Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Size: px
Start display at page:

Download "Capital Rail Constructors: Quarterly Update to MWAA Board of Directors"

Transcription

1 Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2017

2 Agenda 1. Safety 2. Schedule 3. Progress 4. Labor Statistics 5. DBE Subcontracts

3 Scope

4 Safety Since Notice to Proceed: Manpower Hours: 3,280,898 (As of 12/23/2016) Recordable Rate: 0.97 (vs. National Average: 3.30) Lost Time Rate: 0.06 (vs. National Average: 1.70) Current Program Focus: Work adjacent to traffic and within Maintenance of Traffic (MOT) areas Mobile equipment Energized Systems

5 Design Status Design Status Overall: 99% Complete Geotechnical Work 100% Complete Field Survey Work 100% Complete Track Design 100% Complete Systems Design 100% Complete Civil Design 100% Complete Utilities Design 100% Complete Facilities Design (Stations) 99% Complete Wayside Design 100% Complete Structures Design (Aerial Guideway/3 Bridges) 100% Complete

6 Overall Project Status Design and Construction: 52.3% Construction Status: 48.1% Design Status: 99.9%

7 Project Progress Cost Percent Completion Curves by Discipline Entire Project (Base Contract) 12/15/2016

8 Aerial Guideway: Shafts/Columns/Caps 197 of 197 Shafts: 100% Complete 137 of 137 Round Columns: 100% Complete 54 of 54 Rectilinear Piers: 100% Complete 103 of 103 Caps: 100% Complete

9 Aerial Guideway: Girders 561 of 622 Girders Fabricated (90%) 474 of 622 Girders Installed (76%)

10 Aerial Guideway: Decks 109 of 177 Decks Poured (62% Complete)

11 Aerial Guideway: Straddle Bents 6 of 8 Straddle Bents Poured (75%)

12 Facilities: Herndon Station Precast (Ongoing) Jul 2016 Jan 2017 Steel Erection Jan 2017 Mar 2017 Mechanical/Electrical/Plumbing Rough-In Jan 2017 Summer 2017

13 Facilities: Reston Town Center Station Precast (Ongoing) Oct 2016 Mar 2017 Steel Erection Mar 2017 May 2017 Mechanical/Electrical/Plumbing Rough-In Jan 2017 Summer 2017

14 Facilities: Innovation Center Station Mechanical/Electrical/Plumbing Rough-In Ongoing Ceiling Rough-In Ongoing Roofing, Skylights Start Jan 2017 Platform Work Start Spring 2017

15 Facilities: Dulles Airport Station Precast & Steel (Ongoing) Sep 2016 Jun 2017 Tunnel Demolition Complete Concrete Masonry Unit Walls Ongoing Mechanical/Electrical/Plumbing Rough-In Ongoing Roofing Start Jan 2017

16 Facilities: Loudoun Gateway Station Cast-In-Place Concrete (Ongoing) Complete Feb 2017 Precast & Steel Jan 2017 Jun 2017

17 Facilities: Ashburn Station Enabling Work (Complete) Aug 2016 Nov 2016 Excavation & Foundations Nov 2016 May 2017 Precast & Steel Apr 2017 Oct 2017

18 Pedestrian Bridges and Pavilions Pedestrian Bridge Drilled Shafts 8 of 32 Pedestrian Bridge Columns 3 of 21 Pedestrian Bridge Caps 2 of 21 Pavilion Concrete Ongoing: Innovation South, Herndon South, Reston North Pedestrian Bridge Span Deliveries & Assembly: Innovation Spans 5 & 8 Pedestrian Bridge Erection start Feb 2017

19 Civil: Wayside Ductbank TPSS 15 Wayside: Active, building set. TPSS 15 Median: Complete TPSS 14 Wayside: Active, complete Q1 TPSS 14 Median: Complete TPSS 13 Wayside: Complete TPSS 13 Median: Active, complete Q1 TBS 6 Median & Wayside: Active, complete Q1 TPSS 12 Wayside: Active TPSS 12 Median: Complete Q TBS 6 Wayside: Start in next 30 days TBS 7 Wayside: Start Jan 2017 TPSS 17 Wayside: Active, complete Q1 TBS 9 Wayside: Start after TBS 10 TBS 10 Wayside: Start Q1 TPSS 18 Wayside: Start Q1 TPSS 18 Median: Active, complete Q1 TBS 11: Start Q2 TPSS 19 Wayside: Active, complete Q1 TPSS 19 Median: Start Q1 TPSS 20 Wayside: Start Q1 TPSS 20 Median: Active, complete Q2 TBS 8: Start Q2-Q3

20 118 of 172 Manholes installed 42,043 of 62,300 duct bank installed N07: Tie in to Phase 1 N08: Clean manholes and proof duct N09: North of Innovation Station complete Q1, clean manholes and proof duct. TPSS 15 to Route 28 connection turned over to DVP for cable install. N10: Rudder Rd, Autopilot Drive, Cargo 4 to Dulles Station complete Q2 N97: Greenway Median East of 606 bridge; Connection to Package B Underneath Horsepen Lake N11 & N12: Broad Run bridge to TPSS 20: Active, complete Q2 Civil: 34.5 kv Ductbank

21 Civil: Utility Crossings Utility Crossing Remaining Work: N11 & N12 Jack & Bores to be completed in Q1: 3 storm, 3 at TBS #8, 3 in yard leads under streams Directional Drill: Beneath Horsepen Lake complete Q1. Airport bores start Q1 Hand Mine: 2 at 606 Station North, 1 at Herndon Station, 1 partial at Reston Station

22 Civil: Storm Drainage Storm/Wet Utilities Upcoming Work: N07: Reston Station interior storm Q2 N08: Herndon Station interior storm Q1, Herndon South C/D Ramp Q1-Q2, DIAAH/DTR median storm Q1-Q2 N09: Innovation N. Pavilion Q1, DIAAH/DTR median storm Q1-Q1 N10: Adjacent to Dulles Station. N96: Pier drain splash pads N97: TPSS #18 to 606 bridge Q1-Q2 N11: 606 North Pavilion 90% complete N11 & N12: Broad Run to 772 Station active Q1-Q2, North 772 pavilion active, South 772 pavilion Q1

23 Civil: Trackwall East Segment remaining work 7,250 : Herndon and Reston Station tie-in s, Phase 1 connection, under Fairfax County Parkway. Complete all footers by end of Q1. West Segment start Q1, N97 tall walls started near abutments in median

24 Civil: Grading/Excavation/Paving Upcoming Work: N07: 48 water line protection slab Q1 N08: Centreville to Monroe turned over to Track. South Herndon utility relocations and grading in Q1 N09: Abutment A to Horsepen turned over to Track N97: Track wall excavation and undercut N12: Ashburn South Pavilion excavation and site work

25 Track: Cable Trough CIP Cable Trough Wall in Forms Span 70 Setting Precast Cable Trough between Centerville and Monroe Precast Cable Trough Installed: 18,400 of 85,730 linear feet Cast-in-Place Cable Trough Poured: 6,128 of 38,520 linear feet

26 Direct Fixated Track Plinth: 7,100 of 37,178 track feet poured Track: Direct Fixated (DF) Plinths DF Track Construction Span 98/99 DF Track at TPSS 17

27 Track: Ballasted Dumping Initial Ballast West of Horsepen Stockpiling Continuously Welded Rail (CWR) Strings West of Monroe Welded N08 & N09 rail Placing ballast between Abutment A and Horsepen Bridge

28 Facilities/Systems: Traction Powered Substations (TPSS) TPSS 15: Building set; Rough-in and installation; first section of 34.5 kv cable has been pulled to TPSS 15 TPSS 13 Slab poured. Building installation: Jan kv Ductbank installation: TPSS 12, 14, 17, 18, 19, 20, and TBS 6, 9, TBS 10 Ongoing Electrical Grounding: Bridges/Track Wall/Dulles Station Aerial Pier Ongoing

29 Manpower Hours September November 2016 Manpower Hours September 2016 October 2016 November 2016 Professional Staff 46,191 45,499 44,288 Craft Labor CRC & Subcontractors 127, , ,463

30 Labor by Race/Ethnicity September 2013 to December 15, 2016 Total Hires African American Asian Caucasian Hispanic Other # % # % # % # % # %

31 Labor by State September 2013 December 15, 2016 Virginia Maryland District of Columbia Other % % % % September 2013 December % 2.69% 12.47% *includes Pennsylvania, West Virginia and all other states.

32 DBE Status 0

33 Local Employment Outreach Program September November 2016 WEEKLY Job Opportunity Trailer SW Washington, DC 09/12/16 Prince George s County: Veterans Job & Resources Fair 09/13/16 Loudoun County Construction Job Fair 09/20/16 Greater Washington Urban League Job Development Workshop and Training Greater Washington Urban League Employment Outreach

34 Local Employment Outreach Program DC Work Hours Since Program Inception to December 15, , DC Work Hours ,584 26, * From January 2016 August 24, 2016

35 Change Orders DRB Establishment Next Steps:

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors October 2016 Agenda 1. Safety 2. Schedule

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2016 Agenda 1. Safety 2. Schedule

More information

# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report

# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM Date of Meeting: May 2, 2017 # I-2 SUBJECT: Quarterly Metrorail Construction Status Report ELECTION DISTRICTS: Ashburn/Broad Run STAFF CONTACTS: Alan

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM Date of Meeting: # 9 SUBJECT: ELECTION DISTRICTS: STAFF CONTACTS: Public and Private Infrastructure Improvements Adjacent to the Dulles

More information

Microsoft Office Project and Project Server Reporting. June 24 th, 2009 Rich Weller, MBA, PMP, MCTS, MCITP Principal Consultant, Pcubed

Microsoft Office Project and Project Server Reporting. June 24 th, 2009 Rich Weller, MBA, PMP, MCTS, MCITP Principal Consultant, Pcubed Microsoft Office Project and Project Server Reporting June 24 th, 2009 Rich Weller, MBA, PMP, MCTS, MCITP Principal Consultant, Pcubed Agenda Reporting with Microsoft Project Views Static Reports Visual

More information

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility

More information

TOWN MANAGER S WEEKLY REPORT

TOWN MANAGER S WEEKLY REPORT TOWN MANAGER S WEEKLY REPORT UPCOMING MEETINGS & EVENTS Planning Commission Meeting: Wednesday, February 15, 6:00 PM, Town Hall 1. Shops of College Park Retail and Hotel 2. VA Clinic Additional Signage

More information

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT: BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: March 13, 2018 # 7 SUBJECT: ELECTION DISTRICT: Contract Award/Roadway and Civil Design

More information

A Positive Impact COVER STORY: WALSH-SHEA CORRIDOR CONSTRUCTORS

A Positive Impact COVER STORY: WALSH-SHEA CORRIDOR CONSTRUCTORS A Positive Impact Job opportunities and open communication with the community are just as important to the Crenshaw/LAX Transit Project in Los Angeles as tunneling and rail placement. BY JIM HARRIS 14

More information

Slide 1. Slide 2. Voisey s Bay Project Update

Slide 1. Slide 2. Voisey s Bay Project Update Slide 1 Slide 2 Voisey s Bay Project Update October 2003 Slide 3 Presentation Overview Project Components Mine and Concentrator Exploration Argentia Hydromet R&D Innovation Centre Expenditure Forecast

More information

Project Overview/Update: Advanced Signal System CBOSS PTC

Project Overview/Update: Advanced Signal System CBOSS PTC Project Overview/Update: Advanced Signal System CBOSS PTC Board of Directors September 5, 2013 CBOSS PTC - What is it? Communications Based Overlay Signal System Positive Train Control Fiber Optic Network

More information

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014 I-20 EAST TEXAS CORRIDOR STUDY TxDOT Planning Conference, Corpus Christi June 4 th, 2014 Table of Contents 1 Introduction 3-5 2 I-20 East Texas Corridor Advisory Committee 6-10 3 Study Schedule 11-12 4

More information

Olmsted Locks & Dam Inland Waterways Users Board

Olmsted Locks & Dam Inland Waterways Users Board Olmsted Locks & Dam Inland Waterways Users Board MR. DAVID DALE, PE, PMP, SES DIRECTOR, Programs Great Lakes & Ohio River Division 14 January 2014 US Army Corps of Engineers BUILDING STRONG Agenda Status

More information

TOWN MANAGER S WEEKLY REPORT

TOWN MANAGER S WEEKLY REPORT TOWN MANAGER S WEEKLY REPORT UPCOMING MEETINGS & EVENTS Town Council Meeting: Wednesday, May 10, 7:00 PM, Regular Meeting, Town Hall Planning Commission: Wednesday, May 17, 6:00 PM, Town Hall 1. Public

More information

Maximizing Asset ROI for Self & Clients in a Public Sector Setting. July 16 th San Diego

Maximizing Asset ROI for Self & Clients in a Public Sector Setting. July 16 th San Diego Maximizing Asset ROI for Self & Clients in a Public Sector Setting July 16 th San Diego State of Washington Population: 7.53 M Area: 71,303 Sq. Miles Population density: 107 population/mi² Puget Sound

More information

Electrification - Infrastructure Construction activities in Segment 2:

Electrification - Infrastructure Construction activities in Segment 2: Peninsula Corridor Electrification Project (PCEP) Q1 Quarterly Update #12 July 1 September 30, 2017 JPB Board Meeting November 2, 2017 Agenda Item # 8a Electrification - Infrastructure Construction activities

More information

SUB-CONTRACTOR PRE-QUALIFICATION FORM

SUB-CONTRACTOR PRE-QUALIFICATION FORM CONTACT INFORMATION Company Contact Person: Title: Street Address: Suite No.: EXPERIENCE City: Zip: 1. Please check the CSI Codes applicable to your business: 02 00 00 Existing Conditions 02 20 00 Assessment

More information

Pennington County Government Justice Center. Schematic Design - October 27, 2015

Pennington County Government Justice Center. Schematic Design - October 27, 2015 Government Schematic Design - October 27, 2015 N Architecture 2 Proposed - Site Plan Proposed Jail / LEC Addition Proposed Addition 3 County Board Room Public Entrance County Attorney Proposed - Ground

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0002, Ashburn Station North Broad Run CRITICAL ACTION DATE: STAFF

More information

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for

More information

Proposed FY 06 Project Development Program and FY 05 Project Development Program Update

Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Washington Metropolitan Area Transit Authority Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Presented to the Board of Directors: P D E C Planning & Development

More information

Metro Transit Police Update

Metro Transit Police Update Metro Transit Police Update John Harrington Chief of Metro Transit Police 1 Metro Transit Police Mission Protecting our community through innovation and problem solving Vision A department that is reflective

More information

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project Welcome Metro North Transmission Project Vancouver Community Information Open House March 9, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

WWW. M WWW. ORTENS EN O S N.CO N M M

WWW. M WWW. ORTENS EN O S N.CO N M M IT IS ALL ABOUT OUR RELATIONSHIPS RENEWABLE ENERGY HEALTHCARE HIGHER EDUCATION FEDERAL GOVERNMENT CIVIC/MUNICIPAL Seattle, WA Portland, OR Denver, CO Minneapolis, MN Madison, WI Iowa City, IA Milwaukee,

More information

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km) nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Welcome Thank you for attending this community engagement on the Trans- Canada Highway 1 West Project, part of the Highway

More information

Los Angeles Metro Upcoming Tunneling Opportunities

Los Angeles Metro Upcoming Tunneling Opportunities Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension Regional Connector Crenshaw/LAX Transit Corridor Los Angeles County Metropolitan Transportation Authority 1 Westside Subway

More information

Trains, Planes and Automobiles: An Infrastructure Discussion

Trains, Planes and Automobiles: An Infrastructure Discussion Trains, Planes and Automobiles: An Infrastructure Discussion Keith Stauber, SIOR, JLL Chris Clemente, Comstock Companies John D. Porcari, Gateway Program Development Corporation Charles Renner, Husch Blackwell

More information

The Maryland Transit Administration. A Plan to Connect Baltimore

The Maryland Transit Administration. A Plan to Connect Baltimore The Maryland Transit Administration A Plan to Connect Baltimore 1 What We ve Heard Over 1,100 stakeholder comments submitted through the Bus Network Improvement Project (BNIP) Six workshops, three pop-up

More information

Town of Georgetown Comprehensive Plan

Town of Georgetown Comprehensive Plan Town of Georgetown Comprehensive Plan Town Council Kick-Off Meeting w/planning Commission August 24, 2016 Meeting Agenda Introductions Scope of Services Schedule Public Outreach Community Survey SWOT Analysis

More information

CONSTRUCTION & DEVELOPMENT MANUAL SUMTER COUNTY, FLORIDA

CONSTRUCTION & DEVELOPMENT MANUAL SUMTER COUNTY, FLORIDA CONSTRUCTION & DEVELOPMENT MANUAL SUMTER COUNTY, FLORIDA Original: June 1, 2004 Revised: May 31, 2005 Revised: August 8, 2006 Revised: September 1, 2006 Revised: August 20, 2007 Revised: November 1, 2011

More information

Corridor Management Committee. January 14, 2016

Corridor Management Committee. January 14, 2016 Corridor Management Committee January 14, 2016 1 Today s Topics 2 Regional METRO System Overview 2016 Project Overview: Key Activities and Milestones Municipal Consent Schedule Design Resolution Schedule

More information

Orange County Public Schools

Orange County Public Schools Engelwood Elementary School Replacement 100 Percent Design Community Meeting May 16, 2016 1 Meeting Agenda May 16, 2016 Welcome School Board Member Daryl Flynn Introductions Project Update - Architect:

More information

Fairfax County Comprehensive Transit Plan and Transit Development Plan

Fairfax County Comprehensive Transit Plan and Transit Development Plan Fairfax County Comprehensive Transit Plan and Transit Development Plan Board Transportation Committee December 1, 2015 Randy White Stuart Boggs Fairfax County County of Fairfax, Virginia Overview Background

More information

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE Town of Putnam Valley, Putnam County February 7, 2018 1 2 MEETING AGENDA Introductions (5 minutes)

More information

Northern Virginia Transportation Authority

Northern Virginia Transportation Authority IV Northern Virginia Transportation Authority March 23, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation 66 Outside the Beltway Project Scope Multimodal improvements to

More information

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION Metropolitan Washington Airports Authority Procurement and Contracts Dept., MA-29 2733 Crystal Drive

More information

Contractor Licensing Offered by Brightwood Career Institute, Harrisburg

Contractor Licensing Offered by Brightwood Career Institute, Harrisburg Minnesota Contractor Licensing Offered by Brightwood Career Institute, Harrisburg Contractor Licensing and EPA Lead-Safe Certification 2017 Course Catalog Trust the industry leader with your Contractor

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION 1 DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0001, Broad Run CRITICAL ACTION DATE: STAFF CONTACTS: APPLICANT:

More information

Dulles Area Transportation Association

Dulles Area Transportation Association Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements

More information

2011 Bond Program South Houston ES Additions & Renovations. September 2013 Report (Financial reporting through August 31, 2013)

2011 Bond Program South Houston ES Additions & Renovations. September 2013 Report (Financial reporting through August 31, 2013) 2011 Bond Program South Houston ES Additions & Renovations Design Development Library Addition 2012 Library Addition August 2013 September 2013 Report (Financial reporting through August 31, 2013) PISD

More information

Grade 4 Mathematics Pacing Guide

Grade 4 Mathematics Pacing Guide Jul 2014 ~ August 2014 ~ Sep 2014 1 2 3 4 5 6 7 8 9 10 11 12 14 15 16 17 Routines 19 Routines 20 Routines BOY 22 BOY 23 24 11 12 14 29 15 30 31 Notes: Found Online @ wwweverydaymathonlinecom 1 More Calendars

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 11, 2016 SUBJECT: Request to ratify advertisement of public hearings by the Planning Commission and the County

More information

CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE Prepared by

CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE Prepared by CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE 2445 Prepared by BC HYDRO AUGUST 2008 Table of Contents Background... 2 Ductbank on South West... 3 Ampacities at Maximum... 3 at Recent Maximum Demands...

More information

Energy Engineering: Tools and Trends

Energy Engineering: Tools and Trends Energy Engineering: Tools and Trends AEE Northeast Ohio Chapter Meeting March 27, 2008 1 Introduction Background and Experience Energy Engineer for Trane 20 years in HVAC Industry Equipment design and

More information

Updates on the ACPA Education and Training Program

Updates on the ACPA Education and Training Program Updates on the ACPA Education and Training Program AASHTO Subcommittee on Materials Meeting Asheville, NC August 5, 2008 Dr. Michael Ayers Director of Highway Pavement Technology E&T Membership 5 Contractor

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: January 18, 2018 # 8 SUBJECT: ELECTION DISTRICT: Response to Board Member Initiative: Traffic Analysis and Safety Study of Waxpool Road

More information

Orange County Public Schools

Orange County Public Schools 100 % Design/Construction Update Community Meeting May 23, 2016 Meeting Agenda May 23, 2016 Introductions Welcome School Board Member Kathleen Kat Butler Gordon Project Update Facilities Meeting Organizer

More information

Contents:

Contents: Contents: Conventional/REO/Short Sale Single Family Sold Sold Properties by Cities - Properties Sold Supply Inventory Median Price Comparison by Year www.swflrealtors.com Page #. Single Family & Condo

More information

Ted C. Jones, PhD Chief Economist

Ted C. Jones, PhD Chief Economist Ted C. Jones, PhD Chief Economist Hurricanes U.S. Jobs Jobs (Millions) Seasonally Adjusted 150 145 140 135 130 1.41% Prior 12 Months 2.05 Million Net New Jobs in Past 12-Months 125 '07 '08 '09 '10 '11

More information

HISTORIC AMERICAN ENGINEERING RECORD INDEX TO PHOTOGRAPHS. BLACK AND WHITE PHOTOGRAPHS OF HElM BRIDGE

HISTORIC AMERICAN ENGINEERING RECORD INDEX TO PHOTOGRAPHS. BLACK AND WHITE PHOTOGRAPHS OF HElM BRIDGE HISTORIC AMERICAN ENGINEERING RECORD Cerritos Channel Port oflong Beach Los Angeles County California BLACK AND WHITE PHOTOGRAPHS OF HElM BRIDGE Photographer: Stephen Schafer, September 2010 CA-HEIM-l

More information

INTRODUCTION TO FCCI. Safe, Productive, Quality Jobs with Pride! Mission Statement

INTRODUCTION TO FCCI. Safe, Productive, Quality Jobs with Pride! Mission Statement INTRODUCTION TO FCCI Mission Statement To continue building and developing a profitable, safety conscious, diversified employee owned construction company, that provides a quality product with pride, improves

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Consideration of a Board Initiated Zoning Concept Plan Amendment for Moorefield Station

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Consideration of a Board Initiated Zoning Concept Plan Amendment for Moorefield Station Date of Meeting: April 4, 2017 # 3 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Consideration of a Board Initiated Zoning Concept

More information

NATIONAL DEMOLITION ASSOCIATION PROJECT PRE-START SURVEY

NATIONAL DEMOLITION ASSOCIATION PROJECT PRE-START SURVEY NATIONAL DEMOLITION ASSOCIATION PROJECT PRE-START SURVEY PROJECT INFORMATION Project Name Project Number Project Location City Legal Description: Plat # State Zip Code County Client Client Address Contact(s)

More information

Reston Town Center North Development. Community Update

Reston Town Center North Development. Community Update Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive

More information

Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE

Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Achieving Compact & Connected Engaging in a regional transit discussion Pursuing a compact

More information

Opportunity Corridor-Section 3 Stakeholders Meeting. The Kokosing DBT

Opportunity Corridor-Section 3 Stakeholders Meeting. The Kokosing DBT Opportunity Corridor-Section 3 Stakeholders Meeting The Kokosing Design-Build Team Leads Kokosing Construction Lead Contractor Michael Baker International Lead Designer Brownstone Grey Diversity, Inclusion

More information

Using SUE to reduce Delays and Disruptions on City of Toronto s Yonge Street Project

Using SUE to reduce Delays and Disruptions on City of Toronto s Yonge Street Project Using SUE to reduce Delays and Disruptions on City of Toronto s Yonge Street Project Authors: Lawrence Arcand, P.Eng Manager, SUE Services Dept., TSH/TBE Subsurface Utility Engineers Luis De Jesus, P.Eng,

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201697 Resolution: Yes No TITLE: MTPD Security Updates PRESENTATION SUMMARY: The Metro Transit

More information

Opening the New Woodrow Wilson Memorial Bridge: Planning & Implementing a Major Traffic Switch

Opening the New Woodrow Wilson Memorial Bridge: Planning & Implementing a Major Traffic Switch Opening the New Memorial : Planning & Implementing a Major Traffic Switch Scott C. Crumley, P.E., P.T.O.E. Manager March 26, 2009 1 Agenda Background The Major Milestone: Opening the New to Traffic Challenges

More information

Community Update. May 31, 2011

Community Update. May 31, 2011 Community Update May 31, 2011 Presented to: Leaside Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009

North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009 North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings December 9 & 10, 2009 1 Welcome & Introductions 2 3 What Are We Doing Here Tonight? Public Hearing for RTD North Metro Corridor

More information

Provo-Orem Bus Rapid Transit

Provo-Orem Bus Rapid Transit Provo-Orem Bus Rapid Transit and Timpanogos Maintenance Facility Expansion Procurements Informational Meeting August 18, 2014 Agenda Topic Presenter Time Introduction of key project personnel Project history

More information

2014 ITS 3C Summit GDOT TMC Reconfiguration

2014 ITS 3C Summit GDOT TMC Reconfiguration 2014 ITS 3C Summit GDOT TMC Reconfiguration September 16, 2014 Project Objectives Accommodate Current & Future Needs Improve Operational Efficiency Enhance GDOT-SRTA Operational Synergy Minimize Construction

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM Port Authority of New York and New Jersey () - Concrete Sea Wall East of Harrison Car Maintenance Facility DBNUM: PA1424 / UPC: 154090 will receive funding to construct a concrete sea wall to protect PATH

More information

SECOND AVENUE SUBWAY PROJECT Managing Construction and its Challenges in One of the Country s Densest Urban Environments

SECOND AVENUE SUBWAY PROJECT Managing Construction and its Challenges in One of the Country s Densest Urban Environments SECOND AVENUE SUBWAY PROJECT Managing Construction and its Challenges in One of the Country s Densest Urban Environments William E. Goodrich, P.E. Senior Vice President/Program Executive MTA CAPITAL CONSTRUCTION

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

($ millions) DRPA Rebuild PATCO Cars

($ millions) DRPA Rebuild PATCO Cars Delaware River Port Authority of Pennsylvania and New Jersey () Rebuild PATCO Cars DBNUM: DR046 This project will provide for the replacement of PATCOʹs existing car fleet, through complete rebuilding

More information

Freedom of Information Act 2000 reference number RFI

Freedom of Information Act 2000 reference number RFI P. Norris By email to: xxxxxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxx.xxm 02 November 2011 Dear P. Norris Freedom of Information Act 2000 reference number RFI20111218 Thank you for your request under the Freedom

More information

Regional Transit System (RTS) BRT Feasibility Study Project Kick-Off. Project Management Team Meeting May 22, 2008

Regional Transit System (RTS) BRT Feasibility Study Project Kick-Off. Project Management Team Meeting May 22, 2008 Regional Transit System (RTS) BRT Feasibility Study Project Kick-Off Project Management Team Meeting May 22, 2008 Agenda Welcome and Introductions National Bus Rapid Transit Institute (NBRTI) Overview

More information

FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT

FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT Jack Strollo, Broker 500 S. Florida Avenue, Suite 420 Lakeland, Florida 33801 O. 863.683.3425 x103 C. 863.640.8238 jstrollo@resbroadway.com FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

ACEC State Markets Conference April 2018

ACEC State Markets Conference April 2018 1 ACEC State Markets Conference April 2018 AGENDA MBTA By The Numbers FY 2019-2023 Capital Investment Plan Update Major Programs Reliability Modernization Expansion FY 2018 Major Program Highlights Red

More information

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Planning, Program Development and Real Estate Committee Item V- B September 11, 2014 Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Washington Metropolitan

More information

Ohio River Tunnel Update. July 11, 2017

Ohio River Tunnel Update. July 11, 2017 Ohio River Tunnel Update July 11, 2017 Agenda Introductions Getting to Know You Project Overview Ohio River Tunnel Projects Project Schedule Cost Estimate Keeping Each Other Informed Feedback Getting to

More information

Real Estate Forecast 2017

Real Estate Forecast 2017 Real Estate Forecast 2017 Twitter @DrTCJ Non-Renewals - Dead on Arrival Mortgage Insurance Deductibility Residential Mortgage Debt Forgiveness Residential Energy Savings Renewables Wind and Solar ObamaCare

More information

North American Portability Management, LLC Transition Oversight Manager. TOEP Webcast November 7, 2017

North American Portability Management, LLC Transition Oversight Manager. TOEP Webcast November 7, 2017 North American Portability Management, LLC Transition Oversight Manager TOEP Webcast November 7, 2017 Welcome to today s webcast Submit Questions for Q&A Webcast Issues Click the Q&A widget at the bottom

More information

Virginia Department of Transportation Hampton Roads Bridge-Tunnel Action Plan Implementing the Independent Review Panel Recommendations

Virginia Department of Transportation Hampton Roads Bridge-Tunnel Action Plan Implementing the Independent Review Panel Recommendations Virginia Department of Transportation Hampton Roads Bridge-Tunnel Action Plan Implementing the Independent Review Panel Recommendations Initial Panel Charge August 2009 To review existing policies and

More information

S-03-SegB: South Federal Way to Fife LRT

S-03-SegB: South Federal Way to Fife LRT Project Number S-03-SegB Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 4.0 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE

More information

6 Version 1.0 (September 20, 2002) 0 days $0 0 days 01 Oct '02 01 Oct ' days $

6 Version 1.0 (September 20, 2002) 0 days $0 0 days 01 Oct '02 01 Oct ' days $ 1 Windstorm Power Ltd. 0 days $0 0 days 01 Oct '02 01 Oct '02 984 days $0 1 2 Canadian Wind Park 0 days $0 0 days 01 Oct '02 01 Oct '02 984 days $0 2 3 (40 Nordex N80 2.5 MW turbines) 0 days $0 0 days

More information

Eastern Midwest Service Center

Eastern Midwest Service Center Eastern Midwest Service Center Robert L. Smith, PE Forensic Civil / Structural Engineer Columbus, Ohio 614-406-6760 robertsmith@uis-usa.com EDUCATION: Franklin University Columbus, OH Masters of Business

More information

Houston Economic Overview Presented by Patrick Jankowski, SVP Research Greater Houston Partnership

Houston Economic Overview Presented by Patrick Jankowski, SVP Research Greater Houston Partnership Houston Economic Overview Presented by Patrick Jankowski, SVP Research Greater Houston Partnership Order of the Day Order of the Day Rig count fell 80% Oil prices dropped 75% Energy layoffs spiked Office

More information

Engineering Department Overview

Engineering Department Overview Engineering Department Overview Engineering Department Organization General Manager of Maintenance and Traffic Scott Kapton (Acting) Chief Engineer Paul Kovacs General Manager of Engineering Po Collins

More information

Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018

Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018 Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps Park Board Committee Meeting Monday, January 15, 2018 Purpose To provide an update on Metro Vancouver s Stanley Park Water

More information

KAUKAUNA TRAINING CENTER N2218 Bodde Rd, Kaukauna, WI

KAUKAUNA TRAINING CENTER N2218 Bodde Rd, Kaukauna, WI May 2018 29 30 1 2 3 4 5 7:00am-3:30pm Rigging Qualification 40hr (4/30-5/4) 6 7 8 9 10 11 12 5:00pm-9:00pm Total Station 16hr (5/7-5/10) 5:00pm-9:00pm Acoustical Ceilings 16hr (5/7-5/10) 7:00am-3:30pm

More information

OVER 30 YEARS OF EXCELLENCE MIDASCO. Building Tomorrow s Transportation Systems Our Direction Your Safety

OVER 30 YEARS OF EXCELLENCE MIDASCO. Building Tomorrow s Transportation Systems Our Direction Your Safety OVER 30 YEARS OF EXCELLENCE MIDASCO Building Tomorrow s Transportation Systems Our Direction Your Safety COMPANY OVERVIEW Year Founded: 1982 (LLC entity established in 2006) Ownership: Wholly owned subsidiary

More information

Christopher P. Hodges, PE, RRC, CFM, LEED AP, IFMA Fellow, FRICS Principal

Christopher P. Hodges, PE, RRC, CFM, LEED AP, IFMA Fellow, FRICS Principal Christopher P. Hodges, PE, RRC, CFM, LEED AP, IFMA Fellow, FRICS Principal Years with FEA: 20 Total Years Experience: 30+ Education: Master of Science, Materials Science & Engineering, Johns Hopkins University

More information

West Seattle and Ballard Link Extensions. Downtown Open House and Neighborhood Forum September 11, 2018

West Seattle and Ballard Link Extensions. Downtown Open House and Neighborhood Forum September 11, 2018 West Seattle and Ballard Link Extensions Downtown Open House and Neighborhood Forum September 11, 2018 Agenda Why we re here today Alternatives development overview What we heard in Level 1 Level 2 alternatives

More information

Getting in Gear with the Service Catalog

Getting in Gear with the Service Catalog Getting in Gear with the Service Catalog How an actionable Service Catalog can drive Service Management adoption, improve Customer Satisfaction and provide a Return On Investment......And do it quickly

More information

Overview September 7, 2017

Overview September 7, 2017 Overview September 7, 2017 Purpose The purpose of this presentation is to provide an overview of the changes to the required deliverables and workflow for developing plans and models for Illinois DOT projects

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of December 12, 2015 DATE: December 1, 2015 SUBJECT: SP-84-U-15-1 USE PERMIT ASSOCIATED WITH A SITE PLAN for a telecommunications facility; located

More information

CIMA Asia. Interactive Timetable Live Online

CIMA Asia. Interactive Timetable Live Online CIMA Asia Interactive Timetable 2017 2018 Live Online Version 1 Information last updated 09 October 2017 Please note: Information and dates in this timetable are subject to change. CIMA Cert BA Course

More information

SANS Vendor Events. SANS offers a variety of events which bring you in touch with the highly qualified SANS community.

SANS Vendor Events. SANS offers a variety of events which bring you in touch with the highly qualified SANS community. SANS Vendor Events SANS offers a variety of events which bring you in touch with the highly qualified SANS community. SANS National Events over 1200 profession IT Security attendees and over 45 SANS classes

More information

HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION. Presentation to ANC 3E April 13, 2017

HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION. Presentation to ANC 3E April 13, 2017 HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION Presentation to ANC 3E April 13, 2017 1 PURPOSE AND NEED We are committed to providing reliable electric service to our customers. As part of this commitment,

More information

TWENTY-SECOND ANNUAL BUSINESS OPPORTUNITY SEMINAR. Construction Session November 15, 2012

TWENTY-SECOND ANNUAL BUSINESS OPPORTUNITY SEMINAR. Construction Session November 15, 2012 TWENTY-SECOND ANNUAL BUSINESS OPPORTUNITY SEMINAR Construction Session November 15, 2012 TWENTY - SECOND ANNUAL BUSINESS OPPORTUNITY SEMINAR Local Disadvantaged Business Enterprise/Disadvantaged Business

More information

New York Building Congress

New York Building Congress New York Building Congress May 24, 2016 John O Grady Senior Vice President, Capital Program Management NYCT Capital Program Proposed Program 2015-2019 Signals & Communication 20% Rolling Stock (Rail &

More information

COUNCIL MEETINGS July 2017 to June 2018

COUNCIL MEETINGS July 2017 to June 2018 COUNCIL MEETINGS Name 03-Jul 24-Jul 07-Aug 21-Aug 04-Sep 18-Sep 02-Oct 23-Oct 06-Nov 20-Nov 04-Dec 18-Dec 22-Jan 05-Feb 19-Feb 05-Mar 19-Mar 09-Apr 23-Apr 07-May 21-May 04-Jun 18-Jun Christie LA Sexton

More information

Configuration Management

Configuration Management American Society for Quality (ASQ) Washington, DC & Maryland Metro Section (509), Software Special Interest Group (SSIG) IEEE Computer Society Washington, DC & Northern Virginia Chapters Society for Software

More information

For personal use only. Update Event & nearmap Solar

For personal use only. Update Event & nearmap Solar Update Event & nearmap Solar Update Event and nearmap Solar Paul Peterson Senior VP Product & Engineering 2 Current Clear Change Current What s on the ground now Clear Unrivalled clarity Change Monitor

More information