Use case for the south Portuguese network - Results -
|
|
- Rosamond Angelina Sparks
- 5 years ago
- Views:
Transcription
1 Use case for the south Portuguese network - Results - Nélio Machado, REN, Portugal Milenko Halat, AIA, Spain Network Security Assessment Days November 5 th 2015, Brussels
2 Content Description of Portuguese Network Steps for Automatic conversion Preliminary results 2
3 Overview of Portuguese HV network HV lines 8733km 400 kv 2434 km 220 kv 3565 km 150 kv 2734 km Interconections 9 (6 x 400, 3 x 220 kv) Telecontrol (400, 220,150 e 60 kv): Substations 80
4 Overview of Portuguese HV network Interconnections coal gas hidro Windfarms Consumption density
5 2014 Consumption
6 Overview of Portuguese HV network
7 Generation
8
9 2015 4,931MW wind instaled capacity 8,322MW peak load Managing Wind Generation Consumption lower than renewable not dispatchable generation Solution: - Use pump units (1,633MW) - Export (if possible)
10 2015 4,931MW wind instaled capacity 8,322MW peak load Managing Wind Generation Drop of 2500MW of wind generation in less than 8 hours Wind and consumption are in phase opposition Wind forecast generation is very important
11 itesla Portuguese Usecase In order to evaluate itesla toolbox security analysis capabilities, an incident occurred in 23/12/2009 was selected as case study of voltage collapse at South zone of Portugal. This situation was created by local extreme wind conditions in a event that is techically called Explosive cyclogenesis also referred as a weather bomb. It is an intense low pressure system with a central pressure that falls 24 millibars in a 24-hour period.
12 itesla Portuguese Usecase 23/dec/ :38 First hit On a area of 50 km, wind speed of 220km/h was registered 13 towers were hit and collapse 3 lines got out of operation: (1) 400 and (2) 150kV
13 itesla Portuguese Usecase 23/dec/ :34 Second hit Local windfarm registered wind speed of 201km/h 14 towers were hit and collapse 4 lines got out of operation: (1) 400 and (3) 220kV
14 Situation in 23/12/2009 2nd hit Rio Maior Batalha Zêzere Carregado South Portugal (Setúbal, Alentejo and Algarve) Spain) coal gas hidro Fuel emergency turbines
15 itesla Portuguese Usecase This situation was managed by REN operation control room during 3 months using steady state contingencies results to decide if fuel emergency turbines were needed Generation Load forecast itesla approach - Steady state and dynamic calculation - Uncertainties were considered validating all operation space Generation Load forecast
16 Objective/Challenge: itesla Portuguese Usecase Generate 1 month snapshots before incident and 1 week after CIM14 format will be used which consider static references (RDFIDs) in all cases Difficulties: REN snapshots are in PSS/E format Equipment at snapshots don t have static references Our CIM converter tool vendor is discontinuing CIM14 as TSOs will use CGMES in the future
17 itesla Portuguese Usecase REN generated 21.6GB of information 1728 datasets in CIM14 Metering Database (Generation and load) Base RAW File 16/12/2009 CIM converter ODMS v11 CIM14 UseCases Outage Database SCADA Database Voltage Profile RDFID mapping file TestCase 16/12/2009
18 Conversion Modules The itesla platform has been designed to support ( plug ) different dynamic simulation engines One of them is Dymola, for Modelica By developing automatic conversion modules (from proprietary formats to Modelica) we aim to ease the adoption of itesla platform This step has a series of advantages by itself So far, we have developed conversion modules from Eurostag and PSSE tools, but extensible to any proprietary simulation tool 18
19 How does it work? (1/3) PSSE dynamic file (.dyr) The connections depend on each configuration model CRESTUMA parameter Real SNREF = 100.0; // BUSES // TAP CHANGER TRANSFORMERS // LINES // LOADS // CAPACITORS // GENERATORS PowerSystems.Electrical.Machines.PSSE.GENSAL.GENSAL G1( eterm = 1.0, anglev0 = , pelec = 533.0, qelec = , Mbase = , Tpd0 = 5.0, Tppd0 = 0.06, Tppq0 = 0.1, H = 3.2, D = 0.0, Xd = 0.75, Xq = 0.5, Xpd = 0.25, Xppd = , Xppq = , Xl = , s10 = , s12 = // REGULATORS // EVENT:FAULT PowerSystems.Electrical.Events.PwFault _fault(x = 0.5, R = 0.5, t1 = 20, t2 = 100); equation // Connecting REGULATORS and MACHINES connect(scrx.efd.pelec, gensal.efd); connect(hygov.pmech, gensal.pmech); // Connecting REGULATORS and REGULATORS connect(stab2a.vothsg, ieeet2.vothsg); // Connecting REGULATORS and CONSTANTS connect(ieeet2.voel, const.y); // Connecting LINES connect(_bus.p, pwline_2.p); Modelica file 19
20 How does it work? (2/3) Modelica Library (ipsl) model CRESTUMA parameter Real SNREF = 100.0; // BUSES // TAP CHANGER TRANSFORMERS // LINES // LOADS // CAPACITORS // GENERATORS PowerSystems.Electrical.Machines.PSSE.GENSAL.GENSAL G1( eterm = 1.0, anglev0 = , pelec = 533.0, qelec = , Mbase = , Tpd0 = 5.0, Tppd0 = 0.06, Tppq0 = 0.1, H = 3.2, D = 0.0, Xd = 0.75, Xq = 0.5, Xpd = 0.25, Xppd = , Xppq = , Xl = , s10 = , s12 = // REGULATORS // EVENT:FAULT PowerSystems.Electrical.Events.PwFault _fault(x = 0.5, R = 0.5, t1 = 20, t2 = 100); equation // Connecting REGULATORS and MACHINES connect(stab2a.pelec, genrou.pelec); // Connecting REGULATORS and REGULATORS connect(stab2a.vothsg, ieeet2.vothsg); // Connecting REGULATORS and CONSTANTS connect(ieeet2.voel, const.y); // Connecting LINES connect(_bus.p, pwline_2.p); // COUPLING DEVICES 20
21 How does it work? (3/3) Modelica generatorregulation connections model CRESTUMA parameter Real SNREF = 100.0; // BUSES // TAP CHANGER TRANSFORMERS // LINES // LOADS // CAPACITORS // GENERATORS PowerSystems.Electrical.Machines.PSSE.GENSAL.GENSAL G1( eterm = 1.0, anglev0 = , pelec = 533.0, qelec = , Mbase = , Tpd0 = 5.0, Tppd0 = 0.06, Tppq0 = 0.1, H = 3.2, D = 0.0, Xd = 0.75, Xq = 0.5, Xpd = 0.25, Xppd = , Xppq = , Xl = , s10 = , s12 = // REGULATORS // EVENT:FAULT PowerSystems.Electrical.Events.PwFault _fault(x = 0.5, R = 0.5, t1 = 20, t2 = 100); equation // Connecting REGULATORS and MACHINES connect(scrx.efd.pelec, gensal.efd); connect(hygov.pmech, gensal.pmech); // Connecting REGULATORS and REGULATORS connect(stab2a.vothsg, ieeet2.vothsg); // Connecting REGULATORS and CONSTANTS connect(ieeet2.voel, const.y); // Connecting LINES connect(_bus.p, pwline_2.p); 21
22 Converting a power grid (1/2) STEPS Preliminary checks: Are all the required models in the Library? Model and validate what you need Is the system consistent in the native tool? (Power Flow, Dynamic Simulation) Are the CIM files correctly generated? (No info missing, correct version) Automatic conversion: Try Regulation groups is simple examples Try first small representative systems Time step for simulation or is the correct integrator? Follow the recommendations. Wrong integrator may introduce artificial behavior. Solver chosen 22
23 Converting a power grid (1/2) STEPS Library release as Open Source Community Publishing analysis and recommendations Preliminary checks: Are all the required models in the Library? Model and validate what you need Is the system consistent in the native tool? (Power Flow, Dynamic Simulation) Are the CIM files correctly generated? (No info missing, correct version) Automatic conversion: Try Regulation groups is simple examples Try first small representative systems Time step for simulation or is the correct integrator? Follow the recommendations. Wrong integrator may introduce artificial behavior. Solver chosen 23
24 Converting a power grid (2/2) Modelica file has been generated: Does the system check? Connection problems, different number of equations and variables. Does the Modelica file initialize? Different kind of problems [check the models, parameters ] Is there an stable solution? Check initial values on elements Is the steady state value similar to the native tool? LF: Do the values correspond? Is the same swing? Introduce events: Software to software validation What are the acceptability criteria? [Remember some models comes from an interpretation of the black-box models] Increase complexity: Until arrive to the target system. Observe computation times: recommendations about simulation engine, integration methods, etc 24
25 Converting a power grid (2/2) Library release as Open Source Community Publishing analysis and recommendations Modelica file has been generated: Does the system check? Connection problems, different number of equations and variables. Does the Modelica file initialize? Different kind of problems [check the models, parameters ] Is there an stable solution? Check initial values on elements Is the steady state value similar to the native tool? LF: Do the values correspond? Is the same swing? Introduce events: Software to software validation What are the acceptability criteria? [Remember some models comes from an interpretation of the black-box models] Increase complexity: Until arrive to the target system. Observe computation times: recommendations about simulation engine, integration methods, etc 25
26 Portuguese network Description 656 connected buses. 171 Gens of which 146 are connected + 86 WT4G1 14 different regulation configurations
27 Regulation Groups Reg Group Infinite Bus Example Created to check the connection
28 Results Conversion of whole Portuguese network is on progress Trimmed portions have been simulated: RIBATEJO South part: [Currently fixing problems in some models that are present there] 28
29 RIBATEJO Fault in Bus at t = 5[s] 29
30 South Part 27 gens / 80 buses (Below Lisbon) [Fixing] Some ESST1A models in the.dyr file have KLR = 0 and it should be declared not equal to zero. 30
31 Summary The automatic conversion needs some tuning, but the effort will decrease progressively This work totally worth it: not only to benefit from itesla platform, but to perform analysis. For instance, using custom regulations or events 31
32 Thanks! 32
33 Conversion tool: Status Overview Automatic conversion from Eurostag or PSSE to Modelica Merge dynamic and static parts Simulations ~ 70 generators so far Events automatically included Two initialization schemes Uses the Modelica Library Modelica Power Systems Library Quite complete, ordered and validated Compatible with OpenModelica Prepared to collaborative working and maintenance Systems Set of systems (~18) of different size and complexity
34 System conversion to Modelica Dynamic Static PSS/E Modelic a Library Conversion module In itesla Platform Modelica Representation
35 Modelica Library Component type Component Modelica model Checked GENERATORS EXCITERS GOVERNORS STABILIZERS WIND GENERATORS GENSAL GENROU ESST4B ESAC1A ESAC2A ESST1A ESDC1A ESDC2A EXST1 IEEET1 IEEET2 ST5B SCRX SEXS GAST GGOV1 x IEESGO IEEEG1 HYGOV TGOV1 IEEEST PSS2A PSS2B STAB2A WT3G1 * WT4G1 * All devices for Norwegian, Portuguese and Greek networks have been modelled. The models recently integrated in the library will be tested in the conversion of Greek and Portuguese network.
36 Modelica Library
37 Summary table Status: Converted Systems
38 Inclusion of events We have modelled 6 types of events so far o Line opening, o bus / line fault, o bank / load / setpoint modification The event is included a posteriori, as a modification of the converted system Event id Event type Elemen t Event parameters
NERC MOD List of Acceptable Models and Model Library Block Diagrams for Use in Dynamic Simulation (MOD-026-1, R1)
NERC MOD-026-1 List of Acceptable Models and Model Library Block Diagrams for Use in Dynamic Simulation (MOD-026-1, R1) PJM Interconnection Original Document Date: July 1, 2014 Current Document Date: March
More informationA Tool to ease Modelica-based Dynamic Power System Simulations
A Tool to ease Modelica-based Dynamic Power System Simulations Raul Viruez 1 Silvia Machado 1 Luis María Zamarreño 1 Gladys León 1 François Beaude 2 Sébastien Petitrenaud 2 Jean-Baptiste Heyberger 2 1
More informationA Modelica Power System Library for Phasor Time-Domain Simulation
2013 4th IEEE PES Innovative Smart Grid Technologies Europe (ISGT Europe), October 6-9, Copenhagen 1 A Modelica Power System Library for Phasor Time-Domain Simulation T. Bogodorova, Student Member, IEEE,
More informationObjective. High Level Overview of Dynamic Model Building Process. Inputs, Outputs. MISO 16 Dynamic Model Suite. MISO 16 Dynamic Data Request
1 Objective High Level Overview of Dynamic Model Building Process Inputs, Outputs MISO 16 Dynamic Model Suite MISO 16 Dynamic Data Request Reference Material for New Data Submitters High level Timeline
More informationT&D Challenges and Opportunities
T&D Challenges and Opportunities Mark McGranaghan Vice President, Power Delivery and Utilization Alberta Power Industry Consortium November 5, 2014 Tomorrow s Power System (vision) The Integrated Grid
More informationPowsybl basics, IIDM
Powsybl basics, IIDM ipst/powsybl day, 2018-05-25 Sylvain Leclerc sylvain.leclerc@rte-france.com Powsybl-core: basics 2 What it s not: - A ready-to-run application (but https://github.com/powsybl/powsybl-gse
More informationSystem Engineering, IT/OT Integration and the Smart Grid. Steve Apps Pr.Eng SAIEE Associate Director EON Consulting, South Africa
System Engineering, IT/OT Integration and the Smart Grid Steve Apps Pr.Eng SAIEE Associate Director EON Consulting, South Africa South African grid: large and complex Line (kv) Length (km) 765 1,859 533
More informationCIM for Dynamic 2010 CIM Workshop
Answers for energy. CIM for Dynamic 2010 CIM Workshop T&D Service Solutions Chuck DuBose Siemens PTI September 09, 2010. History CIM for Planning Interop New York: 11/11/2008 EPRI CIM for Planning Results
More informationSolutions for transmission network management
EM SG SOLutions Solutions for transmission network management Energy Management Smart Grid Solutions Solutions for Transmission Network Management Overview Operator Training Simulator Blackout Prevention
More informationCORESO A CENTRALIZED REGIONAL SECURITY COORDINATION INITIATIVE. Leading coordination for enhanced reliability of supply
CORESO A CENTRALIZED REGIONAL SECURITY COORDINATION INITIATIVE Leading coordination for enhanced reliability of supply A bit of recent history 2 (near) black out as triggering factor... 4 November 2006
More informationFeasibility Study on Load Flow and Short Circuit Project
Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationEURELECTRIC CEER Joint Workshop on Voltage Quality Monitoring
EDP Distribuição Experience with Power Quality Monitoring in Portugal EURELECTRIC CEER Joint Workshop on Voltage Quality Monitoring Brussels, 18 November 2009 Nuno Melo Power Quality Activity Group Contents
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More informationHIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM
HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM A. Valenti* I Bel ** S. Lee *EDF **EPRI E2I ConEdison France USA USA arnaud.valenti@edf.fr
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationReal-time transient stability simulation tool
ephasorsim: Real-time transient stability simulation tool Vahid Jalili-Marandi, Ph.D. OPAL-RT Technologies Vahidj@opal-rt.com 1 Large 10 000+ Nodes Wide Area Simulation ephasorsim Large EMT Simulation
More informationSmart Distribution Technology
Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications
More informationN-1-1 Reactive Upgrades
N-1-1 Reactive Upgrades Previous Analysis Discussed at November 2011 TEAC Voltage collapse for multiple 500 kv N-1-1 contingency pairs A number of reactive upgrade locations evaluated to determine a optimal
More informationCIM 2 Modelica Factory
CIM 2 Modelica Factory Automated Equation-Based Cyber-Physical Power System Modelica Model Generation and Time-Domain Simulation from CIM luigiv@kth.se, fragom@kth.se Electric Power Systems Dept. KTH Stockholm,
More informationInnovative Tools for the Future Coordinated Operation of the Pan-European Electricity Transmission System. Tuesday January 14, 2014
2 nd itesla/umbrella Open Workshop Innovative Tools for the Future Coordinated Operation of the Pan-European Electricity Transmission System Tuesday January 14, 2014 1 1 st common workshop held in Brussels
More information3D diagrams of Eurostag generator models for improved dynamic simulations
3D diagrams of Eurostag generator models for improved dynamic simulations Achieve online dynamic security analysis To make good network situations short-term forecast, initializing dynamic simulations
More informationEMS / DMS. DISTRIBUTION MANAGEMENT SYSTEM- Functional Description
EMS / DMS DISTRIBUTION MANAGEMENT SYSTEM- Content 1. INTRODUCTION... 4 2. MODES OF INTERACTION WITH THE SCADA SYSTEM... 5 2.1 Simulation Mode... 5 2.2 State Estimation Mode (See functional description
More informationDemonstration and Proposal for Transmission Owner (TO) Utilization of Dispatch Interactive Mapping Application (DIMA) Tool
Demonstration and Proposal for Transmission Owner (TO) Utilization of Dispatch Interactive Mapping Application (DIMA) Tool Ed Kovler Jacqulynn Hugee November 2017 What is DIMA? 2 Aware of your surroundings?
More informationDSO for Republic of Ireland. Supplying every home in the country
Coordinated Planning in Ireland & Active Voltage Management using Wind Generation ESB Networks About ESB Networks DSO for Republic of Ireland Supplying every home in the country Asset Owner Transmission
More informationISO New England Data Modeling Requirements
A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationAchieving Smarter Grid Operation With On-Line DSA Technology
Achieving Smarter Grid Operation With On-Line DSA Technology Powercon 2014 October 20-22, 2014, Chengdu, China Lei Wang Powertech Labs Inc. 12388 88 th Avenue Surrey, BC, Canada A very simple version of
More informationGrid Analytics Conference 2013
Grid Analytics Conference 2013 SCADA Data: Breaking down silo-based operations and teams to leverage SCADA data and improve network operation, maintenance and investment decisions Aurélio Blanquet, EDP
More information4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)
A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure
More information4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)
A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure
More informationDynamic Load Models in PowerWorld Simulator
Dynamic Load Models in PowerWorld Simulator Jamie Weber (weber@powerworld.com) Director of Software Development 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com
More informationReal Time Digital Simulator Testing of an On Line Integrated Stability Control System
Real Time Digital Simulator Testing of an On Line Integrated Stability Control System R.P. Wierckx, M. Kawasaki, N. Saito, K. Anzai, S.C. Verma Abstract The paper describes the testing of an on line integrated
More informationQuick Start for User Defined Models
Quick Start for User Defined Models Last Updated: June 11, 2013 PowerWorld Corporation 2001 South First St Champaign, IL 61820 (217) 384-6330 http://www.powerworld.com info@powerworld.com Overview... 3
More informationChristian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1
Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms May 22, 2009 Slide 1 FACTS Applications Flexible AC Transmission Systems May 22, 2009 Slide 4 System Studies - Grid Codes
More informationSMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM
SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the
More informationChapter 2 State Estimation and Visualization
Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation
More informationAgenda An Overview of Network Codes, CIM & CGMES
Agenda An Overview of Network Codes, CIM & CGMES Elkraft 2017 2017-05-18 Lars-Ola Österlund Now Brolunda Consulting Retired from ABB Software Enterprise fall 2016 Worked with standards in IEC TC57 and
More informationWHERE THE DIGITAL TRANSFORMATION OF THE EUROPEAN ELECTRICITY SYSTEM STARTS:
WHERE THE DIGITAL TRANSFORMATION OF THE EUROPEAN ELECTRICITY SYSTEM STARTS: European Network of Transmission System Operators for Electricity >> To guarantee the efficient operation of the end-to-end electrical
More informationWECC Criterion MOD-(11 and 13)-WECC-CRT-1.1
WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements
More informationReal-time Power System Operation. Energy Management Systems. Introduction
1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern
More informationIntelliGrid. Don Von Dollen IntelliGrid Program Manager (650)
IntelliGrid Don Von Dollen IntelliGrid Program Manager dvondoll@epri.com www.epri-intelligrid.com (650) 855-2679 Background EPRI s IntelliGrid Program Mission: To accelerate the transformation of the power
More informationVolt/VAR Control Options and How to Leverage AMI Data
By Tom Helmer, Executive Consultant and Joseph Sottnik, P.E., Project Manager, Black & Veatch Published in the August 2012 issue of PowerGrid International Energy efficiency and operational optimization
More informationA Modelica Power System Component Library for Model Validation and Parameter Identification
A Modelica Power System Component Library for Model Validation and Parameter Identification Luigi Vanfretti 1,2 Tetiana Bogodorova 1 Maxime Baudette 1 1:Smart Transmission Systems Lab. (SmarTS Lab), Electric
More informationD DAVID PUBLISHING. Integration of PSS E Web Application with Power System Simulation Platform. 1. Introduction
Journal of Mechanics Engineering and Automation 7 (207) 262-268 doi: 0.7265/259-5275/207.05.003 D DAVID PUBLIHING Integration of P E Web Application with Power ystem imulation Platform YU Hao, LIANG Xiaopeng
More informationGeneration Interconnection Feasibility Study Report
Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study
More informationRG-CE System Protection & Dynamics Sub Group
RG-CE System Protection & Dynamics Sub Group 17 April 2017 Contents Contents... 1 1. Introduction... 2 1.1 Normative reference...2 2. Dynamic Security Assessment... 3 3. Functional Architecture... 5 3.1
More informationUSE CASE 14 CONTROLLED ISLANDING
I USE CASE 14 CONTROLLED ISLANDING Use Case Title Centralized application separates grid into islands to prevent blackout Use Case Summary Controlled islanding is a method that can significantly improve
More informationOverview of Brunel University National Grid CIM Research Collaboration
Brunel Institute of Power Systems Overview of Brunel University National Grid CIM Research Collaboration Gareth Taylor Brunel University Nigel Hargreaves CIM Users Group, Windsor May 17 th 2012 EngD Environmental
More informationSCADA and Central Applications An introduction
SCADA and Central Applications An introduction Course map Outline of the lecture Power System Operation - Centralised Control Applications SCADA - SCADA architecture & Components - SCADA system functions
More informationPower System Network Simulator (PSNsim)
The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment
More informationPowerWorld s Experience Using Real-Time Power System Models
PowerWorld s Experience Using Real-Time Power System Models Presented by: James Weber, Ph.D. Director of Software Development February 28, 2018 2001 South First Street Champaign, Illinois 61820 (217) 384-6330
More informationLecture 5 Substation Automation Systems. Course map
Lecture 5 Substation Automation Systems 1 Course map 2 1 Contents of the Lecture Part 1 Substation Automation Components Substation Automation Functions Communication within the Substation (Intro) Part
More informationBoost Accuracy & Productivity
Expanded to Deliver Unsurpassed Performance Intelligence Reliability Boost Accuracy & Productivity Detailed Dynamic Simulation Rule-Based Time-Saving Capabilities Improved Performance 64-Bit Architecture
More informationCASE STUDY : Transient Stability Simulation Package
CASE STUDY : Transient Stability Simulation Package CLIENT NAME : A major T&D solutions provider in the world END CUSTOMER : A public T&D utility in one of the SAARC nations PROJECT TITLE : Customized
More informationRequirements for Model Validation
Draft Need Requirements Application for Model Validation Reporting Requirements for Model Validation Reporting for Generators and Generator Control Systems Revision 0 Wednesday 16 November 2005 Prepared
More informationApproval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9
PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6
More informationFINIST OPERATOR TRAINING SIMULATOR QUICK START REVISION 2.0 OF 01/18/2011
FINIST OPERATOR TRAINING SIMULATOR QUICK START REVISION 2.0 OF 01/18/2011 MONITOR ELECTRIC, 2011 FINIST: OPERATOR TRANING SIMULATOR Contents 1. About This Manual.. 8 1.1. Introduction...... 5 1.1.1. How
More informationDER leveraging IEC for the seamless and cost-effective integration of DER into the power system. IEC Europe 2017
DER leveraging IEC 61850 for the seamless and cost-effective integration of DER into the power system IEC 61850 Europe 2017 CONTENTS Part 1 Introduction, context Part 2 Case-study of three independent
More informationedart Quick Reference Guide
edart Quick Reference Guide Revision: 05 Effective Date: 08/16/2017 PJM 2017 Prepared by edart Project Team Table of Contents Table of Contents... 2 Revision History... 6 About the Quick Reference Guide...
More informationThis section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationMIGRATION PROCESS FROM UCTE DEF TO CGMES SECOND EDITION
MIGRATION PROCESS FROM UCTE DEF TO CGMES SECOND EDITION 24 OCTOBER 2016 PT CGM Page 1 of 18 ENTSO-E AISBL Avenue Cortenbergh 100 1000 Brussels Belgium Tel +32 2 741 09 50 Fax +32 2 741 09 51 info@entsoe.eu
More informationGridEye FOR A SAFE, EFFICIENT AND CONTROLLED POWER GRID
FOR A SAFE, EFFICIENT AND CONTROLLED POWER GRID SMART GRID VISION To solve today s energy and pollution problems, DEPsys believes that the world should be powered entirely by renewable energy. By applying
More informationOwner/Operator Forum 12 December
Owner/Operator Forum 12 December Steve Halsey DG Development Manager Today s Agenda Transition to DSO Breakout session What we do the role of the DNO Our vision Welcome and Introduction (DNO) Distribution
More informationAspects of Power System Modeling, Initialization and Simulation using the Modelica Language
Aspects of Power System Modeling, Initialization and Simulation using the Modelica Language Gladys León, Milenko Halat Marc Sabaté Aplicaciones en Informática Avanzada, S.L. Sant Cugat del Vallés, Barcelona,
More informationNERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016
NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons
More informationinovgrid to Smartlife April 2015
inovgrid to Smartlife April 2015 EDP started as a local incumbent and is now a truly global energy player Wind energy 25% of EBITDA IPO at Jun 08 Power: 8.1 GW # 3 world operator (in 11 countries) Company:
More informationCost of Electricity (CoE)
Cost of Electricity (CoE) Cost reduction Road to 40% reduction in CoE 2 June 2014 Christian Juul For External usage Reduction in cost is essential to make offshore wind competitive and reduce dependency
More informationPOWER SYSTEM SECURITY CONCEPTS
POWER SYSTEM SECURITY CONCEPTS 1.1 INTRODUCTION The Power System needs to be operationally secure, i.e. with minimal probability of blackout and equipment damage. An important component of power system
More informationNext Generation Scada Architectures
Next Generation Scada Architectures Jan Vorrink TenneT at a glance Europe's first cross-border grid operator 2,813 employees EBIT 725 (EUR million) Assets 13.645 (EUR billion) Investments (2014-23) 20
More informationSTCP22-1 Issue 003 Production of Models for GB System Planning
STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission
More informationLAB6 ADDITION OF GENERATION EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY
LAB6 ADDITION OF GENERATION EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY PURPOSE: The purpose of this lab is to introduce a wind farm into a base case and analyze the effects using PSS/E. Introduction
More informationLarge Embedded Generators Register of Completed Projects
Large Embedded Generators Register of Completed Projects This document contains a description of the completed projects relating to the connection of Large Embedded Generators to the TasNetworks distribution
More informationArkona Offshore Wind Project
Holger Matthiesen 04.12.2017 Arkona Offshore Wind Project Norwegian offshore wind delegation E.ON strategy Global trends like sustainability and climate protection, digitalization and technological innovation
More informationGrid Interconnection of Renewable Generation
Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection
More informationGeneration Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationVoltage control in MV and LV grid Distributed automation solution. Sami Repo Tampere University of Technology, Finland Coordinator of IDE4L project
1 Voltage control in MV and LV grid Distributed automation solution Sami Repo Tampere University of Technology, Finland Coordinator of IDE4L project 2 Content IDE4L project Problem of voltage control in
More informationEvolution of Control for the Power Grid
Evolution of Control for the Power Grid Anjan Bose Washington State University Pullman, Washington, USA University of Seville Seville, Spain June 17, 2016 THE INTERCONNECTED GRID Economics Transfer electric
More informationSMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2
SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:
More informationEDS SCADA NUMBERING SYSTEM
Document Number: EDS 05-9007 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 05-9007 SCADA NUMBERING SYSTEM This standard describes the system for numbering SCADA wiring within switchgear
More informationLearning Based Scheme for Islanding and Reconnection
1 Learning Based Scheme for Islanding and Reconnection Eduardo Cotilla-Sanchez Oregon State University with Carter J. Lassetter, Jinsub Kim This material is based upon work supported by the Department
More informationA perspective on European TSOs migration to CIM data exchange
Youssef AKEL A perspective on European TSOs migration to CIM data exchange CIM planning and operations exchanges seen from RTE Plan 1. Planning and operations data exchanges from RTE 2. Migration of data
More informationDRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models
DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models Problem Statement With the proliferation of distributed energy resources (DER), Transmission Planners must adapt
More informationDeveloping a Dynamic Smart Grid Model
European Association for the Development of Renewable Energies, Environment and Power Quality (EA4EPQ) International Conference on Renewable Energies and Power Quality (ICREPQ 12) Santiago de Compostela
More informationAwareness of the Situation
17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog
More informationRequirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company
Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents
More informationKEDS DSO Development Plan. George Karagutoff, KEDS CEO Prishtina, Kosovo 20 March, 2018
KEDS DSO Development Plan George Karagutoff, KEDS CEO Prishtina, Kosovo 20 March, 2018 1 INVESTMENTS AT A GLANCE KEDS begun its operations after the successful unbundling of Distribution and Supply business
More informationADVANCED SYSTEM ARCHITECTURE AND ALGORITHMS FOR SMART DISTRIBUTION GRIDS: THE SUSTAINABLE APPROACH
ADVANCED SYSTEM ARCHITECTURE AND ALGORITHMS FOR SMART DISTRIBUTION GRIDS: THE SUSTAINABLE APPROACH André MADUREIRA Ricardo BESSA Luís SECA INESC TEC Portugal INESC TEC Portugal INESC TEC Portugal andre.g.madureira@inesctec.pt
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December
More informationCIM and Harmonization
CIM and 61850 Harmonization Herbert Falk Solutions Architect SISCO Common Information Model in Smart Grid, Distribution, Transmission Workshop September 9, 2010 The Holy Grail Asset Connectivity An audience
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationSouthern Company Smart Grid
Southern Company Smart Grid Smart Grid Investment Grant Update July 25, 2011 Southern Company Southern Company is one of the nations largest generators of electricity Has 4.4 million retail customers across
More informationEnergy Security: A Global Challenge
A presentation from the 2009 Topical Symposium: Energy Security: A Global Challenge Hosted by: The Institute for National Strategic Studies of The National Defense University 29-30 September 2009 By SCOTT
More informationProcedures for cross-border transmission capacity assessments PROCEDURES FOR CROSS-BORDER TRANSMISSION CAPACITY ASSESSMENTS.
PROCEDURES FOR CROSS-BORDER TRANSMISSION CAPACITY ASSESSMENTS October 2001 1/13 Table of contents 1 INTRODUCTION... 4 2 GENERAL GUIDELINES... 5 3 BASE CASE CONSTRUCTION... 6 3.1 NETWORK MODEL... 6 3.1
More informationBattery Energy Storage System Information Modeling Based on IEC 61850
Journal of Power and Energy Engineering, 2014, 2, 233-238 Published Online April 2014 in SciRes. http://www.scirp.org/journal/jpee http://dx.doi.org/10.4236/jpee.2014.24033 Battery Energy Storage System
More informationPublic Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM
Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities
More informationEffect of Topology Control on System Reliability: TVA Test Case
Effect of Topology Control on System Reliability: TVA Test Case Professor Kory W. Hedman School of Electrical, Computer, and Energy Engineering Arizona State University Tempe, AZ 85287-5706 CIGRE, October
More informationSystem Studies for American Transmission Co. s Benson Lake SVC Project
Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC Outline Introduction
More informationEnedis, Distribution System Operator (DSO) heading towards the future
Enedis, Distribution System Operator (DSO) heading towards the future Update : August 2018 ENEDIS, the main DSO in France : key figures (2017) 38 703 EMPLOYEES 11,4 ANNUAL TURNOVER 14 083 MILLION EUROS
More informationStrategy Consulting Digital Technology Operations. Transmission Distribution SCADA Separation 2017 EMMOS Conference
Strategy Consulting Digital Technology Operations Transmission Distribution SCADA Separation 2017 EMMOS Conference SCADA for Electric Utility Operations The SCADA platform is at the heart of Electric Utility
More information