1 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM Date of Meeting: May 2, 2017 # I-2 SUBJECT: Quarterly Metrorail Construction Status Report ELECTION DISTRICTS: Ashburn/Broad Run STAFF CONTACTS: Alan Winn, Transportation and Capital Infrastructure Joe Kroboth, III, Transportation and Capital Infrastructure PURPOSE: To provide the Board of Supervisors (Board) with information relating to construction activity occurring on the Metrorail Silver Line Phase 2 Extension Project in the first quarter of calendar year BACKGROUND: The Metropolitan Washington Airports Authority (MWAA), in cooperation with the Washington Metropolitan Area Transit Authority (WMATA), Fairfax and Loudoun Counties is constructing a 23.1 mile extension of WMATA s Metrorail System, known as the Silver Line. The project is being implemented in two distinct phases. Phase 1 extended Metrorail north and west from the East Falls Church station (Orange Line) by adding five new rail stations located in Fairfax County ending at the Reston-Wiehle East Station. Phase 1 opened for revenue service in July Phase 2 adds six Metrorail stations beyond to the Reston-Wiehle East Station three of which are located in Fairfax County: Reston Town Center, Herndon, and Innovation Center; and three of which are located in Loudoun County: Dulles Airport, Loudoun Gateway (Route 606) and Ashburn (Route 772). At this juncture, it is projected that Phase 2 will be open for revenue service in Development of the Metrorail Silver Line Phase 2 Extension project is a significant transportation capital improvement project for Loudoun County and the Washington Metropolitan Region. Civil construction activity for the Silver Line Phase 2 Extension ramped up significantly in 2016 and is expected to be sustained through To this end, staff plans to provide quarterly updates to the Board focusing on the construction activity in Loudoun County for the project for the Board s information and benefit. This update is limited to the Metrorail project and not associated with the adjacent construction capital projects (e.g., Croson Lane, Old Ryan Road to Ashburn Metrorail Station), which are reported to the Finance/Government Operations and Economic Development Committee (FGOEDC) on a quarterly basis.

2 Item I-2, Quarterly Metrorail Construction Status Report Board of Supervisors Business Meeting May 2, 2017 Page 2 The quarterly construction activity update will follow calendar year quarters. The update provided under this staff report covers the January through March 2017 (first quarter for 2017). Phase 2 Project: The Metrorail Silver Line Phase 2 project is the final 11.4 miles of the 23.1 total mile Silver Line Extension. As mentioned, it will operate from the Wiehle-Reston-East station through Dulles International Airport to its permanent terminus at Ashburn Station (formerly known as the Route 772 Station). Phase 2 Major Contracts: Three construction contracts have been awarded and are actively being managed to complete the Phase 2 Metrorail Silver Line Extension. Package A consists of the Metrorail Stations and the main line track system. Package B consists of the Metrorail Maintenance Facility; and Package S entails the removal of soil stockpiled on the Maintenance Yard site that was excess material from the Phase 1 project. Package A Contract: Metrorail Stations and Main Line Tracks: Design-Builder: Capital Rail Constructors Contract Awarded: May 2013 Construction Commenced: July 2013 Original Substantial completion date: July 2018 Adjusted substantial completion date: August 2019 Package B Contract: Maintenance Facility: Design-Builder: Hansel Phelps Contract Awarded: July 2014 Original Substantial completion date: August 2018 Adjusted substantial completion date: May 2019 Package S Contract: Soil Stockpile Removal: Contractor: Atlantic Contracting & Material Co. Contract Awarded: November 2013 Construction Completed: July 2016 Construction management and oversight of the Metrorail Silver Line project is provided by MWAA. Loudoun County staff meet bi-weekly with MWAA staff to address and coordinate issues arising during construction activity. Rail Project status and Construction Activity 1 st Quarter 2017: According to MWAA, the civil construction activities for the Metrorail Extension project have been estimated to be approximately 46 percent complete at the close of the 1 st Quarter of calendar year Construction activities during this quarter are summarized in Table 1.

3 Item I-2, Quarterly Metrorail Construction Status Report Board of Supervisors Business Meeting May 2, 2017 Page 3 Table 1 Summary of Construction Activities Completed by Station Area Loudoun Gateway Station Site grading and preparation Station facility excavation and foundations Station facility cast-in-place and precast concrete structural construction, columns, walls Utility installation Power and communications underground conduits Traction Power Substation excavation and foundations Ashburn Station Site grading and preparation Station facility excavation and foundations Station facility cast-in-place and precast concrete structural construction, columns, walls Pavilion building excavations and foundations (north and south) Storm drainage system Pedestrian Bridge pier foundation and column (south) Utility installation Power and communications underground conduits Traction Power Substation excavation and foundations Project Summary Schedules: Periodically, MWAA provides DTCI staff with an updated summary schedule information for each station and station area. Table 2 summarizes the most recent schedule information for the respective Loudoun County Stations. Table 2 Estimated Completion Date by Work Area Station or Construction Work Area Dulles Airport Station: Dulles Airport Station Dulles Airport Station Pedestrian Tunnel Access Loudoun Gateway Station: Loudoun Gateway Station Loudoun Gateway Station Area and Pavilion Building Ashburn Station: Ashburn Station Ashburn North Station Area and Pavilion Building Ashburn South Station Area and Pavilion Building Estimated Completion Date June 2018 October 2017 October 2018 March 2018 February 2019 June 2018 June 2018

4 Item I-2, Quarterly Metrorail Construction Status Report Board of Supervisors Business Meeting May 2, 2017 Page 4 Staff will provide a presentation including photographs of Phase 2 construction activity (Attachment 1). FISCAL IMPACT: There is no fiscal impact associated with this item. ATTACHMENT: 1. PowerPoint presentation, Metrorail Silver Line Phase 2 Construction Status Report, 1 st Quarter Calendar Year 2017

5 Metrorail Silver Line Phase 2 Construction Status Report 1 st Quarter Calendar Year 2017 Presented to: Loudoun County Board of Supervisors May 2, 2017 ATTACHMENT 1 1

6 Ashburn North Commuter Parking Garage (Comstock Partners): 2

7 Parking Garages: Ashburn South and Loudoun Gateway Commuter Garages: Contract award (FGOEDC), April 18, 2017 Contract award, full Board, May 2, 2017 Recommended DB Team: S.D. Bollard Construction Start construction fall 2017 Completion estimated Summer

8 Silver Line Phase 2 Status: Civil construction activity in Loudoun County ramped up in 2016 and will continue through the end of 2018 Phase 2 Overall Construction is 46% Complete 1 st Qtr Construction Activity in Loudoun County: Ashburn Station and Station Areas Site preparation/grading Utility Installation Storm water conduits and regional pond Conduit Installation Pavilion construction North/South Station Areas Ped bridge foundations drilled and placed Loudoun Gateway and Station Area Site preparation/grading Station Foundations Cast and Pre-cast columns and walls Utility Installation Power and communications conduits Precast textured and brick walls

9 Estimated Completion Civil Construction Ashburn and Loudoun Gateway Stations and Station Areas Project Loudoun Gateway Station Loudoun Gateway Station Area Ashburn Station Ashburn Station Area - North Ashburn Station Area - South Estimated Completion Civil Construction October 2018 March 2018 February 2019 June 2018 June 2018

10 Installing Conduits Under Westbound DIAAH:

11 Hand Mining Through Rock :

12 Guideway Structure Into Dulles Airport Station:

13 Aerial Guideway Entering East Side Dulles Station:

14 Dulles Airport Station:

15 Dulles Airport Station Precast:

16 Dulles Airport Station: 12

17 Form and Install Reinforcing for Aerial Guideway:

18 Inspection Building at Maintenance Yard: 14

19 Water Line Installation Under Storm Drain:

20 Dulles Yard Site Electrical Ductbank:

21 Rebar & Concrete Work-Yard Leads

22 Loudoun Gateway Station, walls and slab: 18

23 Route 606 Bridge Over Greenway Crash Wall: 19

24 Loudoun Gateway Station Foundations:

25 Loudoun Gateway Station

26 Loudoun Gateway: Pre-Cast Components

27 Loudoun Gateway: Precast Platform Walls

28 Ashburn Station North Pavilion Bldg. Wood Forms

29 Ashburn Station South Ped Bridge Footing

30 Questions? 26

31 Metrorail Silver Line, Phase 2: 27

32 Package B Dulles Yard Layout:

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors October 2016 Agenda 1. Safety 2. Schedule

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2017 Agenda 1. Safety 2. Schedule

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM Date of Meeting: # 9 SUBJECT: ELECTION DISTRICTS: STAFF CONTACTS: Public and Private Infrastructure Improvements Adjacent to the Dulles

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2016 Agenda 1. Safety 2. Schedule

More information

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT: BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: March 13, 2018 # 7 SUBJECT: ELECTION DISTRICT: Contract Award/Roadway and Civil Design

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0002, Ashburn Station North Broad Run CRITICAL ACTION DATE: STAFF

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION 1 DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0001, Broad Run CRITICAL ACTION DATE: STAFF CONTACTS: APPLICANT:

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Consideration of a Board Initiated Zoning Concept Plan Amendment for Moorefield Station

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Consideration of a Board Initiated Zoning Concept Plan Amendment for Moorefield Station Date of Meeting: April 4, 2017 # 3 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Consideration of a Board Initiated Zoning Concept

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: January 18, 2018 # 8 SUBJECT: ELECTION DISTRICT: Response to Board Member Initiative: Traffic Analysis and Safety Study of Waxpool Road

More information

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for

More information

Northern Virginia Transportation Authority

Northern Virginia Transportation Authority IV Northern Virginia Transportation Authority March 23, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation 66 Outside the Beltway Project Scope Multimodal improvements to

More information

Proposed FY 06 Project Development Program and FY 05 Project Development Program Update

Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Washington Metropolitan Area Transit Authority Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Presented to the Board of Directors: P D E C Planning & Development

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility

More information

Fairfax County Comprehensive Transit Plan and Transit Development Plan

Fairfax County Comprehensive Transit Plan and Transit Development Plan Fairfax County Comprehensive Transit Plan and Transit Development Plan Board Transportation Committee December 1, 2015 Randy White Stuart Boggs Fairfax County County of Fairfax, Virginia Overview Background

More information

Trains, Planes and Automobiles: An Infrastructure Discussion

Trains, Planes and Automobiles: An Infrastructure Discussion Trains, Planes and Automobiles: An Infrastructure Discussion Keith Stauber, SIOR, JLL Chris Clemente, Comstock Companies John D. Porcari, Gateway Program Development Corporation Charles Renner, Husch Blackwell

More information

Approval of Medical Center New Entrance Agreement

Approval of Medical Center New Entrance Agreement Finance & Administration Committee Action Item III-A February 14, 2013 Approval of Medical Center New Entrance Agreement Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Slide 1. Slide 2. Voisey s Bay Project Update

Slide 1. Slide 2. Voisey s Bay Project Update Slide 1 Slide 2 Voisey s Bay Project Update October 2003 Slide 3 Presentation Overview Project Components Mine and Concentrator Exploration Argentia Hydromet R&D Innovation Centre Expenditure Forecast

More information

2018 State and Federal Legislative Program

2018 State and Federal Legislative Program 2018 State and Federal Legislative Program STATE TRANSPORTATION FUNDING The passage of HB 2313 (2013) was the result of bipartisan cooperation throughout the Commonwealth. The regional funding provided

More information

Transportation Tuesdays Online Sixth in webinar series for transit CEOs & board members on economic sustainability June 19, 2012

Transportation Tuesdays Online Sixth in webinar series for transit CEOs & board members on economic sustainability June 19, 2012 Transportation Tuesdays Online Sixth in webinar series for transit CEOs & board members on economic sustainability June 19, 2012 Innovative Funding and Financing Practices: Naming Rights, Tolls, and Other

More information

Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove

Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove Finance, Administration and Oversight Committee Action Item III-J February 14, 2008 Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove Washington Metropolitan

More information

A Positive Impact COVER STORY: WALSH-SHEA CORRIDOR CONSTRUCTORS

A Positive Impact COVER STORY: WALSH-SHEA CORRIDOR CONSTRUCTORS A Positive Impact Job opportunities and open communication with the community are just as important to the Crenshaw/LAX Transit Project in Los Angeles as tunneling and rail placement. BY JIM HARRIS 14

More information

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014 I-20 EAST TEXAS CORRIDOR STUDY TxDOT Planning Conference, Corpus Christi June 4 th, 2014 Table of Contents 1 Introduction 3-5 2 I-20 East Texas Corridor Advisory Committee 6-10 3 Study Schedule 11-12 4

More information

Dulles Area Transportation Association

Dulles Area Transportation Association Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements

More information

Reston Town Center North Development. Community Update

Reston Town Center North Development. Community Update Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive

More information

Downtown Boise Multimodal Center

Downtown Boise Multimodal Center Treasure Valley High Capacity Transit Study Downtown Boise Multimodal Center Environmental Assessment June 2009 Prepared by the Federal Transit Administration and Valley Regional Transit. U.S. Department

More information

Wireless Network (Neutral Host) Request for Proposals Update

Wireless Network (Neutral Host) Request for Proposals Update Finance, Administration and Oversight Committee Action Item III-B March 13, 2008 Wireless Network (Neutral Host) Request for Proposals Update Washington Metropolitan Area Transportation Authority Board

More information

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS Commonwealth of Virginia Office of Transportation P3 s Dusty Holcombe, Deputy Director DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS September 20, 2011 Virginia: DT / MT

More information

7900 HARKINS ROAD Lanham, MD

7900 HARKINS ROAD Lanham, MD 7900 HARKINS ROAD 7900 HARKINS ROAD This rare offering represents the opportunity to acquire a best-in-class office asset with guaranteed NNN cash flow for 12 years at a significant discount to replacement

More information

The Blue Line Extension

The Blue Line Extension The Blue Line Extension NORTH CAROLINA JOINT TRANSPORTATION OVERSIGHT COMMITTEE Presented by Carolyn Flowers CATS Chief Executive Officer Raleigh, NC February 10, 2012 Overview Charlotte Area Transit System

More information

County of Loudoun. Department of Planning and Zoning MEMORANDUM

County of Loudoun. Department of Planning and Zoning MEMORANDUM County of Loudoun Department of Planning and Zoning MEMORANDUM DATE: June 12, 2015 TO: FROM: Jacqueline Harlow, Project Manager Planner III, Land Use Review Kelly Williams, Planner III Community Planning

More information

Metropolitan Council. Transportation Division Proposed Transit Capital Program

Metropolitan Council. Transportation Division Proposed Transit Capital Program Metropolitan Council Transportation Division Proposed 2015-2020 Transit Capital Program Transportation Committee October 27, 2014 Goals of the 2015 Capital Program Simplify the process Standardize the

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201697 Resolution: Yes No TITLE: MTPD Security Updates PRESENTATION SUMMARY: The Metro Transit

More information

2018 Priorities. Staff Lead Legend: 2 P age DCAO GMDS CAO GMEPW. Mayor and Council

2018 Priorities. Staff Lead Legend: 2 P age DCAO GMDS CAO GMEPW. Mayor and Council Priorities Table of Contents Executive Summary Page 3 Economic Development Page 4 Infrastructure Page 5 Safety and Security Page 6 Service Delivery Page 7 Social and Environmental Page 8 Operational Plan

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

1. Significant Changes

1. Significant Changes Security Upgrades Project (NMSSUP) Phase II, Los Alamos National Laboratory (LANL), Los Alamos, New Mexico Project Data Sheet is for Construction 1. Significant Changes The most recent DOE O 413.3B approved

More information

Los Angeles Metro Upcoming Tunneling Opportunities

Los Angeles Metro Upcoming Tunneling Opportunities Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension Regional Connector Crenshaw/LAX Transit Corridor Los Angeles County Metropolitan Transportation Authority 1 Westside Subway

More information

Contractor Alliancing Sean Mooney Programme Manager

Contractor Alliancing Sean Mooney Programme Manager 1 Contractor Alliancing Sean Mooney Programme Manager Today s Agenda Introduction Background Contractor Alliancing The Process Alliance Electricity Alliance North (EAN) Optimise Water (LLP) JV Benefits

More information

Community Update. May 31, 2011

Community Update. May 31, 2011 Community Update May 31, 2011 Presented to: Leaside Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Report to the Business Administration Committee

Report to the Business Administration Committee Report to the Business Administration Committee Recommendation to Award a Contract to Replace Wi-Fi Infrastructure Systems at Ronald Reagan Washington National Airport and Washington Dulles International

More information

CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT

CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT 35 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net CONSTRUCTION COMMITTEE NOVEMBER 20, 2014 SUBJECT: ACTION: CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT INCREASE

More information

Corridor Management Committee. January 14, 2016

Corridor Management Committee. January 14, 2016 Corridor Management Committee January 14, 2016 1 Today s Topics 2 Regional METRO System Overview 2016 Project Overview: Key Activities and Milestones Municipal Consent Schedule Design Resolution Schedule

More information

Dealing With a Disaster and Its Effect on the Utility Operation

Dealing With a Disaster and Its Effect on the Utility Operation Nashville Electric Service Dealing With a Disaster and Its Effect on the Utility Operation UTA Fall Conference Florence, Alabama October 12-14, 2011 Outline Who We Are Typical Emergency Response Challenges

More information

TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013

TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013 TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013 Introduction The Transport Chapter of the 1818 Society organized a tour of the Washington

More information

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT 16 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 18, 2015 SUBJECT: ACTION: EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF

More information

STUDY REPORT #1 ADDENDUM

STUDY REPORT #1 ADDENDUM STUDY REPORT #1 ADDENDUM 1.0 PURPOSE OF ADDENDUM This document is an addendum to Study Report #1: Sub-System Planning Alternatives. The purpose of this addendum is to bridge the gap between the initial

More information

Community Update. June 8, 2011

Community Update. June 8, 2011 Community Update June 8, 2011 Presented to: Scarborough Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Engineering Department Overview

Engineering Department Overview Engineering Department Overview Engineering Department Organization General Manager of Maintenance and Traffic Scott Kapton (Acting) Chief Engineer Paul Kovacs General Manager of Engineering Po Collins

More information

OVER 30 YEARS OF EXCELLENCE MIDASCO. Building Tomorrow s Transportation Systems Our Direction Your Safety

OVER 30 YEARS OF EXCELLENCE MIDASCO. Building Tomorrow s Transportation Systems Our Direction Your Safety OVER 30 YEARS OF EXCELLENCE MIDASCO Building Tomorrow s Transportation Systems Our Direction Your Safety COMPANY OVERVIEW Year Founded: 1982 (LLC entity established in 2006) Ownership: Wholly owned subsidiary

More information

A greenfield port. New Port Project, Qatar. written by: Martin Ashcroft research by: Jon Bradley

A greenfield port. New Port Project, Qatar. written by: Martin Ashcroft research by: Jon Bradley A greenfield port The New Port Project Steering Committee is tasked with the design and development of a port to meet the requirements of the Qatar National Vision 2030 written by: Martin Ashcroft research

More information

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE Town of Putnam Valley, Putnam County February 7, 2018 1 2 MEETING AGENDA Introductions (5 minutes)

More information

Rosslyn Station New Entrance

Rosslyn Station New Entrance Finance & Administration Committee Action Item III-A February 11, 2010 Rosslyn Station New Entrance Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD

More information

NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD 777 North Capitol Street, N.E. Washington, D.C

NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD 777 North Capitol Street, N.E. Washington, D.C TPB R2-2014 July 17, 2013 NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD 777 North Capitol Street, N.E. Washington, D.C. 20002 RESOLUTION APPROVING THE 2013 CONSTRAINED LONG RANGE TRANSPORTATION

More information

Illinois Tollway Diversity Advisory Council. Gustavo Giraldo, Chief of the Department of Diversity and Strategic Development April 12, 2017

Illinois Tollway Diversity Advisory Council. Gustavo Giraldo, Chief of the Department of Diversity and Strategic Development April 12, 2017 Illinois Tollway Diversity Advisory Council Gustavo Giraldo, Chief of the Department of Diversity and Strategic Development April 12, 2017 Diversity Report recommendations Technical Assistance Program

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary. MEAD Number:

Washington Metropolitan Area Transit Authority Board Action/Information Summary. MEAD Number: Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 102948 Resolution: Yes No TITLE Metro Transit Police Department Third Quarter Security Report

More information

Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing

Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing Customer Services, Operations, and Safety Committee Board Information Item III-B September 24, 2009 Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing Washington Metropolitan Area

More information

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time. TO WHOM IT MAY CONCERN: NOTICE OF RE-SCHEDULED BOARD MEETINGS This is notice that the re-scheduled meetings of the Board of Directors of the New Jersey Transit Corporation, NJ Transit Rail Operations,

More information

A RESOLUTION. WHEREAS, On January 20, 2017, the inauguration of the 47th President of the United States of

A RESOLUTION. WHEREAS, On January 20, 2017, the inauguration of the 47th President of the United States of RESOLUTION 2016-130 APPROVING AN AGREEMENT WITH WASHINGTON METROPOLITAN TRANSIT AUTHORITY TO PROVIDE UP TO TEN POLICE OFFICERS IN SUPPORT OF SECURITY MEASURES FOR THE 2017 PRESIDENTIAL INAUGURATION; AND

More information

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension MOTION NO. M2014-79 Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital

More information

PRIORITIZATION MODEL RESULTS OTHER TRANSPORTATION

PRIORITIZATION MODEL RESULTS OTHER TRANSPORTATION PRIORITIZATION MODEL RESULTS OTHER TRANSPORTATION itization Project itization Rank Name Score 1 Transportation Plan Update 64.85 2 Signal Timing Optimization 54.15 3 Intelligent Transportation System (ITS)

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 16, 2016 SUPPLEMENTAL REPORT

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 16, 2016 SUPPLEMENTAL REPORT ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 16, 2016 SUPPLEMENTAL REPORT DATE: July 14, 2016 SUBJECT: Adoption of the Fiscal Year (FY) 2017-2026 Transit Development Plan (TDP).

More information

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Planning, Program Development and Real Estate Committee Item V- B September 11, 2014 Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Washington Metropolitan

More information

Example. Section: PS 709 Examples of Calculations of Reduced Hours of Work Last Revised: February 2017 Last Reviewed: February 2017 Next Review:

Example. Section: PS 709 Examples of Calculations of Reduced Hours of Work Last Revised: February 2017 Last Reviewed: February 2017 Next Review: Following are three examples of calculations for MCP employees (undefined hours of work) and three examples for MCP office employees. Examples use the data from the table below. For your calculations use

More information

CONSTRUCTION & DEVELOPMENT MANUAL SUMTER COUNTY, FLORIDA

CONSTRUCTION & DEVELOPMENT MANUAL SUMTER COUNTY, FLORIDA CONSTRUCTION & DEVELOPMENT MANUAL SUMTER COUNTY, FLORIDA Original: June 1, 2004 Revised: May 31, 2005 Revised: August 8, 2006 Revised: September 1, 2006 Revised: August 20, 2007 Revised: November 1, 2011

More information

Downtown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary

Downtown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary north, lrt, light, transit, rail, track, line, closure, close, road, interuption, partial, lane, construction, bulletin, NAIT, line, motorist, pedestrian, map, metro, line,downtown to NAIT LRT Concept

More information

State Water Survey Division

State Water Survey Division THE CLIMATE OF ILLINOIS Lying midway between the Continental Divide and the Atlantic Ocean, and 500 miles north of the Gulf of Mexico, Illinois has a climate labeled as continental. Cold winters, and warm,

More information

STAFF REPORT. Meeting Date: To: From: La Cienega Station. Subject: Attachments:

STAFF REPORT. Meeting Date: To: From: La Cienega Station. Subject: Attachments: Ii STAFF REPORT Meeting Date: To: From: Subject: June 20, 2017 Honorable Mayor & City Council Mark Cuneo, City Engineer Robert Welch, Project Manager Metro Purple Line Extension Section 1 Construction

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of September 22, 2018

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of September 22, 2018 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 22, 2018 ATE: September 12, 2018 SUBJECT: Award of Contract ITB-18-273 to Crown Construction Co. for the construction of playground

More information

Project Overview/Update: Advanced Signal System CBOSS PTC

Project Overview/Update: Advanced Signal System CBOSS PTC Project Overview/Update: Advanced Signal System CBOSS PTC Board of Directors September 5, 2013 CBOSS PTC - What is it? Communications Based Overlay Signal System Positive Train Control Fiber Optic Network

More information

Electrification - Infrastructure Construction activities in Segment 2:

Electrification - Infrastructure Construction activities in Segment 2: Peninsula Corridor Electrification Project (PCEP) Q1 Quarterly Update #12 July 1 September 30, 2017 JPB Board Meeting November 2, 2017 Agenda Item # 8a Electrification - Infrastructure Construction activities

More information

CONNECTING AND TRANSFORMING CALIFORNIA. Frank Vacca, Chief of Rail Operations UNLV Symposium October 17, 2018 Las Vegas, Nevada

CONNECTING AND TRANSFORMING CALIFORNIA. Frank Vacca, Chief of Rail Operations UNLV Symposium October 17, 2018 Las Vegas, Nevada CONNECTING AND TRANSFORMING CALIFORNIA Frank Vacca, Chief of Rail Operations UNLV Symposium October 17, 2018 Las Vegas, Nevada CONNECTING CALIFORNIA: Scope of Work Phase I:» 520 Miles» San Francisco to

More information

Creating Dallas-Fort Worth s Transportation System: Celebrating Partnerships and Milestones

Creating Dallas-Fort Worth s Transportation System: Celebrating Partnerships and Milestones Creating Dallas-Fort Worth s Transportation System: Celebrating Partnerships and Milestones Presentation to the Texas Transportation Commission August 27, 2014 Presenters Mike Cantrell Commissioner, Dallas

More information

Public Works 2017 Budget Presentation. Public Works What We Do

Public Works 2017 Budget Presentation. Public Works What We Do Public Works 2017 Budget Presentation Public Works What We Do The Public Works Department interacts with all citizens of the county and our visitors for which our work activities have a direct impact.

More information

New York Building Congress May 24, Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital

New York Building Congress May 24, Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital New York Building Congress May 24, 2016 Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital Construc@on Agenda 1. East Side Access 2. Second Avenue Subway 3. Penn Access 4. Security Projects

More information

Community Update. June 21, 2011

Community Update. June 21, 2011 Community Update June 21, 2011 Presented at Beth Sholom Synagogue Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Metrobus 30s Line Enhancements

Metrobus 30s Line Enhancements Customer Service, Operations and Safety Committee Action Item III-C February 14, 2008 Metrobus 30s Line Enhancements Washington Metropolitan Area Transportation Authority Board Action/Information Summary

More information

Section 4: Citizen s Guide to SDEIS

Section 4: Citizen s Guide to SDEIS Section 4: Citizen s Guide to SDEIS Improving mobility Record Page 40 Easing congestion Strengthening our communities Central Corridor Light Rail Transit Citizens Guide to the Supplemental Draft State

More information

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION Metropolitan Washington Airports Authority Procurement and Contracts Dept., MA-29 2733 Crystal Drive

More information

Planning, Design, CM and Construction Opportunities. UTCA Briefing. August 2016

Planning, Design, CM and Construction Opportunities. UTCA Briefing. August 2016 Planning, Design, CM and Construction Opportunities UTCA Briefing August 2016 1 Opportunities CAPITAL S Strategic investments: State-of-Good-Repair Rolling stock Infrastructure Technology Asset Management

More information

BOARD OF SUPERVISORS 2015 TRANSIT SUMMIT INFORMATION ITEM. New Electronic Payments Program Update

BOARD OF SUPERVISORS 2015 TRANSIT SUMMIT INFORMATION ITEM. New Electronic Payments Program Update BOARD OF SUPERVISORS 2015 TRANSIT SUMMIT INFORMATION ITEM Date of Meeting: May 27, 2015 # 8 SUBJECT: ELECTION DISTRICT: STAFF CONTACTS: New Electronic Payments Program Update Countywide Kathleen Leidich,

More information

Recommendation to Board. Final Action

Recommendation to Board. Final Action MOTION NO. M2017-59 City of Seattle Center City Mobility Plan Agreement MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 05/04/2017 05/25/2017 Recommendation

More information

Palm Beach TPA TAC September 5, 2018

Palm Beach TPA TAC September 5, 2018 Palm Beach TPA TAC September 5, 2018 STEVE ANDERSON, AICP Palm Tran Project Manager ADAMS CONSULTING GROUP TINDALE OLIVER Project Team 1996 Palm Tran 2 1996 County Population: 900,000 people Gas: $0.97

More information

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m. AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting July 9, 2014 Executive Director Approval

More information

Disaster Management Facilities in the Western Cape. JJ Botha; Technical Director AFRICON

Disaster Management Facilities in the Western Cape. JJ Botha; Technical Director AFRICON Disaster Management Facilities in the Western Cape JJ Botha; Technical Director AFRICON Presentation Background The envisaged EMC model for the Province Current Status for: EMC Establishment: Overberg

More information

Virginia Transit Update

Virginia Transit Update Virginia Transit Update Jennifer Mitchell Agency Director Virginia Transit Association May 24, 2017 1 Key Priorities for Statewide Transit Program Funding Safety and State of Good Repair Expansion 2 Funding

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: Security Report - 2nd Quarter 2011 PURPOSE: The Metro Transit Police

More information

AUGUST 14, 2013 FINAL AGENDA PUBLIC COMMENTS ON AGENDA ITEMS AND OTHER MATTERS

AUGUST 14, 2013 FINAL AGENDA PUBLIC COMMENTS ON AGENDA ITEMS AND OTHER MATTERS NEW JERSEY TRANSIT CORPORATION NJ TRANSIT BUS OPERATIONS, INC. NJ TRANSIT RAIL OPERATIONS, INC. NJ TRANSIT MERCER, INC. NJ TRANSIT MORRIS, INC. REGULARLY SCHEDULED BOARD OF DIRECTORS MEETINGS CALL TO ORDER

More information

Bellevue s Traffic Adaptive Signals

Bellevue s Traffic Adaptive Signals What we ll cover Bellevue s Traffic Adaptive Signals SCATS Phase 1 Implementation SCATS Operations Responsiveness New Features Some Initial Results 2011 Program and Beyond Final Thoughts ITE Quad Mtg April

More information

San Antonio TransGuide: TOC Update ITS Texas 2009

San Antonio TransGuide: TOC Update ITS Texas 2009 San Antonio TransGuide: TOC Update ITS Texas 2009 Brian G. Fariello, P.E. Traffic Management Engineer TxDOT- San Antonio bfariel@dot.state.tx.us (210) 731-5247 San Antonio TransGuide Partner Agencies Current

More information

Report to the Business Administration Committee Recommendation to Award a Contract for Datacenter Colocation and Associated Support Services

Report to the Business Administration Committee Recommendation to Award a Contract for Datacenter Colocation and Associated Support Services Report to the Business Administration Committee Recommendation to Award a Contract for Datacenter Colocation and Associated Support Services February 2018 Purpose Staff requests that the Business Administration

More information

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9 THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental

More information

PUBLIC WORKS ORGANIZATIONAL CHART

PUBLIC WORKS ORGANIZATIONAL CHART PUBLIC WORKS ORGANIZATIONAL CHART C-108 Actual 2012-13 Adopted Year-End Estimated 2014-15 2015-16 PROGRAM EXPENSES/REVENUES Salaries & Benefits $ 1,725,030 $ 1,855,980 $ 1,676,130 $ 1,956,510 $ 1,979,470

More information

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9 THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental

More information

TOWN MANAGER S WEEKLY REPORT

TOWN MANAGER S WEEKLY REPORT TOWN MANAGER S WEEKLY REPORT UPCOMING MEETINGS & EVENTS Planning Commission Meeting: Wednesday, February 15, 6:00 PM, Town Hall 1. Shops of College Park Retail and Hotel 2. VA Clinic Additional Signage

More information

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public

More information

Super Storm Sandy Disaster Preparedness and Resilience 2013 Environmental Affairs Conference

Super Storm Sandy Disaster Preparedness and Resilience 2013 Environmental Affairs Conference Super Storm Sandy Disaster Preparedness and Resilience 2013 Environmental Affairs Conference Susanne DesRoches, LEED AP Sustainable Design and Climate Adaptation Manager May 15, 2013 Port Authority Facility

More information

Bill Jackson Asst. Statewide Utility Engineer, Office of Construction MDOT SHA

Bill Jackson Asst. Statewide Utility Engineer, Office of Construction MDOT SHA Jeff Ensor TDD Chief of Staff Director of Project Development & Delivery MDOT MTA Purple Line Judy Freedman Breckon Director of Property Acquisition MDOT MTA Purple Line Brian Horn Purple Line Real Estate

More information

MULTIJURISDICTIONAL TOLLING AND COOPERATION THE 91 EXPRESS LANES EXPANSION. ITS California Annual Meeting October 16, 2014

MULTIJURISDICTIONAL TOLLING AND COOPERATION THE 91 EXPRESS LANES EXPANSION. ITS California Annual Meeting October 16, 2014 MULTIJURISDICTIONAL TOLLING AND COOPERATION THE 91 EXPRESS LANES EXPANSION ITS California Annual Meeting October 16, 2014 91 Project Extends the 91 Express Lanes from the Orange County Line to I 15 in

More information