & Support Director 1 Introducing Electricity North West 5 million 2.4 million (45% of demand) 20,000 I&C (55% of demand)
More informationCapital Contribution Policy for New Load and Network Extensions Marlborough Lines
Capital Contribution Policy for New Load and Network Extensions Marlborough Lines Table of Contents 1. Glossary of Terms... 3 2. Purpose... 4 3. Policy... 5 4. Network Development Levy... 6 5. Remote Area
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationEDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES
Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-0150 LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES LPN This standard provides guidelines for the development of the 33kV distribution
More informationDRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1
DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...
More informationPPL EU Relay Standardization
PPL EU Relay Standardization John Sonnelitter Senior Engineer, Transmission Relay Engineering Richard Michael Jr. Support Engineer, Transmission Relay Engineering 9/18/2018 Background PPL EU is undergoing
More informationDigital Protection Past, Present, and Future
Digital Protection Past, Present, and Future Eric A. Udren Quanta Technology, LLC Pittsburgh, PA Presentation for CIGRÉ Grid of the Future Symposium Boston, MA October 22, 2013 eudren@quanta-technology.com
More informationAdvanced Monitoring Solutions for Critical Electric Power Transmission & Distribution Assets
Advanced Monitoring Solutions for Critical Electric Power Transmission & Distribution Assets www.intellisaw.com The Case for Critical Asset* Monitoring The vast majority of critical assets in the field
More information1. Project Description
Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal
More informationHigh-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY
S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are
More informationUSE CASE 14 CONTROLLED ISLANDING
I USE CASE 14 CONTROLLED ISLANDING Use Case Title Centralized application separates grid into islands to prevent blackout Use Case Summary Controlled islanding is a method that can significantly improve
More informationICP. Simplifying. Competition in Connections FOR UNMETERED, METERED AND DISTRIBUTED GENERATION CONNECTIONS
ICP Simplifying Competition in Connections FOR UNMETERED, METERED AND DISTRIBUTED GENERATION CONNECTIONS ICP Competition in Connections Did you know you have a choice of who provides your new electricity
More informationEDS LV CUSTOMER UNMETERED SUPPLIES
Document Number: EDS 08-2102 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-2102 LV CUSTOMER UNMETERED SUPPLIES EPN, LPN, SPN This standard details the requirements for unmetered single-phase
More informationIntelligent Grid and Lessons Learned. April 26, 2011 SWEDE Conference
Intelligent Grid and Lessons Learned April 26, 2011 SWEDE Conference Outline 1. Background of the CNP Vision for Intelligent Grid 2. Implementation of the CNP Intelligent Grid 3. Lessons Learned from the
More informationElectrical Integration with Smart Communication
Electrical Integration with Smart Communication New possibilities with Industrial Ethernet ABB Group September 24, 2009 Slide 1 Unified Integration Approach MES and Business Systems Knowledge Portals as
More informationEandis IEC61850 Next steps. 27 September 2017
Eandis IEC61850 Next steps Eandis in the Energy market Regulator CREG / VREG Producers Electricity Import Natural Gas Elia Distribution Grid Operator Fluxys Suppliers Customers 2 HS Eandis Network: TS
More informationSWITCHYARD SYSTEM BC1-SS-11-SD TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1
SWITCHYARD SYSTEM TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1 November 2011 PREFACE This Training System Description has been designed to assist you in meeting the requirements of Module BC1-SS-11
More informationRoad Map to Grid Modernization
Road Map to Grid Modernization APIC, University of Alberta May 5 th, 2016 Presenter: Chris Chapelsky, MSc., P.Eng. Operations 1 Engineer About EPCOR Water & Power Transmission & Distribution in Edmonton
More informationVerification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation
111 Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation Z. Gajić (ABB, Sweden) JP Wang / PW Gong / YS Xu (ABB China) ZX Zhou (CERPI, China) Summary Power utilities
More informationINTEGRATED DISTRIBUTION GRID MANAGEMENT SYSTEM
INTEGRATED DISTRIBUTION GRID MANAGEMENT SYSTEM ABSTRACT Robert SCHMARANZ robert.schmaranz@kaerntennetz.at Jürgen PASKER juergen.pasker@kaerntennetz.at This paper introduces an Integrated Grid Management
More informationPOWER GRIDS. We are bridging the gap. Enabling Digital Substations.
POWER GRIDS We are bridging the gap. Enabling Digital s. 2 A B B D i g i ta l S u b s tat i o n s ABB s Digital provides customers in the utility sector with unmatched control and efficiency. The digital
More informationSDG&E EPIC Program Overview
SDG&E EPIC Program Overview Presented by: Frank Goodman, SDG&E i-pcgrid Workshop March 30, 2018. All copyright and trademark rights reserved. Presentation overview SDG&E overview Project lists for three
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationHigh Speed Powerline Communication for the Smart Grid
High Speed Powerline Communication for the Smart Grid UPA Vision for the Future Chris Graham-Fielding Freedom Digital Networks Freedom Digital Networks Privately funded UK company Formed in 2004 Deploy
More informationPresented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011
Photovoltaic Solutions Make the most of your solar PV project Presented by: Oscar Araujo Photovoltaic Solutions Manager 4 th Canadian German Solar PV Conference March 2 nd 2011 Agenda Solutions for Renewable
More informationTENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT
TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN >>> TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN Tengiz is one of the largest oil fields in the world, and is located in western
More informationBest practices for making switchgear safer.
Best practices for making switchgear safer. www.sea.siemens.com www.usa.siemens.com/switchgear Prepared by: Ken Newsome - Consulting Business Developer Kevin Mullins - Consulting Business Developer Joe
More informationNERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum
Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationTransition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007
Data Center Operations Outsourcing Transition Plan Implementation: Final Page 1 of 15 DOCUMENT CONTROL SHEET Schedule/Exhibit Amendment Control Sheet Title of Amended Document: Section 4 Transition Plan
More informationEPRI Protection Settings Evaluation Tool (PSET)
EPRI Protection Settings Evaluation Tool (PSET) Mahendra Patel & Sean McGuinness Grid Operations & Planning EPRI Protection Settings Evaluation Tool (PSET) Software Intended use: Automatically assess the
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution
More informationPOWER INFRASTRUCTURE PLAN 2016
POWER INFRASTRUCTURE PLAN 2016 Introduction LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4 million people
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationPower Infrastructure Plan
Power Infrastructure Plan 2015 Introduction Background LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4
More informationSTRATHCONA AREA TRANSMISSION UPGRADE PROJECT
STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a
More informationFlexible Connections and Principles Of Access Policy
1. SCOPE This document defines the Policy for Flexible Connection Solutions and their Principles Of Access to be adopted throughout SP Energy Networks from 28 th February 2017. The purpose of this document
More informationInsight into the Utility Network. Erik Hoel and Tom Brown March 13, 2018
Insight into the Utility Network Erik Hoel and Tom Brown March 13, 2018 Utility network New network framework to support utility and telco solutions Vision: Provide utility customers with the ability to
More informationTHE CONNECTION AND USE OF SYSTEM CODE USE OF SYSTEM APPLICATION
v1.10 CUSC - EXHIBIT F THE CONNECTION AND USE OF SYSTEM CODE USE OF SYSTEM APPLICATION SUPPLIER INTERCONNECTOR USER INTERCONNECTOR ERROR ADMINISTRATOR v1.10 PLEASE STUDY THE FOLLOWING NOTES BEFORE COMPLETING
More informationJanuary 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.
California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California
More informationUnofficial Comment Form Project Disturbance Monitoring
Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request
More informationCritical Asset Identification Methodology. William E. McEvoy Northeast Utilities
Critical Asset Identification Methodology William E. McEvoy Northeast Utilities Disclaimer This NPCC TFIST workshop provides a forum for the presentation and discussion of member experience in the implementation
More informationTitle Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP)
Discipline Engineering Standard - NSW Category Electrical Title Reference Number POP 07 - (RIC Standard: EP 99 00 00 04 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More information(Above 100km Distance) (Streetlight Pole) (Above 100km Distance) (Streetlight Pole)
Part 9 Miscellaneous Drawing Register Number Description M1-1 SSN Network Device with LV Aerial Supply (ABC) Arrangement M1-2 SSN Network Device with LV Aerial Supply Arrangement M1-3 SSN Network Device
More information