Gumeni Substation 132kV loop in lines. Northern Ngwedi Substation Ngwedi Substation Build new 400kV substation and install 2 x 500 MVA Transformers
|
|
- Piers Waters
- 6 years ago
- Views:
Transcription
1 Eskom Holding SOC Ltd. - List of Eligible Sub-Projects *Updated December 2015* Projects added since the previous disclosure are highlighted in yellow. Grid Scheme Project High level scope of project Northern Hendrina Prairie Marathon (Lowveld Strengthening Phase 2) Gumeni Substation Build new 400kV substation and install 1 x 500 MVA Transformer, including 132kV loop in lines Northern Ngwedi Substation Ngwedi Substation Build new 400kV substation and install 2 x 500 MVA Transformers Northern Borutho Substation Borutho Substation Build new 400kV substation and install 2 x 500 MVA Transformers Line (Loop-in Loop-out) Install 5.473Kms of line Tshwane strengthening Thuso Substation Build new 400kV substation and install 2 x 250 MVA Transformers Apollo Substation Disassemble old 275kV Substation & 275kV line to Apollo Waterberg Spitskop substation Marang substation Upgrade fault levels to integrate Waterberg Upgrade fault levels to integrate Waterberg Vaal Strengthening phase 1 Vaal 1 Remaining refurbishment work of 2 feeders at Glockner and 132kV yard at Bernina. Minor works at Hera & Taunus substations Kookfontein 3rd Transformer Line Substation Install 2.501Km line to Glockner substation Install 315MVA transformer Avon (IPP) Avon Substation Interconnection to IPP - Feeder and Bus Section Simmerpan Strengthening Phase 1A Substation Line Build a new 88 kv yard and dismantle & remove the existing/old 88 kv yard. Refurbish the existing ± 5km 275kV line from Jupiter - Simmerpan.
2 Hydra Omega Section A Section B Section C Build 60 km of line Build 60 km of line 60 km of line Sterrekus substation New substation, installation of 2000MVA trfr Fully equip 132 kv Transformer 1 Bay Foskor Substation Modify Transformer 3 bay for the new 275/132k V Transformer and replace some equipment. Foskor-Acornhoek Decommission 132 kv Transformer 2 Bay Fully equip 275kV Transformer 1 Bay Acornhoek Substation Modify Transformer 3 bay for the new 275kV Transformer and replace some equipment. Decommission 275kV Transformer 2 Bay Nieuwehoop Substation Construction of transformer Bay, 2 Bus Coupler, 2 Feeder bays, B/B Reactor and line reactor Aries - Nieuwehoop Aries Substation 1 Feeder Bay Aries- Nieuwehoop line 80km of 400kV line Grassridge Substation Construction of 132kV Feeder 16 with double busbar selection, 3 x -Busbar Extension bays, 1 x 132kV Overpass Bay Grassridge - Dedisa Strengthening Dedisa Substation Construction of 132kV Feeder 2 with double tubular busbar selection Grassridge - Dedisa 132kV line Construct 8.3km line
3 Dedisa Substation Install 4x 400kV 100MVAr capacitor banks. PE Strengthening Poseidon Substation Grassridge Substation Install 4x Fully equip capacitor bank bays with double busbar selection. Construct Tubular Busbar extension at Dedisa Substation only. Delphi Substation Ankerlig Plant Replacement Ankerlig Reinsulation Replacing only the Surge Arrestors Garona SS Strengthening Cuprum Garona Substation Kronos Substation Equipping 400kV Transformer bay and building a new 132kV HV Yard. Substation Reinsulation Substation Reinsulation Insulator replacement and RTV Silicone Coating Amakhala Emoyeni (IPP) Amakhala Emoyeni Khobab Wind Farm Integration at Helios (IPP) Loeriesfontein Wind Farm Integration at Helios (IPP) Khobab Wind Farm Integration at Helios (IPP) Loeriesfontein Wind Farm Integration at Helios (IPP) To build a new 132kV yard and equip a 132kV feeder bay (feeder 7) at Poseidon 400/220/132/66kV Dedicated strengthening scope: Establish 2 x 132 kv feeder bays. Shared strengthening scope: 400kV Yard: Extend the 400kV busbar, Install and commission a 400kV Transformer bay, Install and commission a 500MVA 400kV/32kV transformer. 132kV Yard: Install busbar 1 and busbar 2, Install and commission a 132kV transformer bay, Install and commission a bus coupler bay. Bloemfontein Strengthening p1 Firgrove/Pinotage New TS New Firgrove Substation - Establish a new 132 / 400kV, 2 x 500 MVA substation near existing Firgrove distribution substation. 400 kv Line - Loop in, Loop out Palmiet/Stikland Transmission line (0.6km)
4 Hydra Longyuan Mulilo Maanhaarberg 96.5 MW WEF (IPP) and Hydra Longyuan Mulilo Plateau North 139 MW WEF (IPP) Network shared cost scope of work at Hydra at MTS 132kV Network - Busbar extension, 1 x fully equipped bus coupler bay, 2 x fully equipped bus section bays, 1 x fully equipped transformer bay with double busbar selection, Upgrade the existing 132kV busbars, 1 x 132kV Overpass for existing feeder 9 Bletterman, 275kV Main Steelwork to create overpass over new 132kV yard, 1 x feeder 1 Brittsville replace existing 132kv breaker, 1 x feeder 3 Cuprum 1 replace existing 132kV breaker, 1 x feeder 5 Chameleon replace existing 13kV breaker, 1x feeder 7 Roodekuil replace existing 132kV breaker, 1 x feeder 8 Bushbuck replace existing 132kV breaker, 1 x feeder 9 Bletterman replace existing 132kV breaker, 1 x Transformer 2 replace existing 132kV breaker and 1 x Transformer 3 replace existing 132kv breaker. 400kV Network - Busbar Extension - 1 x fully equipped bus section bay, 1 x fully equipped transformer bay with double busbar selection, 1 x feeder 4 Droervier 3 replace existing 400kV breaker, 1 x feeder 5 Beta 1 replace existing 400kV breaker, 1 x feeder 7 Droerivier 1 replace existing 400kV breaker,1 x feeder 9 Perseus 3 replace existing 400kV breaker, 1 x 500MVA 4000/132kV Transformer, Commissioning of new infrastructure Dedicated scope of work at Hydra MTS for Maanhaarberg and Plateau - Equip 2x 132kV feeder bay and commissioning of new infrastructure Mulilo Prieska PV (PTY) LTD integration at Kronos (IPP) Mulilo Sonnedex PV (PTY) LTD Integration at Kronos (IPP) Dedicated strengthening scope - Establish 2x132kV Feederbays Shared strengthening Scope kv Busbar extension and general civil works Namaqualand/Gromis- Oranjemund Gromis-Oranjemund line: 130km 400kV trip tern line (operated at 220kV) from Gromis to Oranjemond. Gromis substation: 220kV feeder bay Reconfigure Fdr 2 & 3 to double busbar selection. Oranjemund substation: 220kV feeder bay Reconfigure Fdr 2 & 3 to double busbar selection. Meet N-1 Grid code compliance.
5 JHB North Phase 2a: Lepini Ext 275kV 2x Implementation of 2 x 150 MVAR 275kV Shunt Capacitors Nojoli 86.6MW Wind Farm Project at Poseidon (IPP) IPP integration Bloemfontein 1B: Everest Merapi line Everest - Merapi 275kV transmission line as well as the 275kV feeder bays at Everest and Merapi substations. Highveld South Reinforcement Phase 1 : Sol MTS Install 4 x FCLR's Install a temporary 5th transformer Dedisa OCGT Dedisa OCGT Stikland Plant Replacement Stikland Reinsulation Replacing only the Surge Arrestors 1 x isolator with earth blade and current transformer with provision for future circuit breakers on each busbar
Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationSTCP 04-3 Issue 005 Real Time Data Provision
STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationABB static var compensator stabilizes Namibian grid voltage
Power ABB static var compensator stabilizes Namibian grid voltage factor! Rolf Grünbaum, Mikael Halonen, Staffan Rudin The spectacular dune landscapes of Namibia are a key factor in the country s booming
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationBluenergy operates in the renewable energy and in the electrical infrastructure construction and maintenance sectors.
1 BLUENERGY BACKGROUND Introduction Bluenergy Africa Industrial (Pty) Ltd (Bluenergy) owns 100% of the equity of PLC Sub Sahara Limited and PLC South Africa Service (Pty) Ltd (PLC SA Service). Bluenergy
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationPower Transmission Division Link between power generation and distribution
Power Transmission Division Link between power generation and distribution Seite 4 High Voltage Substations Schemes, Devices and Types of AIS Installation Content Link between power generation and distribution
More informationOTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER
Parsons Brinckerhoff Associates OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER A report prepared for 23 March 2007 Disclaimer Notice Report for
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationSmart Distribution Technology
Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications
More informationHIGH VOLTAGE CONTRACTORS. Winnipeg The Pas Snow Lake - Thompson
HIGH VOLTAGE CONTRACTORS Winnipeg The Pas Snow Lake - Thompson DESIGN BUILD MAINTAIN AMPS Powerline Incorporated is a high voltage electrical service provider of choice for new high voltage electrical
More informationEU DONOR FUNDED SMART GRID PROGRAMME
EU DONOR FUNDED SMART GRID PROGRAMME 1 Historical Background Msunduzi Local Municipality is a local municipality in Umgungundlovu District Municipality, KwaZulu-Natal, South Africa. It encompasses the
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationUPDATES EPC Contract Signed August 2017
ACO SOLAR HV BOP PROJECT NUMBER 2655 Convalt Energy LLC MOEE Myanmar Power Generation, Substation UPDATES EPC Contract Signed August 2017 Convalt Energy LLC are developing a 300MW AC solar farm in Myanmar
More informationCollector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co.
Collector System Design Considerations for Wind Farms Sean Carr Ernst Camm S&C Electric Co. 1 Overview Challenges in wind farm collector systems Design considerations for collector systems Summary The
More informationABB Surge Arresters Contribution to Power Quality Line Side Protection
James Taylor, Technology Support Manager / Principal Specialist May 2013 ABB Surge Arresters Contribution to Power Quality Line Side Protection May 6, 2013 Slide 1 Availability of electric power supply
More informationUpdates and Modifications to Report
QUARTERLY COMPLIANCE REPORT (APRIL 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision
More informationPSSS/PSAC Engineering, Muhammad Adil, Substation Automation Systems. ABB Group October 29, 2014 Slide 1
PSSS/PSAC Engineering, Muhammad Adil, 30-10-2014 Substation Automation Systems October 29, 2014 Slide 1 CONTENT INTRODUCTION IEC61850 ABB s BAY LEVEL SOLUTIONS ABB s STATION LEVEL SOLUTIONS ABB s AS A
More informationGeneration Interconnection Impact Study Report. For. Interconnection Customer Q0022
Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer
More informationEDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES
Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-0150 LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES LPN This standard provides guidelines for the development of the 33kV distribution
More informationSacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,
Sacramento Municipal Utility District SMUD May 10, 2010 1 SMUD Facts and Figures 900 Sq. Miles Service Area 585,500 Customers 1.4 million Area Population 10 Bulk Substations 473 Miles of Transmission Lines
More informationReal Time Digital Simulator Testing of an On Line Integrated Stability Control System
Real Time Digital Simulator Testing of an On Line Integrated Stability Control System R.P. Wierckx, M. Kawasaki, N. Saito, K. Anzai, S.C. Verma Abstract The paper describes the testing of an on line integrated
More informationOutage Management System Pilot Roll-out: Division User Manual
Outage Management System Pilot Roll-out: Division User Manual February 2017 Table of Contents 1. Outage Management System... 2 1.1. Overall Objective... 2 1.2. Outage Categories... 2 1.3. Division User
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationCONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]
Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected
More informationIEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems
Alexandre Oudalov, ABB Switzerland Ltd., Corporate Research, 2014-04-30 Microgrid Protection IEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems Microgrid Protection
More informationProtection and Control REX640 Product Presentation
ABB OY DISTRIBUTION SOLUTIONS Protection and Control REX640 Product Presentation 1MRS758996 A Product introduction Protection and Control REX640 All-in-one protection for any power distribution application
More informationAgenda for the Meeting of Southern Region constituents regarding Connectivity/LTA Applications of IPPs in SR received during November & December, 2016
Agenda for the Meeting of Southern Region constituents regarding Connectivity/LTA Applications of IPPs in SR received during November & December, 2016 (To be discussed along with Agenda for Follow up Meeting
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationGeneration Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationTitle System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)
Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards
More informationFACTS and HVDC for Grid Connection of Large Wind Farms
David Larsson Power-Gen Europe 2005 Milan, Italy FACTS and HVDC for Grid Connection of Large Wind Farms www.abb.com/facts FACTS Agenda Wind Generators Response to Grid Faults PICTURE JPG-FORMAT WEB OPTIMIZED
More informationSTCP22-1 Issue 003 Production of Models for GB System Planning
STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission
More informationProgress Report on the GCC Electricity Grid Interconnection in the Middle East
GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Progress Report on the GCC Electricity Grid Interconnection in the Middle East by: Adnan Al-Mohaisen, GM, GCCIA Luc Chausse, Project Director, SNC-Lavalin
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationASSET RISK MANAGEMENT Criticality Framework
ASSET RISK MANAGEMENT Criticality Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to
More informationAwareness of the Situation
17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog
More informationp. 1 p. 9 p. 26 p. 56 p. 62 p. 68
The Challenges and Opportunities Faced by Utilities using Modern Protection and Control Systems - Paper Unavailable Trends in Protection and Substation Automation Systems and Feed-backs from CIGRE Activities
More informationCampus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE
Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Key Factors of Resilient Electrical
More information1. Project Description
Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal
More informationAUAS SVC, PERFORMANCE VERIFICATION BY RTDS AND FIELD TESTS. S. Boshoff C. van Dyk L Becker M Halonen, S Rudin, J Lidholm Dr T Maguire
AUAS SVC, PERFORMANCE VERIFICATION BY RTDS AND FIELD TESTS S. Boshoff C. van Dyk L Becker M Halonen, S Rudin, J Lidholm Dr T Maguire S Boshoff Consulting TAP NamPower, ABB Power Systems, Sweden RTDS, Canada
More informationCOMPANY PROFILE
COMPANY PROFILE www.khweza.co.za Introduction Khweza Imikhono Khweza Imikhono (Pty) Limited is a black woman-owned company which operates in the area of infrastructure expansion projects. The company implements
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationSCADA Training - T&D Automation
SCADA Training - T&D Automation Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq This course covers all the
More informationSapphire Wind Farm 330/33kV Substation
Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationNERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016
NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons
More information115 kv / 34.5 kv Solar Power Plant / Substation
115 kv / 34.5 kv Solar Power Plant / Substation Project Plan MAY1602 INDUSTRY CLIENT: ADVISORS: TEAM EMAIL: TEAM: Black and Veatch Corporation Venkataramana Ajjarapu, Anne Kimber may1602@iastate.edu Chase
More informationImplementation of a Power Line Carrier solution to support anti-islanding protection and reduce interconnection costs for Distributed Generation
Implementation of a Power Line Carrier solution to support anti-islanding protection and reduce interconnection costs for Distributed Generation Jorge Valenzuela Cleveland, Oct 2017 Background NG Solar
More informationIMP/ 001 / 014 Policy for the Protection of Distribution Networks
Version:- 1.1 Date of Issue:- July 2016 Page 1 of 39 IMP/ 001 / 014 Policy for the Protection of Distribution Networks 1. Purpose The purpose of this document is to detail the network protection philosophy
More informationSubstation Automation Products. High impedance differential busbar protection REB650 Relion 650 series
Substation Automation Products High impedance differential busbar protection REB650 Relion 650 series One IED for a wide range of high impedance differential protection applications ABB introduces a new,
More informationThe Efficient Way. SVC PLUS Innovation meets experience. Answers for energy.
The Efficient Way SVC PLUS Innovation meets experience Answers for energy. Enhancement of Grid Efficiency Improved dynamic stability and power quality of power systems in a new, highly economical manner
More informationPortable Power Solutions
http://siemens.com/energy/portable-power-solutions Portable Power Solutions Plug and play High Voltage E-Houses, skids and mobile high voltage substations up to 420 kv Plug & play solutions for flexible
More informationSCADA SYSTEM FOR PEDEEE SYRIA PROJECT
SCADA SYSTEM FOR PEDEEE SYRIA PROJECT TYPE MS-TDPRO32 OPERATION MANUAL Copyright 2010 - Microener Pag 1 of 26 INDEX 1 General features and installation directions 3 1.1 Installation 3 1.2 Hardware Configuration
More informationHugo E. Meier, Heidelberg, Germany, June 2014 Integrator Partner Seminar2014 Substation automation trends
Hugo E. Meier, Heidelberg, Germany, June 2014 Integrator Partner Seminar2014 Substation automation trends Substation automation trends Contents Product Portfolio Trends in substation automation Cyber Security
More informationCOMPACT SUBSTATION WITH 34.5kV GIS (GAS-INSULATED SWITCHGEAR. Cleverson Shindi Takiguchi S&C Electric Europe LTd. Cape Town/WC South Africa
COMPACT SUBSTATION WITH 34.5kV GIS (GAS-INSULATED SWITCHGEAR Cleverson Shindi Takiguchi S&C Electric Europe LTd. Cape Town/WC South Africa Alexandre Taijun Ohara S&C Electric Company Curitiba/PR Brazil
More informationRequirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company
Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents
More informationBenefits, offering and references
DOC ID: 9AKK107045A9180 DISTRIBUTION SOLUTIONS Digital medium-voltage switchgear Benefits, offering and references Contents Digital switchgear for medium-voltage applications Digital switchgear definition
More information2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning
Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities
More informationSolution Renewables. tgood.com
Solution Renewables tgood.com TGOOD Introduction TGOOD is the global leader in prefabricated electric power distribution solutions. It is the company that first comes to mind when cost-effective electric
More informationSystem Studies for American Transmission Co. s Benson Lake SVC Project
Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC Outline Introduction
More informationClearView SCADA Benefits
ReLab Software s ClearView SCADA is a true out-of-the-box solution with all the components necessary for deployment in substation automation and control room applications. ClearView is built for the time
More informationPROTECTION, AUTOMATION & CONTROL
PROTECTION, AUTOMATION & CONTROL 1. DTIVA The members of the DTIVA product line are configured to protect and control the elements of not solidly grounded radial networks. Here the application of Petersen
More informationUpdates and Modifications to Report
QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationApproval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9
PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6
More informationCompany Introduction and Overview
Company Profile Company Introduction and Overview Brandis Industries Pty Ltd is a Queensland owned and operated Specialist Electrical Service Provider to the High Voltage Electrical Power Industry with
More informationPower System Network Simulator (PSNsim)
The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment
More informationABB AG - EPDS. Gas-insulated switchgear Type ZX2
ABB AG - EPDS Gas-insulated switchgear Medium voltage switchgear Single or double busbar systems 12 kv, 2500 A, 40 ka 24 kv, 2500 A, 40 ka 36 kv, 2500 A, 40 ka Slide 2 Medium voltage switchgear With IAC
More informationHigh and Medium Voltage Substation Design, Testing and Maintenance. KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel.
Training Course : High and Medium Voltage Substation Design, Testing and Maintenance Training Course For One Week In KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel Which Be Held As Under Details : Tel.
More informationKarl Iliev, San Diego Gas & Electric Company
INTEGRATING DER THROUGH DISTRIBUTION SYNCROPHASORS Karl Iliev, San Diego Gas & Electric Company 2002 San Diego Gas and Electric Co. and Southern California Gas Company. All copyright and trademark rights
More informationUndergrounding power lines- the great challenge
Undergrounding power lines- the great challenge 1 Calculation of 1. short-circuit currents. To be revised! 2. temporary overvoltages. 3. electromagnetic transients 1 Undergrounding power lines and the
More informationBusbar protection REB 670
Gunnar Stranne Busbar protection REB 670 Rio de Janeiro April 23-25, 2006 ABB Power Technologies AB 2 3 4 REB 500 is enabled for use with IEC61850 communication Benefits of REB 670 outstanding features
More informationPower Systems Communications Implementation of IEC61850 in a Substation Environment
Power Systems Communications Implementation of IEC61850 in a Substation Environment 26 October 2009 Reference VEE4700-01 Revision 0 Document Control Document ID: DOCUMENT1 Rev No Date Revision Details
More informationLAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY
LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY PURPOSE: The purpose of this lab is to introduce PSS/E. This lab will introduce the following aspects of PSS/E: Introduction to
More informationMedium Voltage Metal-Enclosed Power Capacitor Banks
66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Power Capacitor Banks General Northeast Power System s (NEPSI's) medium
More informationAutomation System Solutions
Automation System Solutions Automation Systems for Power Grid, Power Plant and Industries NR Electric Corporation Automation for Power Grid Substation Automation System Conventional Substation Automation
More informationNational Load Despatch Centre Power System Operation Corporation
Module on Procedure for Data Collection National Load Despatch Centre Power System Operation Corporation Background Algorithms/ Processes AC Load flow and transmission losses Slack bus determination- Average
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved
More informationMarch 4, Mona Substation Line position & assoc relaying, communications & metering
700 N.E. Multnomah, Suite 550 Portland, OR 97232 March 4, 2004 Merrill Brimhall PacifiCorp Merchant 201 South Main, Suite 2200 Salt Lake City, Utah 84111 Dear Mr. Brimhall: PacifiCorp Transmission Systems
More informationMedium Voltage Metal-Enclosed Harmonic Filter Systems
66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Harmonic Filter Systems General NEPSI s armorvar, medium voltage metal-enclosed
More informationEXPERIENCE WITH IEC IN THE REFURBISHMENT OF AN IMPORTANT EUROPEAN 380 KV SUBSTATION. Switzerland
21, rue d Artois, F-75008 PARIS B5-109 CIGRE 2006 http : //www.cigre.org EXPERIENCE WITH IEC 61850 IN THE REFURBISHMENT OF AN IMPORTANT EUROPEAN 380 KV SUBSTATION S. LAEDERACH* 1, W. BAASS 2, K.P. BRAND
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution
More informationMemorandum. This memorandum requires Committee action.
California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure
More informationABB AG Calor Emag Medium Voltage Products Gas-insulated switchgear Type ZX2. ABB Gas-insulated switchgear type ZX2 1
ABB AG Calor Emag Medium Voltage Products Gas-insulated switchgear 17.02.2015 Gas-insulated switchgear type ZX2 1 Medium voltage switchgear type ZX2 Single or double busbar systems 12 kv, 2500 A, 40 ka
More informationPresented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011
Photovoltaic Solutions Make the most of your solar PV project Presented by: Oscar Araujo Photovoltaic Solutions Manager 4 th Canadian German Solar PV Conference March 2 nd 2011 Agenda Solutions for Renewable
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationA guide on PowerWorld Simulator ver. 12.0
A guide on PowerWorld Simulator ver. 12.0 This tutorial has been developed to aid the undergraduate and graduate students at the University of Cyprus to learn the basic features of PowerWorld. It is not
More informationPurpose of High Voltage Circuit Switchers
Purpose of High Voltage Circuit Switchers Vertical interrupter circuit switcher without integral disconnect switch (Figure 2) Three-phase Interruption and Protection Circuit switchers have been developed
More informationRelevant Electrical Standards (RES) Grid Code Review Panel January 2014
Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same
More informationTransmission Infrastructure Investment & Development in Vietnam
Transmission Infrastructure Investment & Development in Vietnam Presented by: Mr. Cao Duc Dung Expert of Technical Department National Power Transmission Corporation (NPT) 28 September, 2011 1 CONTENTS
More informationOptimized MV Generator Power Plant Architectures for Large Data Centers
Optimized MV Generator Power Plant Architectures for Large Data Centers White Paper 262 Revision 0 by Julien Moreau Malik Megdiche Daniel Radu Executive summary For large (>5 MW) data center applications,
More informationGAS. POWER. WATER. TELCO. POWER
GAS. POWER. WATER. TELCO. POWER Who is Zinfra? Zinfra is a leading power, gas, water and telco infrastructure service provider. We offer a comprehensive range of engineering, construction and maintenance
More informationSubstation SCADA Monitoring
Substation SCADA Monitoring Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Substations are a critical component
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationMicrogrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids
Enrico Ragaini (ABB Low Voltage Products), Alexandre Oudalov (ABB Corporate Research), ISGT Europe 2012, Berlin Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids
More informationOC IEEE IAS/PES Meeting February 21, 2013
San Diego International Airport: Building For The Future, Through Underground Distribution Automation and SCADA OC IEEE IAS/PES Meeting February 21, 2013 1 Presenter: Randy Denton, PE Under Ground Utility
More informationSWITCHYARD SYSTEM BC1-SS-11-SD TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1
SWITCHYARD SYSTEM TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1 November 2011 PREFACE This Training System Description has been designed to assist you in meeting the requirements of Module BC1-SS-11
More information